Old Posted Dec 1, 2024, 2:34 PM
DTcrawler DTcrawler is offline
Registered User
 
Join Date: Feb 2019
Location: Ottawa
Posts: 998
They’re still reporting it as integration with Line 2 instead of Stage 2? Which one is it? I don’t understand what kind of software integration between Lines 1 and 2 (if any) would be necessary.
     
     
  #17762  
Old Posted Dec 1, 2024, 3:43 PM
DTcrawler DTcrawler is offline
Registered User
 
Join Date: Feb 2019
Location: Ottawa
Posts: 998
Looks like regular service has resumed early, as of 10:38 am.
     
     
  #17763  
Old Posted Dec 11, 2024, 1:59 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,663
Ottawa LRT to shut down Saturday for software testing on Stage 2 extension
R1 and shuttle bus service will be provided for transit users on Dec. 14.

Sadeen Mohsen, Special to the Citizen
Published Dec 10, 2024 • Last updated 14 hours ago • 1 minute read


Ottawa’s Line 1 LRT system will be fully shut down for planned testing and service adjustment on Dec. 14.

The closure is required for “system integration testing of train control software” on the Stage 2 O-Train eastern extension, Transit General Manager Renée Amilcar wrote in a memo to the mayor and city councillors on Tuesday.

Amilcar’s memo said the goal was to create “seamless travel on the extended line from Blair Station to Trim Station as part of the O-Train East extension.”

Construction on the 12.5-kilometre Stage 2 eastern extension construction began in 2021. When completed, it will connect Blair Station with five new stations further along in Ottawa’s east end: Montreal; Jeanne d’Arc; Orléans Boulevard; Place d’Orléans; and Trim.

The eastern extension will not be available for service until sometime in 2025.

Meanwhile, the north-south Trillium Line extension is set to open on Jan. 6 — more than two years after its original target date — following months of testing.

“We understand that this service adjustment is disruptive and thank our customers for their ongoing patience,” Amilcar said.

During Saturday’s shutdown of Line 1, also known as the Confederation Line, R1 bus service will operate between Tunney’s Pasture and Blair stations between 6 a.m. and 2 a.m.

In addition, shuttle buses will run between St-Laurent and Cyrville stations in the east end and between Lees Station and Mackenzie King Bridge in central Ottawa, Amilcar’s memo said.

Regular service for Line 1 is planned to resume on Dec. 15, the memo added.

https://ottawacitizen.com/news/local-new...urday-software-testing-stage-2-extension
     
     
  #17764  
Old Posted Dec 11, 2024, 2:41 PM
qprcanada qprcanada is offline
Registered User
 
Join Date: Apr 2018
Posts: 145
Shutting down Line 1 on what is possibly the busiest shopping day of the year seems short sighted.
     
     
  #17765  
Old Posted Dec 11, 2024, 2:43 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,084
Quote:
Originally Posted by qprcanada View Post
Shutting down Line 1 on what is possibly the busiest shopping day of the year seems short sighted.
People should just hop in their cars and drive, obviously.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #17766  
Old Posted Dec 11, 2024, 2:51 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,805
How many dozen more times will we need to shut down Line 1 to accomodate the east extension, then repeat with the west extension shortly afterwards.
     
     
  #17767  
Old Posted Dec 11, 2024, 2:55 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,805
Quote:
Originally Posted by Uhuniau View Post
People should just hop in their cars and drive, obviously.
Indeed, and don't shop downtown. I was planning to shop on Saturday and this definitely affects my plans.
     
     
  #17768  
Old Posted Dec 11, 2024, 2:59 PM
YOWetal YOWetal is offline
Registered User
 
Join Date: Oct 2006
Posts: 7,742
Quote:
Originally Posted by qprcanada View Post
Shutting down Line 1 on what is possibly the busiest shopping day of the year seems short sighted.
With the tax break it might be the busiest day in many years. But who would take transit to go shopping? Certainly not anyone who makes such decisions.
     
     
  #17769  
Old Posted Dec 11, 2024, 11:27 PM
zzptichka zzptichka is offline
Registered User
 
Join Date: Dec 2015
Location: Outaouias
Posts: 2,382
TIL at 6pm trains already run at off-peak schedule with 10 minute headways. Standing room only. What a joke.
__________________
My aerial Ottawa photos on Flickr 📷
     
     
  #17770  
Old Posted Dec 11, 2024, 11:31 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,114
Quote:
Originally Posted by zzptichka View Post
TIL at 6pm trains already run at off-peak schedule with 10 minute headways. Standing room only. What a joke.
6pm has long been the cut-off for "frequent" service. Many "frequent" routes drop from 15 minute headways to 30 minute headways right at 6pm.

Naturally, "New Ways to Bus" isn't going to change that either.
     
     
  #17771  
Old Posted Dec 11, 2024, 11:36 PM
DTcrawler DTcrawler is offline
Registered User
 
Join Date: Feb 2019
Location: Ottawa
Posts: 998
It does seem like activities pertaining to integration between stages 1 and 2 are becoming a regular thing, and will continue to occur until stage 2 is complete. If that's the case, full day weekend closures cannot continue this way. It's unacceptable to keep planning such disruptive closures. It really shows how out of touch OCT are for them to be so trigger happy with full-day weekend closures in favour of using overnight hours to do the work.
     
     
  #17772  
Old Posted Dec 11, 2024, 11:57 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,114
Quote:
Originally Posted by DTcrawler View Post
It does seem like activities pertaining to integration between stages 1 and 2 are becoming a regular thing, and will continue to occur until stage 2 is complete. If that's the case, full day weekend closures cannot continue this way. It's unacceptable to keep planning such disruptive closures. It really shows how out of touch OCT are for them to be so trigger happy with full-day weekend closures in favour of using overnight hours to do the work.
a) overnight hours aren't necessarily long enough to do the work

b) the trains actually need to be running to carry out the work (testing signaling integration), which means all other regular overnight work can't happen

It's not that straightforward to just "do it overnight".
     
     
  #17773  
Old Posted Dec 12, 2024, 2:01 PM
OTownandDown OTownandDown is offline
Registered User
 
Join Date: Jul 2018
Posts: 1,632
LOVE getting in the line to park at Rideau Centre. (The only reason I'd take the train today is to go to the Market and avoid a claustrophobic and expensive visit to the Rideau Centre Overheated Garage). So I guess that's out for this weekend.
     
     
  #17774  
Old Posted Dec 12, 2024, 2:43 PM
qprcanada qprcanada is offline
Registered User
 
Join Date: Apr 2018
Posts: 145
Quote:
Originally Posted by OCCheetos View Post
a) overnight hours aren't necessarily long enough to do the work

b) the trains actually need to be running to carry out the work (testing signaling integration), which means all other regular overnight work can't happen

It's not that straightforward to just "do it overnight".
Then plan to do the work on a Sunday. The least busy day of the week.
     
     
  #17775  
Old Posted Dec 12, 2024, 2:50 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,641
Despite the annoyance, this is super exciting. Is it possible that LRT East rolls out on time??

AND under budget??

With such a long wait for all this work, I think the steady opening of the 3 sections (S, E, W) is going to feel lightning fast compared to the last 5-7 years.

The trains are pretty snazzy and the downtown tunnel is so much better than my recent experiences in Edmonton and Calgary.







Now if only we had a downtown gathering place or facility to really test out this new system...maybe somewhere near the junction of the different lines
     
     
  #17776  
Old Posted Dec 12, 2024, 2:52 PM
hwy418 hwy418 is offline
Registered User
 
Join Date: Jun 2013
Posts: 410
Quote:
Originally Posted by qprcanada View Post
Then plan to do the work on a Sunday. The least busy day of the week.
Exactly! Same for the OR174 work - multiple full closures on Saturday?!? And you never know when those hit unless you're on social media. Sorry but a PVMS sign after Blair warning of the highway closure at Montreal Rd is useless. What a clown show!
     
     
  #17777  
Old Posted Dec 12, 2024, 8:55 PM
DTcrawler DTcrawler is offline
Registered User
 
Join Date: Feb 2019
Location: Ottawa
Posts: 998
Quote:
Originally Posted by OCCheetos View Post
a) overnight hours aren't necessarily long enough to do the work

b) the trains actually need to be running to carry out the work (testing signaling integration), which means all other regular overnight work can't happen

It's not that straightforward to just "do it overnight".
I’m sure there’s a balance to be struck. A planned closure to Line 1 during regular service hours should be treated as a last resort. Given how frequently they’ve been shutting down the line for parts or the entirety of weekends these past few months, it doesn’t feel like the impact on riders is apparent to them. Hell, with the crowding we saw on single-car trains during summer weekends, I’m not sure they even know people use the O-train on weekends.
     
     
  #17778  
Old Posted Dec 13, 2024, 1:19 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,064
Quote:
Originally Posted by hwy418 View Post
Exactly! Same for the OR174 work - multiple full closures on Saturday?!? And you never know when those hit unless you're on social media. Sorry but a PVMS sign after Blair warning of the highway closure at Montreal Rd is useless. What a clown show!
Considering Line 2 has been closed for over 4 years, I won't shed a tear for the occasional weekend closures of the 174, even if they do impact me. Small price to pay.
     
     
  #17779  
Old Posted Dec 14, 2024, 3:07 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
At least misery loves company, and we aren't the only ones with full line shutdowns, although we're the only ones with planned ones.

I think this is the price of ATC. Older signaling systems wouldn't shut down everything everywhere. The benefits of ATC are obvious, but this is a drawback

https://www.blogto.com/city/2024/12/ttc-shuts-down-subway-service-emergency-repairs/
     
     
  #17780  
Old Posted Dec 14, 2024, 6:26 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,805
Without reliable service, ridership will not recover. How many employers will put up with delayed employees repeatedly, after reading the Toronto situation.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 7:37 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.