Finally some proper plans for the expansion of YUL ! A lot to unpack.
See screenshots 2 posts down.
New satellite building pretty much on the current taxiway C (former runway 10/28). This we knew. Phase 1, which is planned to be operational by summer 2028, is for it to accommodate 12 widebodies or 24 narrowbodies for international and domestic flights. Airport capacity will increase to 30 million. Further phases will double those gate numbers, and the passenger capacity will increase from 35 million in 2035 to 45 million in 2048.
A 400m tunnel passing underneath the main apron will connect it to the main terminal building. It will service passengers, the baggage handling system (BHS), and ground service equipment (GSE).
The transborder jetty is getting an extension of 5-6 gates, some of which will cater to widebodies. This is a good idea, as AC uses widebodies on routes to FLL, LAX, SFO.
A lot of new taxiways will also be built in order to accommodate this new setup.
The aeroquai and the domestic jetty will disappear. Good riddance to both ! The main terminal building will fatten up.
Eventually, the deicing facility will need to be moved as well, by the looks of it.
Ooof ! A lot of work. Good luck ADM ! Between this work on the airside, and the work planned in order to expand the road network leading to the terminal + the REM on the landside, YUL will be a construction site for the next 20+ years.....
Maybe I should bid to move to YYC tower. Construction over there is mostly done !