This is such wishful thinking. Vancouver is not tired and old? It is currently what Metrotown, Whatley, etc want to be in 30 years. And left wing? Vancouver is pretty on the right compared to other cities like it, and moreso than most Metro Vancouver councils right now. It has the most YIMBY council too, so while in the past few years it has been outbuilding Surrey in New starts (check CMHC for more info), the Broadway Plan is going to bring Vancouver up from quarter of starts to probably over a third. Vancouver's downtown is expanding beyond the peninsula and there's no sign of it slowing down.
And the idea that Vancouver holds too much power is laughable. Vancouver constantly gets shafted when it comes to infrastructure. South of Fraser gets a bunch of new bridges, highway expansions, and a new Skytrain extension, meanwhile Vancouver can't even get Skytrain to UBC which would have way more ridership. South of Fraser's problems are a result of sprawl because of Vancouver's nimbyism, but the tide on that has completely switched. Watch Vancouver continue to outbuild Surrey in the next decade.
|
Point of note.
The Skytrain extension not going to UBC is not as a consequence of lack of will (political or otherwise) or prioritization, but rather because of logistical issues.
They can't build the Arbutus-UBC leg until the plans for the Jericho lands development are more finalized and concrete (excuse the pun) and the construction has began on at least part of that development that will hold the skytrain station - for coordination and resource-management purposes.
It's not something you can do after the fact or piece-meal.
The Jericho Lands initial proposal wasn't made until some time after the Skytrain extension construction and phasing schedule had already been decided and more or less finalized. And as the city/Translink had a preference for the line to pass through Jericho Lands rather than the original route going south of it, it meant that this phase of the construction could only go as far as Arbutus until the Jericho Lands proposal was much farther along in their development. We currently don't even have anything of that proposal beyond the initial masterplan concept.
At the same time, you can't hold up the completion and opening of the rest of the extension line on the East until the Jericho Lands was ready to go or got built-out because that would likely add another 8-10 years on top of any current completion date (currently scheduled to open in 2027, I believe?)
So would you have preferred us to wait until the mid-to-late 2030's for the Broadway Extension line running all the way to UBC to open? Rather than the current phased schedule that allows them to open the line to Arbutus as soon as in two years time?