1140 Sunningdale Road East - 3.5s townhouses (Under Construction)

A 4 storey mixed use building is being proposed for Sunningdale Rd E.. 42 units plus some commercial space.


https://london.ca/business-developme...nningdale-road




Design brief -



https://london.ca/sites/default/file...20-%20AODA.pdf
Reply With Quote
     
     
  #2  
Old Posted Dec 22, 2021, 9:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Reply With Quote
     
     
  #3  
Old Posted Jan 9, 2024, 12:04 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
The garden centre building is being demolished and site clean-up is now underway. Will the developer start construction of the low rise building soon?
Reply With Quote
     
     
  #4  
Old Posted Jan 9, 2024, 12:32 AM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 855
Looks like this has been switched to a 36-unit stacked townhouse development according to a site-plan application filed back in the summer (available through the city's online permit registry).

If I remember correctly, the main floor commercial space from the original proposal a few years ago was supposed to be for the garden centre. They recently moved to the new plaza at Sunningdale and Richmond a couple months ago.

Also, the developer (according to the project page from the original proposal) is Royal Premier Homes. I have lost track of how many infill proposals they have across the city that they have already received zoning for. It would be nice to see them finally start construction on one of them.
Reply With Quote
     
     
  #5  
Old Posted Feb 29, 2024, 9:19 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Site prep now underway with utilities being installed to serve these future townhouses.
Reply With Quote
     
     
  #6  
Old Posted Jun 1, 2024, 12:35 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
They have made good progress with these townhouses with the basement walls now poured. Should see the framers starting soon.
Reply With Quote
     
     
  #7  
Old Posted Aug 5, 2024, 3:13 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
They have now framed upto the 2nd floor level for the row of townhouses fronting Sunningdale Rd.
Reply With Quote
     
     
  #8  
Old Posted Aug 16, 2024, 3:55 PM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 855
This new townhouse development is being called "Nova"

https://novalondon.ca/


Some renderings:


Looking northwest from Sunningdale Rd:




Looking south:


Last edited by CanadianTalk; Sep 29, 2024 at 11:05 PM. Reason: updated w/ better pictures
Reply With Quote
     
     
  #9  
Old Posted Aug 26, 2024, 7:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Framing the roof joists on this 3.5s unit this week. Should see most of the roof sheeting installed by weeks end.
Reply With Quote
     
     
  #10  
Old Posted Sep 8, 2024, 4:33 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Installing the asphalt shingles on the roof now and also have made good progress installing the window modules.
Reply With Quote
     
     
  #11  
Old Posted Sep 29, 2024, 8:02 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Masonry contractor already making good progress installing the exterior brick.
Reply With Quote
     
     
  #12  
Old Posted Oct 9, 2024, 2:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Looks like the exterior brick work is now complete for the first floor and the exterior siding for the 2nd and 3rd floors has started. Drywall already being delivered to start interior finishing.
Reply With Quote
     
     
  #13  
Old Posted Oct 17, 2024, 6:29 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,399
Concrete curbs are now poured for the driveway and parking lot and grading prepped ahead of paving. Siding install for 2nd and 3rd floor progressing well on the exterior finishing.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 11:15 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.