Quote:
Originally Posted by Pegasus
The line to nowhere . . . Instead of building vanity projects why don't the (useless) council and (even more useless) mayor fix or replace aging infrastructure - such as the crumbling water feeder main!!! (Are the four-car trains still trapped in the depot . . . just asking)?
Also, if a new LRT line is so essential I don't understand why the (existing) 7th Avenue track couldn't be used for the Green Line downtown section - surely the extra trains could be accommodated using advanced signalling. Many major cities around the world function quite well with above-ground trams and LRT.
|
Using the 7th Ave corridor was evaluated in the 2000s.
There is a maximum theoretical capacity of 36 3 car trains per hour entering from the east. The maximum practical capacity is somewhere between 26 trains per hour, and 36, but the number drops slightly as trains are lengthened. I don't think schedules have been able to achieve 30 trains consistently.
At 4 car trains, the combined demand of the North Central, SE, South, and NE lines is 41 trains per hour. SE, South, and NE, is 32 trains per hour.
Easy to see sharing 7th gets maxed out fast. Using 7th necessitates the 8th Ave tunnel earlier, which compared to a 'do nothing' scenario, looks much more expensive.
The evaluation reflects the 'original sin' of the green line. Options are evaluated piecemeal not as a whole, and so, we ended up in this path dependent situation where we are stuck with a project no one is proud of.