Still working on a few sections of the exterior wall cladding. Interior finishing is also making progress. Will likely not be complete by start of Fall term.
Reply With Quote
     
     
  #42  
Old Posted Jul 24, 2024, 2:16 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,167
Some new July 2024 photos of the progress on the exterior cladding for this building. Progress on the interior is also happening fast and they will be touch and go on being able to open this for the start of the Fall term. They also have alot of exterior landscaping and walkways to complete once they complete the exterior finishing.

https://www.haymanconstruction.com/E...reneurship.htm
Reply With Quote
     
     
  #43  
Old Posted Aug 15, 2024, 8:20 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,167
Exterior cladding is nearly complete now with just minor touchups left. Alot of exterior walkways and landscaping is now completed as well. They may be able to do a soft opening of this building on the ground floor levels in time for back to school in Sept.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 4:03 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.