Quote:
Originally Posted by J.OT13
Kind of like how ALT and the Airport needed that extra $13 million on the $55 million budget for the larger footprint and top convention floor?
Because what happened now is that the "bank" (City) rejected the loan so they had to cut the budget down $9.8 million, removing conference space that would have made the project more profitable in the long run.
|
If the convention space would make the project more profitable in the long run then alt should talk to its investors. It sounds more likely the conference floor was an unprofitable add on.