  #361  
Old Posted Jan 14, 2024, 11:24 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,173
BC's peak hourly electrical demand reached an all time high over Friday night at 11,300 MW. That's almost 94% of BC Hydro's nameplate capacity.

Last edited by madog222; Jan 14, 2024 at 11:53 PM.
Reply With Quote
     
     
  #362  
Old Posted Jan 15, 2024, 12:42 AM
Alex Mackinnon's Avatar
Alex Mackinnon Alex Mackinnon is offline
Can I has a tunnel?
 
Join Date: May 2008
Location: East Van
Posts: 2,202
Quote:
Originally Posted by madog222 View Post
BC's peak hourly electrical demand reached an all time high over Friday night at 11,300 MW. That's almost 94% of BC Hydro's nameplate capacity.
Good thing Site C was built, despite there clearly being no demand /s.
__________________
"It's ok, I'm an engineer!" -Famous last words

Last edited by Alex Mackinnon; Jan 15, 2024 at 8:57 AM.
Reply With Quote
     
     
  #363  
Old Posted Jan 15, 2024, 2:27 AM
VancouverOfTheFuture's Avatar
VancouverOfTheFuture VancouverOfTheFuture is offline
Registered User
 
Join Date: Apr 2014
Posts: 3,481
Quote:
Originally Posted by Alex Mackinnon View Post
Good thing Site C was built, despite there clearly being now demand /s.
but i thought site C wasnt needed and was a total waste? i mean even the UN hates us for building it.

good luck to us for trying to electrify our entire heating and transportation sector.
Reply With Quote
     
     
  #364  
Old Posted Jan 15, 2024, 7:31 PM
s211 s211 is offline
Registered User
 
Join Date: Oct 2008
Location: The People's Glorious Republic of ... Sigh...
Posts: 8,512
Quote:
Originally Posted by madog222 View Post
BC's peak hourly electrical demand reached an all time high over Friday night at 11,300 MW. That's almost 94% of BC Hydro's nameplate capacity.
Alberta put out an emergency alert on phones (and presumably broadcast TV) because they were in danger of rolling blackouts.
__________________
If it seems I'm ignoring what you may have written in response to something I have written, it's very likely that you're on my Ignore List. Please do not take it personally.
Reply With Quote
     
     
  #365  
Old Posted Jan 15, 2024, 7:57 PM
whatnext whatnext is online now
Registered User
 
Join Date: Feb 2009
Location: Vancouver
Posts: 27,790
Quote:
Originally Posted by Alex Mackinnon View Post
Good thing Site C was built, despite there clearly being no demand /s.
Site C would have been proposed and designed long before electric cars were a gleam in Elon Musk’s eye. I wonder how B.C. Hydro will be able to handle the load with EVs being the majority of vehicles on the road during a cold snap?

I see Hydro is now defending their importation of 20% of our power this summer by being able to sell power to Alberta, Idaho and Washington over the last week. Did they get lucky or were they actually forecasting such cold temps?

https://biv.com/article/2024/01/rob-shaw-bc-hydros-summertime-power-imports-pay-during-deep-freeze
Reply With Quote
     
     
  #366  
Old Posted Jan 15, 2024, 9:08 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is online now
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,618
Quote:
Originally Posted by whatnext View Post
I see Hydro is now defending their importation of 20% of our power this summer by being able to sell power to Alberta, Idaho and Washington over the last week. Did they get lucky or were they actually forecasting such cold temps?
They were probably hedging their bets so reservoir levels wouldn't get dangerously low.
Reply With Quote
     
     
  #367  
Old Posted Jan 15, 2024, 9:14 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,173
^Also all the run-of-the-river stations would be on minimal or zero production during the summer.
Reply With Quote
     
     
  #368  
Old Posted Jan 15, 2024, 9:33 PM
chowhou's Avatar
chowhou chowhou is online now
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,761
I thought they were worried about snowpack/drought conditions? I didn't even know people were mad about BC Hydro purchasing power.
Reply With Quote
     
     
  #369  
Old Posted Jan 15, 2024, 9:51 PM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,131
Ah, but if we blew sixteen billion bucks on a dam, why do we still need to buy power? /s

Some people need to have "buy low, sell high" explained to them. Most don't care about BC Hydro's purchases at all.
Reply With Quote
     
     
  #370  
Old Posted Jan 15, 2024, 9:53 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is online now
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,618
Quote:
Originally Posted by Migrant_Coconut View Post
Ah, but if we blew sixteen billion bucks on a dam, why do we still need to buy power? /s

Some people need to have "buy low, sell high" explained to them. Most don't care about BC Hydro's purchases at all.
Well BCH used to be a net exporter up until about 5 years ago, now we are a net importer. That's a pretty significant change, and we don't have unlimited interconnects with neighboring utilities and we shouldn't assume they have unlimited cheap power to supply us either.
Reply With Quote
     
     
  #371  
Old Posted Jan 15, 2024, 11:58 PM
libtard's Avatar
libtard libtard is offline
Dahvie Fan
 
Join Date: Aug 2012
Posts: 1,310
We buy power when it’s beneficial to us. Low price and keep our water stored
Reply With Quote
     
     
  #372  
Old Posted Jan 16, 2024, 1:16 AM
whatnext whatnext is online now
Registered User
 
Join Date: Feb 2009
Location: Vancouver
Posts: 27,790
Quote:
Originally Posted by chowhou View Post
I thought they were worried about snowpack/drought conditions? I didn't even know people were mad about BC Hydro purchasing power.
Given that our “clean hydro power” is frequently used a reason to invest in B.C. or to encourage quick adoption of EVs I bet it comes as a shock to many British Columbians that one fifth of our power was purchased from outside the province, possibly from carbon intensive production.
Reply With Quote
     
     
  #373  
Old Posted Jan 16, 2024, 1:47 AM
chowhou's Avatar
chowhou chowhou is online now
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,761
Quote:
Originally Posted by whatnext View Post
Given that our “clean hydro power” is frequently used a reason to invest in B.C. or to encourage quick adoption of EVs I bet it comes as a shock to many British Columbians that one fifth of our power was purchased from outside the province, possibly from carbon intensive production.
British Columbians also might be shocked to learn that around a tenth of our "domestic" power generation has always happened south of the border in Washington as part of the terms of the Columbia River Treaty (or well since the 60s).
Reply With Quote
     
     
  #374  
Old Posted Jan 16, 2024, 1:54 AM
Metro-One's Avatar
Metro-One Metro-One is offline
Registered User
 
Join Date: Sep 2008
Location: Japan
Posts: 17,961
Quote:
Originally Posted by Migrant_Coconut View Post
Ah, but if we blew sixteen billion bucks on a dam, why do we still need to buy power? /s

Some people need to have "buy low, sell high" explained to them. Most don't care about BC Hydro's purchases at all.
Seeing how it wont be completed until 2025, that might have something to do with it currently?
__________________
Bridging the Gap
Check out my Flickr: https://www.flickr.com/photos/30634635@N03/with/29495547810/ and Youtube channel https://www.youtube.com/channel/UCV0_0h9qKlhxXFxuAey_q6Q
Reply With Quote
     
     
  #375  
Old Posted Jan 16, 2024, 1:59 AM
chowhou's Avatar
chowhou chowhou is online now
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,761
Quote:
Originally Posted by Metro-One View Post
Seeing how it wont be completed until 2025, that might have something to do with it currently?
According to the BiV article, BC Hydro imported 10,000GWh of power last year; Site C is expected to have an annual production of only 4,600GWh, so we're still potentially importing electricity in 2025 after completion.
Reply With Quote
     
     
  #376  
Old Posted Jan 16, 2024, 2:08 AM
whatnext whatnext is online now
Registered User
 
Join Date: Feb 2009
Location: Vancouver
Posts: 27,790
Also worth noting, BC Hydro is planning on decommissioning a natural gas fuelled plant on Vancouver Island that would be able to provide power in a crunch. But I guess they’d rather say they don’t operate any NG fired powerplants while quietly buying power from other sources that do.
Reply With Quote
     
     
  #377  
Old Posted Jan 16, 2024, 2:43 AM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is online now
Registered User
 
Join Date: May 2010
Posts: 4,788
Quote:
Originally Posted by chowhou View Post
According to the BiV article, BC Hydro imported 10,000GWh of power last year; Site C is expected to have an annual production of only 4,600GWh, so we're still potentially importing electricity in 2025 after completion.
Is that net imports? It's my understanding that we tend to import power in the winter when demand in the southern US is down, and export it in the summer when it's up (our power doesn't flow directly to California, but it flows to Washington, while their power flows to Oregon, who in turn provide power to California).

I don't see a problem with seasonal power imbalances flowing back and forth to our neighbors. It's a sensible way to deal with complementary demand requirements on the Left Coast.
Reply With Quote
     
     
  #378  
Old Posted Jan 16, 2024, 2:57 AM
chowhou's Avatar
chowhou chowhou is online now
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,761
Quote:
Originally Posted by aberdeen5698 View Post
Is that net imports? It's my understanding that we tend to import power in the winter when demand in the southern US is down, and export it in the summer when it's up (our power doesn't flow directly to California, but it flows to Washington, while their power flows to Oregon, who in turn provide power to California).

I don't see a problem with seasonal power imbalances flowing back and forth to our neighbors. It's a sensible way to deal with complementary demand requirements on the Left Coast.
It's not entirely clear, but the article seems to heavily imply that it was 10,000 GWh in net imports.

Quote:
BC Hydro faced criticism last year for importing 10,000 gigawatt hours of electricity, roughly one-fifth of the province’s needs. It was a rare move for a corporation that is usually a net exporter of power.
The only issue with seasonal back and forth is that our primary electricity import source is Washington where one sixth of their electricity is still produced by burning fossil fuels. It's not the majority, but it's not something to ignore either.
Reply With Quote
     
     
  #379  
Old Posted Jan 16, 2024, 4:28 AM
libtard's Avatar
libtard libtard is offline
Dahvie Fan
 
Join Date: Aug 2012
Posts: 1,310
Quote:
Originally Posted by aberdeen5698 View Post
Is that net imports? It's my understanding that we tend to import power in the winter when demand in the southern US is down, and export it in the summer when it's up (our power doesn't flow directly to California, but it flows to Washington, while their power flows to Oregon, who in turn provide power to California).

I don't see a problem with seasonal power imbalances flowing back and forth to our neighbors. It's a sensible way to deal with complementary demand requirements on the Left Coast.
BC had a direct DC line to California for exporting
Reply With Quote
     
     
  #380  
Old Posted Jan 16, 2024, 5:09 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,681
Quote:
Originally Posted by libtard View Post
BC had a direct DC line to California for exporting
Here's the international transmission/distribution lines, I guess the one near Selkirk is the one exporting power though.

https://www.bchydro.com/energy-in-bc/ope...%20the,crossing%2C%20at%20Blaine%2C%20WA.

The Alberta interconnections

https://www.bchydro.com/content/dam/BCHy...-system/system_operating_orders/7T17.pdf

Last edited by jollyburger; Jan 16, 2024 at 2:51 PM.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 9:32 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.