  #261  
Old Posted Sep 27, 2023, 2:29 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Received this response from staff:

"The 2017 design is the latest available design drawing for Hamilton LRT. The 2017 design is currently being reviewed and updated to incorporate Complete Streets Guidelines, Vision Zero and the Main Street conversion, along with any other new City policies or guidelines adopted after the project was paused in 2019. We anticipate an updated design will be available to the public in early 2024."

Also with the project office not opening early 2023 as planned, procurement not started, and other worrying factors, it seems major construction may in fact be delayed to 2025.
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3kIXnr9MISIZNGfD4A&s=09
Reply With Quote
     
     
  #262  
Old Posted Sep 27, 2023, 3:18 PM
Corktowner Corktowner is offline
Registered User
 
Join Date: Jan 2020
Posts: 79
I can't help but suspect that major construction isn't going to happen at all. But if it is, then 2025 is probably the absolute earliest it could start given where things are now.
Reply With Quote
     
     
  #263  
Old Posted Sep 27, 2023, 3:21 PM
spaghettisam spaghettisam is offline
Registered User
 
Join Date: Sep 2022
Location: Hamilton
Posts: 54
Starting to agree with the sentiment I won’t see this until my grandchildren are here (I’m a university student btw).
Reply With Quote
     
     
  #264  
Old Posted Sep 27, 2023, 8:22 PM
Allroadsleadtoham Allroadsleadtoham is offline
Registered User
 
Join Date: Sep 2023
Posts: 26
This is sad.
Reply With Quote
     
     
  #265  
Old Posted Sep 27, 2023, 8:34 PM
Allroadsleadtoham Allroadsleadtoham is offline
Registered User
 
Join Date: Sep 2023
Posts: 26
Just listened to the Scott Radley show little segment on the LRT. They’re thinking breaking ground by maybe 2025 and full project line won’t be built due to material, interest rate and labour constraints.
Reply With Quote
     
     
  #266  
Old Posted Sep 27, 2023, 8:53 PM
NortheastWind NortheastWind is offline
Registered User
 
Join Date: Feb 2011
Posts: 639
Quote:
Originally Posted by Allroadsleadtoham View Post
Just listened to the Scott Radley show little segment on the LRT. They’re thinking breaking ground by maybe 2025 and full project line won’t be built due to material, interest rate and labour constraints.
https://globalnews.ca/hamilton/program/scott-radley-show
Reply With Quote
     
     
  #267  
Old Posted Sep 27, 2023, 9:33 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Quote:
Originally Posted by Allroadsleadtoham View Post
Just listened to the Scott Radley show little segment on the LRT. They’re thinking breaking ground by maybe 2025 and full project line won’t be built due to material, interest rate and labour constraints.
I mean, it's fun to speculate, but these guys, nor am I an expert, but I'll be waiting for official information. I don't expect anything short of Queenston Circle, but Eastgate seems likely at this point. We may see it done in phases, like McMaster to Queenston Phase 1, and Queenston to Eastgate as Phase 2.
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3kIXnr9MISIZNGfD4A&s=09
Reply With Quote
     
     
  #268  
Old Posted Sep 27, 2023, 11:58 PM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,884
I’d be extremely surprised if it isn’t the full LRT to Eastgate in one phase at this point. The budget isn’t fixed like the podcast portrays from my understanding - they are building it. That’s how every other Metrolinx transit project has been, no reason to think this one is otherwise.
Reply With Quote
     
     
  #269  
Old Posted Oct 7, 2023, 2:09 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Water infrastructure relocation has started.
Reply With Quote
     
     
  #270  
Old Posted Oct 18, 2023, 7:37 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Apparently they uncovered the old street car rails from the 1800s today at King and Sherman during the water main replacement work. That's pretty cool!
Reply With Quote
     
     
  #271  
Old Posted Oct 18, 2023, 8:32 PM
matt602's Avatar
matt602 matt602 is offline
Hammer'd
 
Join Date: Jan 2006
Location: Hamilton, ON
Posts: 4,785
Wish I could see that. Haven't seen them since there was a small portion of them visbile on James South near the GO station.
__________________
"Above all, Hamilton must learn to think like a city, not a suburban hybrid where residents drive everywhere. What makes Hamilton interesting is the fact it's a city. The sprawl that surrounds it, which can be found all over North America, is running out of time."
Reply With Quote
     
     
  #272  
Old Posted Oct 18, 2023, 9:32 PM
craftbeerdad's Avatar
craftbeerdad craftbeerdad is offline
Registered User
 
Join Date: Sep 2020
Location: LC <|> HMLTN
Posts: 507
Here you go, via the Hamilton LRT IG





Reply With Quote
     
     
  #273  
Old Posted Oct 18, 2023, 9:52 PM
SteelTown's Avatar
SteelTown SteelTown is offline
It's Hammer Time
 
Join Date: Mar 2004
Location: Hamilton
Posts: 20,393
The city literally threw some rocks and poured cement over the rails, instead of removing them.
Reply With Quote
     
     
  #274  
Old Posted Oct 19, 2023, 11:16 AM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,884
To be fair, most cities did. Toronto has dug up old tracks on roads where it abandoned tracks as well.

It’s easy to forget how many cities in Ontario had streetcars back in the day too. Even relatively small places like Woodstock had some kind of streetcar service. There was a streetcar that even went between Brantford and Port Dover!

I’m sure there are old streetcar tracks under layers of asphalt all over the province, to be honest.
Reply With Quote
     
     
  #275  
Old Posted Oct 19, 2023, 12:16 PM
ScreamingViking's Avatar
ScreamingViking ScreamingViking is offline
Ham-burgher
 
Join Date: Jun 2013
Location: Hamilton
Posts: 7,493
I seem to remember old tracks being uncovered somewhere downtown (it may have been King) the last time one of the streets was ripped up for reconstruction... but that would have been a long time ago (early 1990s? I think I was taking the B-Line to Mac and had to make extra commute time before classes to account for delays)

I've been seeing more and more large road cuts along King and Main and even some of the side streets. They do get resurfaced to the level of surrounding pavement, but until then they're quite the shock unless you slow right down. I've wondered if that's related to this early work on water mains.
Reply With Quote
     
     
  #276  
Old Posted Oct 19, 2023, 1:51 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Quote:
Originally Posted by ScreamingViking View Post
I seem to remember old tracks being uncovered somewhere downtown (it may have been King) the last time one of the streets was ripped up for reconstruction... but that would have been a long time ago (early 1990s? I think I was taking the B-Line to Mac and had to make extra commute time before classes to account for delays)

I've been seeing more and more large road cuts along King and Main and even some of the side streets. They do get resurfaced to the level of surrounding pavement, but until then they're quite the shock unless you slow right down. I've wondered if that's related to this early work on water mains.
A lot of those are just proper road patches. We're not accustomed to them in Hamilton because our previous council didn't spend the money to do road patches correctly. When they install the asphalt, they have to put 1 layer down and let it settle over a few days and then come back and do a second layer. During that time there's a huge hole in the road that is typically the depth of a layer of asphalt.
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3kIXnr9MISIZNGfD4A&s=09
Reply With Quote
     
     
  #277  
Old Posted Oct 19, 2023, 4:36 PM
ScreamingViking's Avatar
ScreamingViking ScreamingViking is offline
Ham-burgher
 
Join Date: Jun 2013
Location: Hamilton
Posts: 7,493
Quote:
Originally Posted by TheRitsman View Post
A lot of those are just proper road patches. We're not accustomed to them in Hamilton because our previous council didn't spend the money to do road patches correctly. When they install the asphalt, they have to put 1 layer down and let it settle over a few days and then come back and do a second layer. During that time there's a huge hole in the road that is typically the depth of a layer of asphalt.
There are a couple near me that replaced cuts that were very poorly patched before (e.g., there were a few on Main at the Delta that had been there a long time). But I've noticed more cuts where there were none previously, and no apparent pavement issue I can recall (at least not any worse than average, for our wonderfully smooth roads). I haven't done much driving outside of east-central Hamilton in the past few months though, so my "sample size" is limited.

The city's final patching is definitely better than what has been done by others cutting into the roadways, and before that final layer is put down the edges are painted orange so one knows better they need to slow down. Hopefully it holds up much better during the coming winter and freeze-thaw cycles, but the seams are very even with the existing surface so I imagine they'll be less susceptible to water seeping in.
Reply With Quote
     
     
  #278  
Old Posted Oct 19, 2023, 4:45 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Quote:
Originally Posted by ScreamingViking View Post
There are a couple near me that replaced cuts that were very poorly patched before (e.g., there were a few on Main at the Delta that had been there a long time). But I've noticed more cuts where there were none previously, and no apparent pavement issue I can recall (at least not any worse than average, for our wonderfully smooth roads). I haven't done much driving outside of east-central Hamilton in the past few months though, so my "sample size" is limited.

The city's final patching is definitely better than what has been done by others cutting into the roadways, and before that final layer is put down the edges are painted orange so one knows better they need to slow down. Hopefully it holds up much better during the coming winter and freeze-thaw cycles, but the seams are very even with the existing surface so I imagine they'll be less susceptible to water seeping in.
I think the city's auditing system is a bit of a mess. They do medium quality issues and miss the really bad ones. Something similar happened with the sidewalk replacements in ward 2.

It was my understanding that we were going to start filling gaps with tar glues stuff to seal cracks and reduce freeze/thaw damage, but I have yet to see that. The best place to start would be these patches so that they are kept free of water.
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3kIXnr9MISIZNGfD4A&s=09
Reply With Quote
     
     
  #279  
Old Posted Oct 20, 2023, 11:56 AM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Both AECOM and WSP announced that they have been brought on as Technical Advisors for this project this week. So something appears to be happening behind the scenes lately.
Reply With Quote
     
     
  #280  
Old Posted Oct 20, 2023, 2:57 PM
Beedok Beedok is offline
Exiled Hamiltonian Gal
 
Join Date: Jun 2012
Posts: 6,797
Can we save some money by using those old tracks?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Hamilton > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 8:47 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.