Originally Posted by TonyTone
Any update on the East side of the riverfront? have they started infrastructure yet? it's been delayed for 2 years now
|
Not much new news to report - it was reported that the Riverfront Development Corp. got a lot of federal and state monies for infrastructure projects. And this article says, that the planning of the central green was set to start this year (I am assuming that means this is well underway).
"The corporation has divided the east project into three sections. It’s buying property in all three, but has focused most work on area 1, which hugs the curve of the river.
A $30 million project set to start this year will put in roads, signs, sidewalks and utilities. Moving utilities will be a massive job.
One of the key projects there will be creating a central green for that side. The two-acre park will sit in the middle of development, and the RDC hopes to get started with design this year, which cannot be paid for by DelDOT.
About a dozen investors are interested in helping develop the area, she said."
https://townsquaredelaware.com/development-corp-highlights-riverfront-in-hearing/
Article on the recent bond request - some additional info here:
https://delawarebusinesstimes.com/news/rdc-riverfront-east-bond/
"The RDC hopes to begin construction on Riverfront East in 2023. About 80% of the property in phase one has been bought by the RDC at this point."
State of Delaware 2024 Capital funds/approvals included:
“$24 million for Wilmington area projects, including the Riverfront Development Corporation, Frawley Stadium and various park and neighborhood improvements;…”
https://www.wdel.com/news/del-state-sena...09ed790-15fa-11ee-b318-9f8b1b3caaac.html
-Signed by Governor Carney, June 30. So I think Riverfront Development Corp. got everything they wanted. Hopefully we see new construction soon.