The only reason we're having this discussion is because we decided in 2006 not to double track the Trillium line. A lot of people on this board seem to think this was a great idea, but the inadequate frequency and inability to interline is a direct result of this.
Don't forget that the failure of the 2013 upgrades put the final nail in the coffin of good service on that line.
     
     
  #12362  
Old Posted Sep 17, 2019, 1:56 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,933
Quote:
Originally Posted by bradnixon View Post
This makes no sense. The ridership from RSS will be an order of magnitude higher than ridership to/from the airport. We should be designing our transit system for ridership, not as a vanity project.
I don't know if what I picture is coming across properly. If interlined, then both sets of trains, those going to Riverside South and those going to airport, would operate as all-stop from South Keys to Bayview. This would mean substantially more capacity and higher frequencies on that portion. While also meaning no need to change at South Keys. Just pick the train heading to the airport.

Quote:
Originally Posted by bradnixon View Post
The only reason we're having this discussion is because we decided in 2006 not to double track the Trillium line. A lot of people on this board seem to think this was a great idea, but the inadequate frequency and inability to interline is a direct result of this.
I would rather they have twin tracked. But the power that be decided extending service was more important. And I do believe a huge part of that is because they feel they owe Riverside South something after cancelling the original LRT plan. This is why I say that plan and the burb is still screwing us over....
     
     
  #12363  
Old Posted Sep 17, 2019, 2:02 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,842
Quote:
Originally Posted by bradnixon View Post
This makes no sense. The ridership from RSS will be an order of magnitude higher than ridership to/from the airport. We should be designing our transit system for ridership, not as a vanity project.

The only reason we're having this discussion is because we decided in 2006 not to double track the Trillium line. A lot of people on this board seem to think this was a great idea, but the inadequate frequency and inability to interline is a direct result of this.
I don't think there is a strong objection to double tracking the Trillium Line. I think the failure of the 2006 project had a lot more to do with the other aspects of the project (the Albert/Slater mess and the long extension into low population/low density neighbourhoods in the south end).

I would certainly prioritize o-train double tracking over the Trim road extension.
     
     
  #12364  
Old Posted Sep 17, 2019, 2:11 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
The temporary parallel bus service may have been a mistake. It means the outbound bus transfers at Tunney's/Blair/Hurdman aren't working correctly because buses can't get there on time.

They should at least move the outbound PM Connexion routes to the LRT termini ASAP.
     
     
  #12365  
Old Posted Sep 17, 2019, 2:45 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,933
Quote:
Originally Posted by CityTech View Post
The temporary parallel bus service may have been a mistake.
Agreed. It's starting to look like the better course of action would have been to simply rip the band-aid off and force conversion on Monday.
     
     
  #12366  
Old Posted Sep 17, 2019, 3:05 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Good Day. Impression of St. Laurent.

Not bad, but not best. They can improve it.

The ceiling, and the HVAC/plumbing enclosures off the ceiling, has the air of unfinished / still exposed.

The trains on the station west side curve have some squeal as entering / exiting, but nothing extraordinary - probably thanks to the low speed.
The overall volume is like any other Metro, except that if they finished the ceiling in acoustic tiles, it would reduce overall noise well.

The handicapped door big metal button / plate on the right as exiting to the lower mall is either completely broken, or at the least off its internal mount - it's just hanging there.

Also at lower mall level, the center single door, and the next-to-the-right-as-exiting door of the pair, are locked. If broken, there should be a sign stuck on them.
Elsewise, == I Really Hate for-no-good-reason Locked Doors ! == ATT: OC-Transpo - UNLOCK THE DOORS !

I will be testing the AM rush-hour loading and ride soon.
Until then, - EnJoy!
     
     
  #12367  
Old Posted Sep 17, 2019, 3:40 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,799
Quote:
Originally Posted by acottawa View Post
I don't think there is a strong objection to double tracking the Trillium Line. I think the failure of the 2006 project had a lot more to do with the other aspects of the project (the Albert/Slater mess and the long extension into low population/low density neighbourhoods in the south end).

I would certainly prioritize o-train double tracking over the Trim road extension.
In hindsight the best approach would have been the "Alex Munter plan": truncate it to LeBreton and figure out the downtown solution, which hopefully would have led us to the tunnel that we have today.
     
     
  #12368  
Old Posted Sep 17, 2019, 3:46 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,799
Quote:
Originally Posted by Truenorth00 View Post
I don't know if what I picture is coming across properly. If interlined, then both sets of trains, those going to Riverside South and those going to airport, would operate as all-stop from South Keys to Bayview. This would mean substantially more capacity and higher frequencies on that portion. While also meaning no need to change at South Keys. Just pick the train heading to the airport.
Interlining would halve frequency to the south, which is where the vast majority of the ridership will be coming from. Unless the line is twin tracked north of South Keys, that would means trains from the south would only be every 24 minutes. That would not provide enough capacity.

Quote:
I would rather they have twin tracked. But the power that be decided extending service was more important. And I do believe a huge part of that is because they feel they owe Riverside South something after cancelling the original LRT plan. This is why I say that plan and the burb is still screwing us over....
There are real congestion issues in the south end. That is what the LRT is being built for; not because people are "owed" anything.
     
     
  #12369  
Old Posted Sep 17, 2019, 4:20 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,045
Quote:
Originally Posted by Truenorth00 View Post
Great article recapping some of the history and advocacy.

I remember the end part of the last decade. And I completely forgot about Friends of the O-Train and their push against the combined Transitway/LRT plan that was part of the old LRT plan. The Confederation Line is fantastic today in part because of the advocacy of folks like this and David Jeanes.
Yeah, that's a good re-cap. Thanks for re-upping; had it in my to-read tabs last night then I conked out!
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #12370  
Old Posted Sep 17, 2019, 4:21 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,045
Quote:
Originally Posted by kmcamp View Post
Everyone is focused on this, but more important is that the 3 week parallel bus service had an unintended side effect. It means the buses that should be there to pickup passengers at Blair and Tunney's are still stuck downtown.
I really think they should call an early end to parallel service unless there's some union agreement that binds them to it or some such.

We need to reallocate bus resources, and ruthlessly, and soon.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #12371  
Old Posted Sep 17, 2019, 4:26 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,818
Best for Trillium would have been to double track to South Keys, at the very least, and possibly electrify to have Line 1 type vehicles (but with 45 meter platforms). I would also have built a single track extension o the airport which is important to be competitive with other bug cities. Riverside South would be pushed to Stage 3. Do it right, not fast.
     
     
  #12372  
Old Posted Sep 17, 2019, 4:26 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,045
Quote:
Originally Posted by Prometheus188 View Post
We don't have that system yet. because the 3 week parallel bus service is in effect. Buses still get delayed through downtown. They don't start/end at Blair, so the reliability isn't there yet. You're judging a temporary situation based on the old bus network. Wait until October 6th, and if it's still a shitshow after the new bus network comes into effect, then you're right. But we're not there yet. We haven't fully switched over to LRT yet. Not until the bus network that revolves around LRT comes into effect.
It's already clear that waiting and walking space at the transfer stations is inadequate and has design flaws at peak. Some of that will be mitigated (other than at Hurdman) with Phase II, but I think an interim solution is gonna have to be come up with, and soon: we can't wait until Tunney's and Blair become pass-through stations rather than termini.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #12373  
Old Posted Sep 17, 2019, 4:29 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,045
Quote:
Originally Posted by mykl View Post
Blair is the least intuitive station, and has the worst wayfinding. I went to the wrong spot twice. I was assuming that you could still go down the stairs and then across the bus area, and up a couple steps on the other side near the Gloucester Centre. But you HAVE TO climb all the way up just to come all the way back down. And the only staircase is at the very end of the platform which is different from the rest of the stations. The station either needed some escalators, or to allow the old way of crossing the road, or more of a rebuild to reduce unnecessary time waste for anyone trying to get to the Gloucester Centre.
I also love how after all the promises to the maligned east side of town about how things were going to be so great post-LRT, even if the closest stations are two or three km away, that the urban local routes (9 and 12) were given the worst boarding platforms at Hurdman and Blair. The suburban routes were given the prime spots.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #12374  
Old Posted Sep 17, 2019, 4:34 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,045
Quote:
Originally Posted by PHrenetic View Post
The overall volume is like any other Metro, except that if they finished the ceiling in acoustic tiles, it would reduce overall noise well.
Yeah, have noticed that St Laurent is waaay louder than the downtown subway stations. Some tinkering with the acoustics is probably in order.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #12375  
Old Posted Sep 17, 2019, 4:44 PM
Gat-Train Gat-Train is offline
BANNED
 
Join Date: Nov 2018
Posts: 508
Quote:
Originally Posted by Uhuniau View Post
I also love how after all the promises to the maligned east side of town about how things were going to be so great post-LRT, even if the closest stations are two or three km away, that the urban local routes (9 and 12) were given the worst boarding platforms at Hurdman and Blair. The suburban routes were given the prime spots.
That kinda makes sense though. If your commute is longer, your transfer should shorter
     
     
  #12376  
Old Posted Sep 17, 2019, 5:15 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,933
Quote:
Originally Posted by Gat-Train View Post
That kinda makes sense though. If your commute is longer, your transfer should shorter
Disagree. The busiest routes should be closest to the stairs. So that they clear out quickly. This is sort of how it's done in Toronto at least.
     
     
  #12377  
Old Posted Sep 17, 2019, 5:16 PM
Capital Shaun Capital Shaun is offline
Registered User
 
Join Date: May 2012
Location: Ottawa
Posts: 862
Quote:
Originally Posted by Gat-Train View Post
That kinda makes sense though. If your commute is longer, your transfer should shorter
Sure, there's more stairs to take to get to the platform with the 12 at Blair but it kinda makes sense why it's on that platform for now. It's also outside the fare paid zone. A minor inconvenience. The Connexion routes are on the eastbound platform because they all go east onto the 174 or down Blair rd towards Innes. The 12 goes west towards City Park drive. I suspect the layout is temporary as a good chunk of the Connexion routes won't go to Blair after Phase 2 is open. There should be room to move ALL remaining routes onto the fare paid zone platform then.
     
     
  #12378  
Old Posted Sep 17, 2019, 5:20 PM
Aylmer's Avatar
Aylmer Aylmer is offline
Still optimistic
 
Join Date: Nov 2007
Location: Montreal (C-D-N) / Ottawa (Aylmer)
Posts: 5,407
Quote:
Originally Posted by Gat-Train View Post
That kinda makes sense though. If your commute is longer, your transfer should shorter
I would think the opposite should be true. An extra 2 minutes' walk on a 60-minute commute is only an extra 3%. But it's 10% of a 20-minute ride. Short, frequent lines should get the prime spots since the rides they permit are the most sensitive to transfer delays.
__________________
I've always struggled with reality. And I'm pleased to say that I won.
     
     
  #12379  
Old Posted Sep 17, 2019, 5:43 PM
RomanR27 RomanR27 is online now
Registered User
 
Join Date: Apr 2016
Posts: 1,972
Quote:
The Eastbound platform at St-Laurent station is closed. O-Train Line 1 is currently not operating between Cyrville and Blair.
https://twitter.com/OC_Transpo/status/1174012766602108928
     
     
  #12380  
Old Posted Sep 17, 2019, 6:13 PM
zzptichka zzptichka is online now
Registered User
 
Join Date: Dec 2015
Location: Outaouias
Posts: 2,366
And before that there was that:
Quote:
CBC Ottawa
@CBCOttawa
·
56m
HEADS UP: Passengers are reporting the Confederation Line train has been stuck at
@uOttawa
for the past 15 minutes due to a door issue.

#OttawaLRT #ottnews #Ottawa
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 10:54 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.