Quote:
Originally Posted by FFX-ME View Post
The trains are slowing down at the passing tracks which are located at the proposed Gladstone and Walkley stations. Why not just have them stop fully and unload/pickup passengers. That would help remedy some of the issues with the lack of double-tracking since they'd have to stop anyways. How much would it cost to add platforms there. Heck, we might was well just get together, go to Home Depot, buy some wood and build it ourselves! Adding 2 platforms shouldn't cost near 1 Million dollars, just do it.

So do you guys have plans for the weekend? Want to build those LRT stations?
In the EA for the Stage 2 extension there are plans to add stations at Gladstone and Walkley at the same time.

Gladstone is planned to be double tracked. Walkley is not, because the underpass structure is not wide enough to accommodate 2 tracks and there's not enough money to widen it.

Refer to here:
http://www.stage2lrt.ca/wp-content/uploa...illium_Line_Functional_Design_Report.pdf


I suppose that if the station was positioned far enough north or south of Walkley that the single track could split before/after the underpass it would work, but then the platform would probably be too far away from Walkley.
Reply With Quote
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 10:33 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.