As part of the university’s commitment to keeping students, staff, and community members informed, this notice is to advise you of site preparation work for the proposed St. Joseph's College Women's Residence.
From now to mid-December, you can expect the following:
November 12 - 15:
Project site safety fencing with accompanied restricted and modified site access for both vehicular and pedestrian traffic.
Placement of site trailers and equipment.
Site survey.
November 18 - December 6:
Site preparation, including the removal and relocation of trees and concrete walks.
December 9 - December 20:
Installation of underground utilities.
Geotechnical survey and drilling for soil samples.
Construction noise
Contractors are expected to adhere to the City of Edmonton’s noise bylaws, which state that construction activity can take place between 7 a.m. and 10 p.m. Monday to Saturday; and between 9 a.m. and 7 p.m., on Sundays and Statutory holidays. On the rare occasion that construction goes later than the stated times, notification will be shared as soon as possible.
Your patience during this project is appreciated.