Posted Jun 28, 2009, 8:33 PM
|
|
Registered User
|
|
Join Date: Dec 2007
Posts: 306
|
|
as for the Austonian topping out. I believe the next 6 floors will take around 2 months. Then the crown another 2 weeks so that will be around sept 1 to 8 or so. Anyone agree. Unless the extreme heat is slowing progress as seen on the completion of floor 50 and 51. Then a much cooler July could help. As the forcasts go long term it looks like July will be more average before August heats up again.
|