Line 1 eastern extension delayed, trials expected in spring
Current shortage of train cars isn't helping, Ottawa's transit committee told
CBC News
Posted: Feb 12, 2026 2:40 PM EST | Last Updated: 34 minutes ago
Transit riders in Ottawa's east end will have to wait a little longer for OC Transpo's Line 1 LRT extension.
The 12.5-kilometre extension will add five stops from Blair station all the way to Trim Road in Orléans.
On Thursday, councillors on the city's transit committee heard trial running on the extension won't start until April at the earliest, or as late as June.
That's later than previously hoped. Last November, OC Transpo said opening the extension by early 2026 was "definitely achievable."
Beacon Hill-Cyrville Coun. Tim Tierney called the latest delay "a major blow" for east end residents.
"We have to have a more honest discussion about the realistic timelines," he said. "I'd be shocked if it's done in the next year. And that's just reality."
OC Transpo officials said Thursday the project is currently in the "substantial completion" phase — the second of five stages leading to its launch.
Staff say at least 46 train cars are required for the next phase, trial running, which will simulate real service.
But since a new problem with their wheel assemblies was discovered last month, many of those Line 1 cars have been pulled from service. On Thursday, only 21 cars were available — five short of the 26 needed during peak hours.
Troy Charter, Ottawa's interim general manager of transit services, said that shortage has limited OC Transpo's opportunities to "practise" on the eastern extension.
Staff have promised to provide another update before trial running commences.