HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation


Reply

 
Thread Tools Display Modes
     
     
  #1521  
Old Posted Jan 18, 2026, 9:42 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,631
Quote:
Originally Posted by AuxTown View Post
What is the delay here??? The many return to work mandates for downtown workers has resulted in terrible traffic coming in from the east (luckily I come from the west). This would be a perfect time to roll out our shiny new trains from the far depths of Orleans right downtown but it's radio silence regarding a testing schedule :-(
In my experience, the West is FAR worse than the East.
Reply With Quote
     
     
  #1522  
Old Posted Jan 19, 2026, 12:21 PM
Truenorth00 Truenorth00 is online now
Registered User
 
Join Date: May 2017
Posts: 28,370
Quote:
Originally Posted by AuxTown View Post
What is the delay here??? The many return to work mandates for downtown workers has resulted in terrible traffic coming in from the east (luckily I come from the west). This would be a perfect time to roll out our shiny new trains from the far depths of Orleans right downtown but it's radio silence regarding a testing schedule :-(
Quote:
Originally Posted by pattherat View Post
And also zero detail on the deficiencies they said remained to be addressed. WHy not provide those details to the public? It’s what, over a month now since they said that? The line and stations have looked pretty sparse of workers every time I drive through there.
They have a bad habit of being less than transparent. I personally don't think they'll even achieve substantial completion and start testing in Q1. And testing always goes better in warmer weather. Maybe they'll try to have it in service by Canada Day. But I would guess more like Labour Day.
Reply With Quote
     
     
  #1523  
Old Posted Jan 19, 2026, 1:29 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,631
Sutcliffe somehow managed to be far less than transparent than the already opaque Watson years.
Reply With Quote
     
     
  #1524  
Old Posted Feb 9, 2026, 1:47 PM
sseguin sseguin is offline
Registered User
 
Join Date: Aug 2018
Posts: 287
Stage 2 East is coming fast! Rail Fans Canada’s latest February 2026 update covers Ottawa’s O-Train Eastern Extension (Trim ➝ Blair) with station progress, trackwork, and what’s next as trial running approaches.

Watch here:

Video Link
__________________
Rail Fans Canada - https://www.RailFans.ca
Reply With Quote
     
     
  #1525  
Old Posted Feb 9, 2026, 8:22 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,631
Let's hope it opens by September at the very least.
Reply With Quote
     
     
  #1526  
Old Posted Feb 9, 2026, 9:12 PM
FrostyMug FrostyMug is offline
Registered User
 
Join Date: Jul 2023
Location: Ottawa
Posts: 82
Quote:
Originally Posted by J.OT13 View Post
Let's hope it opens by September at the very least.
I have to believe that the current issue with the number of units out of service has delayed testing on the extension. You'd think with past challenges that have surfaced during winter months that this would've been a high priority yet nothing is happening and nothing is being said about when testing might start.

I'd like to see it operational much sooner than September.
Reply With Quote
     
     
  #1527  
Old Posted Feb 9, 2026, 9:14 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,631
Quote:
Originally Posted by FrostyMug View Post
I have to believe that the current issue with the number of units out of service has delayed testing on the extension. You'd think with past challenges that have surfaced during winter months that this would've been a high priority yet nothing is happening and nothing is being said about when testing might start.

I'd like to see it operational much sooner than September.
So would I, but September seems somewhat realistic considering the current issues.
Reply With Quote
     
     
  #1528  
Old Posted Feb 10, 2026, 5:52 PM
Richard Eade Richard Eade is offline
Registered User
 
Join Date: Mar 2008
Location: Nepean
Posts: 2,445
The fact that there have been so few trains running along the new eastern track (Have there even been any, recently?) convinces me that there are deficiencies that need correcting. And that the work to fix them likely can’t be done in the cold of winter. If these were only station issues, then the trains would have still been able to run their tests.

This is not an issue of not having vehicles because of the Cartridge Bearing Assembly problem. This has been evident since before the spalling was discovered. Besides, many of the pulled vehicles are likely still close to the 100,000 km limit. RTM and Alstom insist that the vehicles are still safe. If it is just for testing the tracks, some of the ‘marginal’ vehicles could be used – since they are not in revenue service. If there is a great worry about the operators, bypass the requirement for pressing the ‘dead-man’ switch and run them autonomously – which those vehicles are capable of.

The serious deficiency that is keeping test-trains off that section of track must be either a track, signaling, catenary, or power supply problem.

If it is power, then that could be remedied during the winter. A catenary problem could be corrected during the winter. Signaling can be worked on during the winter. The majority of track is fairly straight and laid on the ground, and could be reset during the winter. This leaves me thinking that there is a concern about the fly-over structure. Concrete work is one of the few things that would need warmer weather to do.

We are not seeing much work happening, to get train movements on the east extension up and running – and it seems that that has been the case for a while now. To me, this points to a problem with something structural – likely the fly-over. I hope that I’m wrong, as that could require serious time and disruption to remedy.
Reply With Quote
     
     
  #1529  
Old Posted Feb 10, 2026, 6:58 PM
Edison53 Edison53 is offline
Registered User
 
Join Date: Aug 2025
Posts: 5
Occasionally drive the 174, sometimes as far as Tenth Line, and have yet to see any serious work (ie number of people) working on *anything* related to the east extension. I think we all deserve a clear explanation of what’s causing the delay (and it isn’t the current Alstom issues, as the delay pre-dates that).
Reply With Quote
     
     
  #1530  
Old Posted Feb 10, 2026, 7:23 PM
skyscraperaccount skyscraperaccount is online now
Registered User
 
Join Date: Jun 2023
Posts: 223
Quote:
Originally Posted by J.OT13 View Post
Sutcliffe somehow managed to be far less than transparent than the already opaque Watson years.
Given those that whisper in the ears of both are the same, not surprising.
Reply With Quote
     
     
  #1531  
Old Posted Feb 11, 2026, 7:38 PM
Catenary Catenary is offline
Registered User
 
Join Date: Dec 2012
Posts: 1,386
Quote:
Originally Posted by Richard Eade View Post
The fact that there have been so few trains running along the new eastern track (Have there even been any, recently?) convinces me that there are deficiencies that need correcting. And that the work to fix them likely can’t be done in the cold of winter. If these were only station issues, then the trains would have still been able to run their tests.

This is not an issue of not having vehicles because of the Cartridge Bearing Assembly problem. This has been evident since before the spalling was discovered. Besides, many of the pulled vehicles are likely still close to the 100,000 km limit. RTM and Alstom insist that the vehicles are still safe. If it is just for testing the tracks, some of the ‘marginal’ vehicles could be used – since they are not in revenue service. If there is a great worry about the operators, bypass the requirement for pressing the ‘dead-man’ switch and run them autonomously – which those vehicles are capable of.

The serious deficiency that is keeping test-trains off that section of track must be either a track, signaling, catenary, or power supply problem.

If it is power, then that could be remedied during the winter. A catenary problem could be corrected during the winter. Signaling can be worked on during the winter. The majority of track is fairly straight and laid on the ground, and could be reset during the winter. This leaves me thinking that there is a concern about the fly-over structure. Concrete work is one of the few things that would need warmer weather to do.

We are not seeing much work happening, to get train movements on the east extension up and running – and it seems that that has been the case for a while now. To me, this points to a problem with something structural – likely the fly-over. I hope that I’m wrong, as that could require serious time and disruption to remedy.
I get out to the East end a couple times a week, and passed a train operating last Thursday night. Today, there was an excavator which appeared to be removing snow, I spotted it behind the Costco and then later in the middle of the highway at the bottom of the flyover. A couple weeks back, I would see a train fairly regularly but they seemed to stop when the bearing issue cropped up.

I regularly see vehicles parked outside stations, so there is definitely work ongoing there. If there are station issues, I can see why they aren't wasting vehicle kilometres.
Reply With Quote
     
     
  #1532  
Old Posted Feb 11, 2026, 11:15 PM
Richard Eade Richard Eade is offline
Registered User
 
Join Date: Mar 2008
Location: Nepean
Posts: 2,445
Thanks for the update. Perhaps most track/signaling/train testing is happening at night.

If station issues involve the interface with the trains, then No, they shouldn't waste the kilometres. But otherwise, trains could be tested, while station deficiencies are being worked on. This should be as parallel a process as possible.
Reply With Quote
     
     
  #1533  
Old Posted Feb 12, 2026, 8:16 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,200
Line 1 eastern extension delayed, trials expected in spring
Current shortage of train cars isn't helping, Ottawa's transit committee told

CBC News
Posted: Feb 12, 2026 2:40 PM EST | Last Updated: 34 minutes ago


Transit riders in Ottawa's east end will have to wait a little longer for OC Transpo's Line 1 LRT extension.

The 12.5-kilometre extension will add five stops from Blair station all the way to Trim Road in Orléans.

On Thursday, councillors on the city's transit committee heard trial running on the extension won't start until April at the earliest, or as late as June.

That's later than previously hoped. Last November, OC Transpo said opening the extension by early 2026 was "definitely achievable."

Beacon Hill-Cyrville Coun. Tim Tierney called the latest delay "a major blow" for east end residents.

"We have to have a more honest discussion about the realistic timelines," he said. "I'd be shocked if it's done in the next year. And that's just reality."

OC Transpo officials said Thursday the project is currently in the "substantial completion" phase — the second of five stages leading to its launch.

Staff say at least 46 train cars are required for the next phase, trial running, which will simulate real service.

But since a new problem with their wheel assemblies was discovered last month, many of those Line 1 cars have been pulled from service. On Thursday, only 21 cars were available — five short of the 26 needed during peak hours.

Troy Charter, Ottawa's interim general manager of transit services, said that shortage has limited OC Transpo's opportunities to "practise" on the eastern extension.

Staff have promised to provide another update before trial running commences.

https://www.cbc.ca/news/canada/ottaw...ring-9.7086419
Reply With Quote
     
     
  #1534  
Old Posted Feb 12, 2026, 9:13 PM
skyscraperaccount skyscraperaccount is online now
Registered User
 
Join Date: Jun 2023
Posts: 223
Quote:
Originally Posted by rocketphish View Post
Line 1 eastern extension delayed, trials expected in spring
Current shortage of train cars isn't helping, Ottawa's transit committee told

CBC News
Posted: Feb 12, 2026 2:40 PM EST | Last Updated: 34 minutes ago


Transit riders in Ottawa's east end will have to wait a little longer for OC Transpo's Line 1 LRT extension.

The 12.5-kilometre extension will add five stops from Blair station all the way to Trim Road in Orléans.

On Thursday, councillors on the city's transit committee heard trial running on the extension won't start until April at the earliest, or as late as June.

That's later than previously hoped. Last November, OC Transpo said opening the extension by early 2026 was "definitely achievable."

Beacon Hill-Cyrville Coun. Tim Tierney called the latest delay "a major blow" for east end residents.

"We have to have a more honest discussion about the realistic timelines," he said. "I'd be shocked if it's done in the next year. And that's just reality."

OC Transpo officials said Thursday the project is currently in the "substantial completion" phase — the second of five stages leading to its launch.

Staff say at least 46 train cars are required for the next phase, trial running, which will simulate real service.

But since a new problem with their wheel assemblies was discovered last month, many of those Line 1 cars have been pulled from service. On Thursday, only 21 cars were available — five short of the 26 needed during peak hours.

Troy Charter, Ottawa's interim general manager of transit services, said that shortage has limited OC Transpo's opportunities to "practise" on the eastern extension.

Staff have promised to provide another update before trial running commences.

https://www.cbc.ca/news/canada/ottaw...ring-9.7086419
Its ok guys, Jimmy just texted me on WhatsApp and assures me it'll be on time and on budget.
Reply With Quote
     
     
  #1535  
Old Posted Feb 13, 2026, 4:37 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,631
Wonder if the City will get sued by KEV for delaying the delivery because of train availability.

If anything, KEV should sue RTM and Alstom.
Reply With Quote
     
     
  #1536  
Old Posted Feb 13, 2026, 9:15 PM
OTownandDown OTownandDown is offline
Registered User
 
Join Date: Jul 2018
Posts: 1,592
Wait just so I understand, there's an issue with the trains. There are 21 trains right now available. There are 26 trains needed during peak hours. There are 46 required for the lengthened line. Where are the 25 additional train sets? Are they in the shed? Is there another shed somewhere? Do they just blindly have the same wheels? Are they delayed because they're waiting for well-designed parts?
Reply With Quote
     
     
  #1537  
Old Posted Feb 13, 2026, 9:33 PM
skyscraperaccount skyscraperaccount is online now
Registered User
 
Join Date: Jun 2023
Posts: 223
Quote:
Originally Posted by OTownandDown View Post
Wait just so I understand, there's an issue with the trains. There are 21 trains right now available. There are 26 trains needed during peak hours. There are 46 required for the lengthened line. Where are the 25 additional train sets? Are they in the shed? Is there another shed somewhere? Do they just blindly have the same wheels? Are they delayed because they're waiting for well-designed parts?
https://www.railfans.ca/traintracker/index.php
This section: Last Reported In-Service Location of All Trains

That'll help you know where some are (though this cant be sorted by line)...there's alot of red.

News article today

https://ottawa.citynews.ca/2026/02/1...lesser-service
Reply With Quote
     
     
  #1538  
Old Posted Feb 13, 2026, 10:04 PM
DarthVader_1961 DarthVader_1961 is offline
Registered User
 
Join Date: Jun 2009
Posts: 434
I recall that the LRT was supposed to be taken over by Metrolinx. Would that mean that RTG will be out of the picture?
Reply With Quote
     
     
  #1539  
Old Posted Feb 13, 2026, 11:35 PM
skyscraperaccount skyscraperaccount is online now
Registered User
 
Join Date: Jun 2023
Posts: 223
Quote:
Originally Posted by skyscraperaccount View Post
https://www.railfans.ca/traintracker/index.php
This section: Last Reported In-Service Location of All Trains

That'll help you know where some are (though this cant be sorted by line)...there's alot of red.

News article today

https://ottawa.citynews.ca/2026/02/1...lesser-service
Glen Gower posted on their substack
https://glengower.substack.com/p/wha...rt-line-1-east
Reply With Quote
     
     
  #1540  
Old Posted Feb 14, 2026, 12:47 AM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,084
Quote:
Originally Posted by DarthVader_1961 View Post
I recall that the LRT was supposed to be taken over by Metrolinx. Would that mean that RTG will be out of the picture?
No. Metrolinx would take the same role that the city takes on today. They would be the ones interacting with RTG/RTM/Alstom.

It would be the same contract structure as what's happening in Toronto with Finch West and Eglinton. TTC operates, Metrolinx owns, all maintenance is privatized.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 12:27 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.