Project Rundown
Unless noted otherwise, all projects for each location are arranged first by status, then by cost, if known (most to least expensive).
Status Order: - under-construction (listed first)
- approved / proposed (listed second)
- completed (listed third, newest to oldest)
- demolished / destroyed (listed fourth)
- cancelled (listed last)
Muskegon
Code:
MUSKEGON CONSTRUCTION
Adelaide Pointe, Phase 1 under construction ($250 million)
(1204 and 1148 W. Western Ave.)
Source: Adelaide Pointe
Former Shaw Walker Factory Repurposing, multi-phase; ongoing (~ $40+ million?)
(general location)
Source: The Frederick News-Post
Terrace Point Landing, ongoing construction (~ $20 million?)
(general location)
Source: Terrace Point Landing
Muskegon Infill Housing (~ 240 homes), under construction (~ $18 million?)
(locations vary - pictured location)
Source: MLive
Hartshorn Village, multi-phase condos, under construction (~ $14 million?)
(general location)
Source: Facebook | Hartshorn Village and Marina
Muskegon Museum of Art Expansion, under construction ($11.2 million)
296 W Webster Ave.
Source: Mathison | Mathison Architects
The Leonard, under construction ($8.9 million)
292 W. Western Ave.
Source: Facebook | The Leonard
Ten21 Apartments, under construction (~ $6 million?)
1021 Jefferson St.
Source: MLive | Courtesy Hooker DeJong
Muskegon Food Hall, under construction (~ $5 million?)
221 W. Webster Ave.
Source: Corey Morse | MLive
Muskegon Central 9-1-1 Dispatch addition, under construction (~ $1.5 million?)
770 Terrace St.
Source: LinkedIn | Construction Simplified
Pigeon Hill Entertainment Complex, under construction ($650,000)
441 W. Western Ave.
Source: MLive | Lynn Moore
MUSKEGON PROPOSED
Windward Point Mixed-Use Development, proposed ($400 million)
(general location)
Source: MLive | Courtesy DPZ CoDesign
Muskegon (Fruitport Township) Casino, proposed ($180 million)
(general location)
Source: WKSO | Courtesy Little River Band of Ottawa Indians / US Bureau of Indian Affairs
Harbor 31 mixed-use development, approved ($110 million)
(general location)
Source: Mlive | Courtesy Henrickson Architecture
Foundry Square mixed-use, proposed ($65 million)
(general location)
Source: Great Lakes Development Group
Hackley Castle Inn & Suites ($11.5 million)
349 W Webster Ave.
Source: Second Wave Media | Courtesy of WheelFish Group
Microtel, proposed, part of Foundry Square (~ $2.5 million?)
(general location)
Source: Great Lakes Development Group
(Muskegon Township) Settlers Glen, proposed ($40 million)
(general location)
Source: MLive | provided by Craig Fritsma
Downtown Mixed-Use Development, proposed ($25 million)
West Western Ave. between Third and Fourth sts.
Source: MLive | Integrated Architecture
Lake View Lofts, Phase 2, proposed (~ $20 million?)
351 W Western Ave.
Source: Crain's Detroit
The Docks housing development, proposed (~ $20 million?)
(general location)
Source: The Docks Muskegon
Former Nelson Elementary School repurposing, proposed (~ $20+ million?)
550 W Grand Ave.
Source: LinkedIn | Cornerstone Architects, Inc.
Fields Cannary Cannabis Facility, proposed ($10 million)
420 S. Harvey St.
Source: MiBiz | Courtesy Photo
Samaritas Senior Housing, proposed ($10 million)
4 W. Webster Ave.
Source: MLive | Courtesy Samaritas
Former Peoples State Bank / Liberty Bank / Ameribank Building Repurposing,
Proposed (~ $35 million?)
880 First St.
Source: Crain's Detroit
The gutted structure as seen in August 2018
Source: MLive
Food Forward Farm - Business Incubator, proposed (~ $7 million)
713 Yuba St. (former Farmers Market)
Source: MLive | Courtesy Rendering
The Shoppes on Sherman, proposed ($5 million)
(Muskegon Heights - general location)
Source: MLive | Courtesy City of Muskegon Heights
Terrace Point Dry Marina and Townhomes, proposed (~ $5 million?)
(general location)
Source: MLive | Courtesy City of Muskegon
1095 Third St., proposed (~ $2+ million?)
1095 Third St.
Source: MLive
Chart House Energy Old Foundry Repurposing, proposed (~ $2+ million?)
825 W. Western Ave.
Source: MLive | Cory Morse
Former MCC Lakeshore Fitness Center redevelopment, proposed (~ $1.5 million?)
900 W Western Ave.
Source: MLive
Harbor Theater mixed-use conversion, proposed ($1.1 million)
1937 Lakeshore Dr.
Source: MLive
VanDyk Convention Center, completed April 2021 ($21 million)
460 W Western Ave.
Source: MLive | Hope Davison
Catholic Charities West Michigan Campus, completed March 2021 ($4.5 million)
(general location)
Source: MLive | Courtesy Catholic Charities West Michigan
Ryerson Creek Outfall EPA Restoration, completed December 2020 ($6.6 million)
(general location)
Source: greatlakesmud.org
1208 8th Street rehabilitation, completed late 2020 ($550,000)
1208 8th St.
Source: Core Realty Partners
Midtown Square infill homes, completed 2020 ($3 million)
(general location)
Source: WZZM 13
Northtown 794, completed June 2020 ($3 million)
794 Pine St.
Source: MLive
Western Place Condominiums, completed Spring 2020 (~ $3 million?)
243 W Western Ave.
Source: My own photo - February 2021
3rd St. / Midtown Streetscape Improvements, completed November 2019 ($900,000)
(general location)
Source: MLive
Mercy Health (former L.C. Walker) Arena renovations, completed 2019 ($3.5 million)
470 W Western Ave.
Source: MiBiz | Courtesy Rendering
Delta Hotels by Marriott (reno & rebranding), completed October 2019 ($6 million)
939 Third St.
Source: Marriott
MCC Arts & Humanities Renovation, completed August 2019 ($9 million)
(general location)
Source: Progressive AE
Lake View Lofts, Phase 1, completed July 2019 ($16 million)
351 W Western Ave.
Source: My own photo - February 2021
Nipote's Italian Kitchen (shipping containers), completed July 2019 (~ $150,000?
98 W Clay Ave.
Source: MLive | Kayla Renie
Industrial Warehouse, 490,000 SF, completed Summer 2019 (~ $6 million?)
2420 Remembrance Dr.
Source: loopnet
Pigeon Hill Production Facility, completed April 2019 ($25 million)
895 Fourth St.
Source: Muskegon Times
Mercy Health New Patient Tower, completed Spring 2019 ($271 million)
1500 E Sherman Blvd.
Source: Building Design + Construction
Heritage Square Townhomes / Condos / Commons, completed Spring 2019 (~ $15 million?)
(general location)
Source: MLive
MCC Health & Wellness Center, completed November 2018 ($14.2 million)
(general location)
Source: Clark Construction Company
Highpoint Flats Apartments (redeveloped highrise), completed May 2018 ($9 million)
285 W Western Ave.
Source: My own photo - February 2021
Rad Dad's Taco & Tequila Bar, completed May 2018 (~ $1 million?)
470 W Western Ave. Suite A
Source: Muskegon Times
Terrace Flats Apartment Conversion, completed Spring 2018 (~ $3 million?)
316 Morris Ave.
Source: apartmentfinder.com
Berkshire Muskegon (Senior Housing), completed April 2018 ($16 million)
929 First St.
Source: My own photo - February 2021
MCC Sturrus Technology Center, completed January 2018 ($15 million)
388 W Clay Ave.
Source: Rapid Growth Media | Courtesy MCC
Mercy Health Urgent Care North, completed December 2018 ($12 million)
2006 Holton Rd.
Source: Mercy Health
Planet 3 Extreme Air Park, completed May 2018 (~ $1 million +?)
1740 E Sherman Blvd. (former Target Store)
Source: MLive
Western Market Pop-Up Shops, completed May 2017, expanded May 2018 (~ $100,000)
(general location)
Source: Muskegon Western Market
Spectrum Health Integrated Care Campus North, completed December 2016 ($13.8 million)
2009 Holton Rd.
Source: Spectrum Health
MCC Science Center, completed August 2015 ($9.6 million)
(general location)
Source: MCC
B.C. Cobb Coal Power Plant Demolition, completed February 2020 (~ $2 million?)
(general location)
Source: MLive
(Dalton Township) Sensi Park Grow Facility, 2019 proposal - cancelled (~ $5 million?)
(general location)
Source: MiBiz | Courtesy Rendering
Sappi Paper Mill Demolition, completed Fall 2017 (~ $2 million?)
(general location)
Source: Holland Sentinel
Chase Hackley Piano Factory Demolition, completed Fall 2017 (~ $150,000?)
(general location)
Source: change.org
Holland
Code:
Hudsonville Ice Cream Expansion, under construction ($51 million)
345 E. 48th St.
Source: American Structurepoint Inc.
Towers on River, under construction ($26.9 million)
159 S River Ave.
Source: City of Holland
Perrigo 357,000 SF Distribution Center Warehouse, under construction ($13.6 million)
13295 Reflections Dr.
Source: Holland Sentinel | Contributed
The River Place by Resthaven, under construction (~ $4.5 million?)
210 / 212 S River Ave.
Source: Resthaven
The Commons at Westshore mixed-use development, proposed (~ $40+ million?)
Holland Charter Township - general location)
Source: Holland Sentinel | Courtesy Shops at Westshore
VisionQuest Companies HQ, proposed ($30 million)
(general location)
Source: Opera News / GRBJ
HOM Flats at 24th and Waverly, proposed (~ $16+ million?)
(general location)
Source: Holland Sentinel | City of Holland
HOM Flats at Felch Street, proposed (~ $12+ million?)
(Holland Charter Township - general location)
Source: Ionia Sentinel-Standard | Courtesy Magnus Capital Partners
W 36th St. Affordable Housing Development, proposed (~ $4 million?)
(general location)
Source: City of Holland
New Holland Brewing Expansion, proposed (~ $500,000?)
206 College Ave.
Source: City of Holland
GRCC Lakeshore Campus, completed August 2021 ($12 million)
(Holland Charter Township - general location)
Source: GRCC
Haworth Hotel, completed June 2021 ($7.5 million)
225 College Ave.
Source: Tripadvisor
Port 393 (event venue), completed June 2020 (~ $1.5 million?)
393 Cleveland Ave.
Source: Port 393
SpringHill Suites Holland (Township), completed April 2020 (~ $16 million)
3084 W. Shore Dr.
Source: Holland Sentinel
Staybridge Suites Holland (Township), completed November 2019 (~ $16 million?)
12170 James St.
Source: Facebook
@Home Realty, completed October 2019 ($6 million)
171 College Ave.
Source: T2 Construction Management
Holland Oz Project, completed July 2019 ($300,000)
Centennial Park
Source: Cory Morse | MLive
West 8th Mixed-Use Development, completed Spring / Summer 2019 (~ $35 million?)
Move theater, HopCat, commercial, apartments, parking deck (6 images, below)
(general location)
West 8th - Site Plan
Source: MLive
West 8th - Partial Rendering
Source: Wood TV 8
West 8th - Sperry's Moviehouse
Source: Holland Sentinel
West 8th - HopCat
Source: Twitter | @HopCatbr
West 8th - Lofts at West 8th
Source: Lofts at West 8th
50 West Residences
Source: realtor.com
Home2 Suites Holland (Township), completed January 2019 (~ $14 million?
3140 W Shore Dr.
Source: Hilton
George & Lucile Heeringa Civic Center Place, completed September 2018 ($16.5 million)
150 W 8th St.
Source: City of Holland
Western Theological Seminary Expansion, completed Fall 2018 ($15 million)
101 E 13th St.
Source: Western Theological Seminary
DeBoer Bakkeri - New / 2nd Location, completed April 2018 (~ $500,000?)
360 Douglas Ave.
Source: Austin Metz | Holland Sentinel
Holland Energy Park, completed October 1017 ($240 million)
1 Energy Park Way
Source: Progressive AE
Courtyard Marriott Downtown, completed February 2016 (~ $18 million?)
121 E 8th St.
Source: Facebook | Courtyard Marriott Downtown
Hope College Jack H. Miller Center for Musical Arts, completed Fall 2015 ($35 million)
221 Columbia Ave.
Source: Hope College
Norton Shores
Coldwater
Ionia
(reserved)
Niles
Grand Haven
Code:
Robinson Landing, under construction ($7.5 million)
(general location)
Source: MCC
The Trib, approved (~ $5 million?)
101 N. Third St.
Source: MLive | City of Grand Haven
GHBLP - New Operations and Technology Center, proposed ($43 million)
(general location)
Source: The Lakeshore | Courtesy Rendering
Forum Lofts, proposed (~ $13 million?)
201 N 3rd St.
Source: Crain's Grand Rapids Business | Cherette Group / Ghafari
GHBLP - Former Power Plant repurposing, proposed
518 Harbor Dr.
Source: Google Maps
Peerless Flats (Mixed-Use Development), completed July 2023 ($24.7 million)
(general location)
Source: Second Wave Media | Courtesy Rendering
South Harbor Drive Rejuvenation, completed Fall 2020 (~ $3 million?)
(general location)
Source: LinkedIn | Abonmarche Consultants, Inc.
Fit Body Boot Camp (Starlite Lanes redevelopment), completed late 2019 (~ $2 million?)
1309 S Beacon Blvd.
Source:
@Home Realty (Starlite Lanes redevelopment), completed late 2019 (~ $2 million?)
1307 S Beacon Blvd.
Source: @Home Realty
Noto's at the Bil-Mar, completed Fall 2018 (~ $1.2 million?)
1223 S Harbor Dr.
Source: MLive | Courtesy Noto's
Lynne Sherwood Waterfront Stadium, completed June 2018 ($4.5 million)
1 N Harbor Dr.
Source: MLive
J.B. Sims Generating Station Demolition, completed early 2020 ($5 million)
1231 N 3rd St.
Source: Wood TV 8
Sturgis
Big Rapids
Benton Harbor
Code:
Benton Harbor Flats rehabilitation, under construction ($4.5 million)
corner of Pipestone and West Main Streets
Source: Moody on the Market
Whirlpool Apartment development, proposed ($22 million)
170 Riverview Dr.
Source: WNDU News 16 | Courtesy Whirlpool Corp.
The Corner at Wall Street, proposed (~$18 million?)
(general location)
Source: Moody on the Market
Twin Cities Harbor Planning Study, visioning, 2015
Concept view of mixed-use development at central dock / inner harbor
(general location)
Source: Southwest MI Planning Commission
Farmers & Merchants Bank Façade Restoration, completed 2019 ($150,000)
92 W. Main St.
Source: MiBiz | Courtesy Rendering
Houndstooth Restaurant & Lofts, completed September 2019 (~ $1.25 million?)
132 Pipestone St.
Source: Herald-Palladium | Don Campbell
The Eddy, completed 2019 (~ $3 million?)
1900 Paw Paw Ave.
Source: LinkedIn | Abonmarche
200 Water Street, completed 2016 (~ $2 million?)
Source: Google Maps
LMC Hanson Technology Center, completed April 2016 ($10.6 million)
2755 E Napier Ave.
Source: AMI
Saranac Flats, completed 2014 (~ $4 million?)
376 W Main St.
Source: apartmenthomeliving.com
Harbor Shores Golf Resort, opened 2010 (ongoing investments, $500+ million)
201 Graham Ave.
Source: Crain's Detroit Business | Courtesy Harbor Shores
Albion
St. Joseph
Three Rivers
Hudsonville
Hastings
Code:
Affordable Housing Project, proposed / on-hold due to arson at Royal Coach building
(~ $20 million?)
(general location)
Source: WZZM 13
...
Marshall
Rockford
Dowagiac
Zeeland
Allegan
Coopersville
South Haven
Wayland
Code:
Gun Lake Casino Phase 5 Expansion (Resort Hotel), under construction ($300 million)
250,000 SF, 250-room Hotel, Dining, Pool & Spa Expansion
1123 129th Ave.
Source: yogonet.com
Gun Lake Tribe US 131 Frontage Development, proposed (~ $100 million+)
(general location)
Source: MiBiz | Kaylee van Tuinen
Gun Lake Casino Phase 4 Expansion, completed September 2021 ($100 million)
72,000 SF of additional new dining, entertainment, & gaming space
1123 129th Ave.
Source: Holland Sentinel | Contributed
MRCC Union Hall and Apprentice Training Center, completed December 2018 ($14 million)
500 Reno Dr.
Source: My own photo
Gun Lake Casino Phase 1-3 Expansion, completed late 2018 ($76 million)
Parking deck, "High-Limit" gaming room, dining, entertainment, & gaming space
1123 129th Ave.
Source: Gun Lake Casino
...
Plainwell
(reserved)
Middleville
Barry Township
Paw Paw
Whitehall
Spring Lake
White Pigeon
Cassopolis
Berrien Springs
New Buffalo
Stanton
(reserved)
Centreville
Douglas
Saugatuck
Last edited by deja vu; Jan 27, 2025 at 12:28 AM.