Side NoteThis post has always been an easy way to view projects in Tucson, however now that kaneui (the author) is gone I am trying to make this post work once again. It's still messy right now but I'll get the hang of things. Sorry for the length of the post. I hope to be able to fix it later. Thanks for bearing with me
Metro Tucson Development Projects
LAST UPDATE: October 11,2013
Credit to kaneui for the creation of this post
(photo: Wikipedia)
Estimated metro population as of January 1, 2013: (Pima County) - 1,003,930
(The Business Journals)
DOWNTOWN REDEVELOPMENT
Rio Nuevo Multipurpose Facilities District
Rio Nuevo is a Tax Increment Financing (TIF) district approved by voters in 1999 to fund and support downtown Tucson revitalization. However, sales tax funds did not begin transferring from the state to Rio Nuevo until 2003 (approximate funds received through June 30, 2012: $97.8M - average of $906k per month). The majority of TIF revenues are currently being used to pay debt service (purchase of Tucson Convention Center, renovation of Fox Theatre, etc.).
As of July 9, 2013, the Tucson City Council has approved Rio Nuevo's proposal to spend $7.8M for improvements to the TCC arena, scheduled for completion in the spring of 2014. Rio Nuevo will also launch at least one new downtown hotel project, after which it can legally spend funds to complete the Mission Gardens, fund downtown streetscape improvements, and begin development of numerous vacant parcels west of the Santa Cruz River.
Rio Nuevo Multipurpose Facilities District map
(courtesy: city of Tucson)
Downtown Tucson projects,
Downtown Tucson projects map,
Rio Nuevo website
Downtown Tucson Partnership's proposed plan (2010):
Revitalizing Downtown Tucson: Building the New Pueblo
12-MONTH OUTLOOK - metro Tucson
COMPLETIONS
Summer, 2013
UA Lowell-Stevens Football Facility ($72.3M)
Sun Link Modern Streetcar - rail line ($56M)
The Retreat at Tucson (student housing - $31M)
LEVEL (student housing - $25M)
The Cadence (student housing - $33M)
Fall, 2013
One East (mixed use - $18M)
Winter, 2013-14
Downtown Links - St. Mary's section ($7.3M)
Spring, 2014
PCC Northwest campus - Science Lab & Classroom Bldg. ($10.1M)
UA Old Main Renovation ($13.5M)
Tucson Convention Center renovations ($7.8M)
Summer, 2014
The Hub at Tucson (student housing tower)
Park Ave. (student housing tower)
El Rio Health Center addition ($14.1M)
UA South Stadium Parking Structure ($18.5M)
STARTS
Fall, 2013
Tucson Convention Center renovations ($7.8M)
The Junction at Iron Horse (student housing)
Green Valley Hospital ($52M)
UA South Campus Parking Structure ($18.5M)
Winter, 2013-14
5th and Congress (mixed-use $32M)
Spring, 2014
UA Bear Down Gymnasium Renovation/Addition ($27.4M)
Summer, 2014
UA Engineering Innovation Bldg. ($63M)
UA Bioscience Research Laboratories ($85M)
UA McKale Memorial Center Renovations/Additions ($80M)
RECENTLY COMPLETED
August 2013
LEVEL (1020 N. Tyndall Ave.) - $25M, 295k s.f., 14-story residential tower for 586 students, including parking, rooftop pool and ground-floor retail.
Developer: Campus Acquisitions. Architect: Shepley Bulfinch. Contractor: UEB.
http://tucsonlevel.com/,
http://www.campusacquisitions.com/ca/under-construction/university-arizona/index.php,
http://www.wildcat.arizona.edu/article/2012/08/student-housing-on-the-rise-throughout-tucson
Webcam: http://www.uebbuilders.com/webcams/tyndall2.html
(renders: Campus Acquisitions, photo: UEB webcam)
The Cadence (345 & 350 E. Congress St.) - $33M, two buildings of student housing with 456 beds on opposite sides of Congress St.:
1. West building - L-shaped, six-story building for 287 students next to Rialto Theatre with 10k s.f. ground-floor retail;
2. East building - five levels of apartments for 169 students over Centro Garage, including 10k s.f. ground-floor retail.
Developers: Capstone Development, Oasis Tucson. Architect: Ankrom Moisan. Contractor: Summit Builders.
http://www.downtowntucson.org/2012/06/student-housing-will-arise-next-rialto-theatre/,
http://www.thecadencetucson.com/,
https://www.facebook.com/thecadencetucson
UNDER CONSTRUCTION
Sun Link Streetcar (3.9 miles - University Medical Center to Mercado District) - $197M, 18 stops, 8 streetcars. Service hours: 6am - 2am
- Luis G. Gutierrez Bridge at Cushing Street ($11.9M): Opened for pedestrian/bike use - October, 2012
- Maintenance & Storage Facility ($7.9M): substantially complete: June, 2013 (
see above). Contractor: D.L. Withers
- Rail line ($56M): construction schedule: April, 2012 - August, 2013. Contractor: Old Pueblo Trackworks
Projected start of operations: 2nd quarter, 2014
http://www.tucsonstreetcar.com/,
http://dot.tucsonaz.gov/projects/project.cfm?cip=6638D2BE-FBF1-E5C6-A82F29CBF9A9D531
route map; first streetcar testing - Portland, OR
Construction progress: streetcar stop and artwork, overhead contact system.
(route map, photos: City of Tucson)
One East (NEC of Stone Ave. and Broadway Blvd.) - $18M, five-story, 136k s.f. mixed-use building with 4k s.f. street-level retail, commercial office (floors 2-3), 24 apartments (floors 4-5), and 119-space parking garage (LEED Silver). Developer/Contractor: Robert Caylor Construction. Architect: Engberg Anderson Architects.
The project is the first recipient of the city's Government Property Lease Excise Tax (GPLET) incentive to encourage city center redevelopment.
Construction timeline: October, 2012 - November, 2013
http://www.oneeasttucson.com/
render looking NE; construction progress - June, 2013 .
(render: Engberg Anderson Architects; photo: ComplotDesigner)
PCC Northwest Campus - Science Lab & Classroom Building (7600 N. Shannon Rd.) - $10.1M, 47k s.f. building with nine science labs, classrooms and lecture hall.
Architect: Burns Wald-Hopkins Shambach.
Construction timeline: December, 2012 - Spring, 2014
http://azstarnet.com/news/local/nor...cle_f218814b-6335-570e-8fc5-aaa52ccfbad4.html (*See links for 2 webcams on site.)
(render: Pima Community College)
Downtown Links (btw. Broadway Blvd. & I-10) - $84.7M project to connect Barraza-Aviation Parkway from Broadway Blvd. to I-10 with a 30 mph, four-lane roadway north of the Union Pacific railroad tracks, providing alternate access to and around Downtown by foot, bike, vehicle, and public transit. In addition to major drainage improvements to the Tucson Arroyo, Downtown Links will offer new and safer underpasses, railroad crossings, and sidewalks.
Phase I - 8th St. drainage - $7.4M (COMPLETED - May, 2012)
Phase II - St. Mary's section (I-10 to Church Ave.) - $7.3M; construction timeline: November, 2012 - January, 2014. Contractor: Borderland Construction
Phases III & IV - 6th St. underpass, link from 6th St. to Broadway (Community Advisory Committee and neighborhood meetings have resumed two-year design phase, currently 30% complete)
Estimated final completion: late 2016
http://www.downtownlinks.info/,
http://dot.tucsonaz.gov/projects/project.cfm?cip=23814370-DA0B-C395-BBBC08F438FC61DF
Phase II - St. Mary's section detail
(maps: city of Tucson)
UA Old Main Renovation - $13.5M renovation of the University of Arizona's oldest (1891) structure of 27k s.f., including reprogramming for administrative functions.
Architects: Poster Frost Mirto, NTD Architecture. Contractor: Sundt Construction.
Construction timeline: January, 2013 - April, 2014
http://www.pdc.arizona.edu/projects/Project.aspx?Project=11-9023
Webcam: http://www.pdc.arizona.edu/webcam/OldMain.aspx
(photo: F.J. Gorat)
The Hub at Tucson (NWC of First St. & Tyndall Ave.) - 13-story tower to house 606 students, including 7,800 s.f. ground-floor retail.
Developer: Core Campus. Architect: Antunovich Associates.
Expected completion date: August, 2014
http://www.corecamp.us/,
http://www.facebook.com/HubAtTucson
construction progress - June, 2013
(drawing, renders, photo: Core Campus)
Next. (1031 N. Park Ave.) - 13-story tower to house 393 students with underground parking garage, rooftop pool, and 8k s.f. ground-floor retail.
Developer: Campus Acquisitions. Architect: Shepley Bulfinch. Contractor: Beal / Derkenne.
Status: estimated construction timeline: January, 2013 - August, 2014.
http://www.campusacquisitions.com/ca/under-construction/university-arizona/park-ave.php
El Rio Health Center expansion (839 W. Congress St.) - $14.1M, 54k s.f. addition to El Rio Community Health Center west of I-10.
Estimated construction timeline: June, 2013 - summer, 2014
http://azstarnet.com/news/science/h...cle_45ce22e5-c117-5989-b806-5c8cc1cebfd2.html
(render: Arizona Daily Star)
Northwest Medical Center expansion (6200 N. La Cholla Blvd.) - $46M, 70k s.f. new surgical wing built in existing surgery parking area.
Construction timeline: January, 2013 - Fall, 2014
http://www.northwestmedicalcenter.c...nces 50 Million Operating Room Expansion.aspx,
http://finehomesdigest.wordpress.co...t-medical-center-begins-46-million-expansion/
County Courts Complex (300 N. Stone Ave.) - $105M, seven-story, 288k s.f. courthouse, 7k s.f. central plant, 1200-space parking garage on 4.3 acres for Pima County. Developer: Pima County. Architect: AECOM. Contractor: Sundt Construction.
Construction timeline: tenant improvements to begin late 2013; occupancy by early 2015.
http://www.sundt.com/projects/pima-county-downtown-courts-complex/
dichroic glass art installation on facade
(site map, renders: AECOM; photo: Gordon Huether)
UA Environmental & Natural Resources Building, Phase 2 (ENR2) (1064 E. Lowell St.) - $75M, four-story, 150k s.f. addition to existing building for faculty offices, research, conference and support space (LEED Silver). Architect: GLHN. Contractor: Hensel Phelps.
Construction timeline: June, 2013 - May, 2015
Status: utility work in progress; project mobilization underway.
http://www.pdc.arizona.edu/projects/Project.aspx?Project=03-8526,
http://www.pdc.arizona.edu/enr2/
(render: GLHN; site plan: UA)
Mission San Agustín Garden (946 W. Mission Lane, W. of I-10; part of Tucson Origins Heritage Park) - re-creation of Spanish Colonial walled garden on its original site that was part of Tucson's historic San Agustín Mission. Friends of Tucson's Birthplace nonprofit under contract to develop, plant, and manage the 4.7-acre, adobe wall-enclosed garden for the city for five years (through 2017).
Phase I (COMPLETED): irrigation lines installed and 140 trees planted as the Kino Heritage Tree Orchard (NE quadrant).
Phase II: Native Desert Garden planted; Heritage Timeline Gardens being prepared and planted.
http://www.tucsonsbirthplace.org/,
http://www.facebook.com/pages/Friends-of-Tucsons-Birthplace/342949029330,
http://dot.tucsonaz.gov/projects/project.cfm?cip=663A9BB2-E468-E114-9D339C76A737EF96
site plan; view from A Mountain showing planted tree orchard - Sep., 2012
Harvest of winter garden - May, 2013; preparation of Heritage Timeline Gardens - June, 2013
(site plan, photos: Friends of Tucson's Birthplace)
APPROVED
Tucson Convention Center Renovations - $7.8M of upgrades, including new seats, lighting, a new video scoreboard, renovated bathrooms and concession stands.
Owner/Developer: Rio Nuevo
Status: project approved by Tucson City Council; expected completion by Spring, 2014.
http://azstarnet.com/news/local/gov...cle_1fcc08ce-555d-580c-b17e-3965b10b021e.html
(renders: Rio Nuevo)
UA South Stadium Parking Structure - $18.5M, 317k s.f., 900-space parking structure to replace surface parking lot just south of 6th St. near Arizona Stadium, nearby dormitories and other athletic facilities.
Expected construction timeline: November, 2013 - August, 2014
Status: schematic design complete; design development is ongoing
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=13-9168
The Junction at Iron Horse (504 E. 9th St.) - four stories, 232-bed student housing complex.
Developer: Roy Drachman. Architect: GD&A Architects.
Status: developer seeking MOU with neighborhood association and final city approvals for possible construction start in late 2013.
https://www.facebook.com/pages/Iron-Horse-Neighborhood/109569192412147?hc_location=timeline
(render, map: GD&A Architects)
Green Valley Hospital (I-19 and Canoa Ranch Dr.) - $52M, 32-bed hospital and medical office buildings on 22 acres. Developer: McDowell Enterprises
Construction timeline: Phase I -two-story hospital expected to open in 2014; Phase II - medical offices and two-story building east of hospital.
Status: County has approved zoning variances; developers in discussion with potential operators.
http://www.gvnews.com/sahuarita_sun...cle_e679b6f0-e024-11e2-b6ed-001a4bcf887a.html
UA Bear Down Gymnasium Addition/Renovation - $27.4M adaptive re-purposing of historic 1926 facility, including a south side addition for an eventual 75k s.f.
Architects: Poster Frost Mirto / NTD Architecture. Contractor: Sundt Construction.
Estimated construction timeline: April, 2014 - August, 2016
Status: programming and schematic design in process
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=12-9151
(photo: UA)
UA Engineering Innovation Building - $63M, 107k s.f. research center to provide critically needed infrastructure to support student recruiting/retention and consolidate key research and support functions.
Estimated construction timeline: June, 2014 - October, 2015
Status: schematic design phase underway
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=05-8623
UA Bioscience Research Laboratories - $85M, 120k s.f. laboratory facility for interdisciplinary research in many health science disciplines.
Estimated construction timeline: June, 2014 - January, 2016
Status: design development in process
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=12-9134
UA McKale Memorial Center renovations/additions - $80M upgrade to 39 year-old, 14,650-seat sports arena, including premium seating and improved ADA access, as well as new concourses, restrooms, concessions and points of sale.
Estimated construction timeline: Phase I: June, 2014 - January, 2016; Phase II completion: June, 2017.
Status: construction contract in progress
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=13-9191
(photo: Kelly Presnell, 2005)
The Bridges (N. of I-10 btw. Kino Parkway & S. Park Ave., acreage west of S. Park Ave.) - 351-acre infill project on former site of Tucson Downtown Airport:
- UA BioPark (65 acres, 3M+ s.f. mixed-use project with housing, R&D facilities, offices, hotel, conference center-
see below)
- Tucson Marketplace at The Bridges (113 acres, 1M+ s.f. regional power center -
see below)
- 700+ single-family residences by KB Homes/US Lennar Homes (128 acres)
- open space and parks (45 acres)
Developers: Eastbourne Investments, Ltd., Retail West Properties, Genesis Tucson South
aerial photo - May, 2012; site plan
UA BioPark (36th St. & Kino Parkway) - 65-acre, 3M+ s.f. mixed-use research park (office, hotel, conference center, rental housing)
Status: Site is development ready: $8.6M of Phase II Infrastructure completed in June, 2012--including roads, utilities, and perimeter landscaping.
http://www.uatechpark.org/static/index.cfm?action=group&contentID=72,
http://www.pdc.arizona.edu/projects/Project.aspx?Project=10-8958
Phase I site plan, render
Tucson Marketplace at The Bridges - 1M+ s.f. regional power center on 113 acres; Costco and Walmart Supercenter completed.
Status: construction on a few smaller pads currently in progress.
http://www.tucsonmarketplaceatthebridges.com/
For more 2012 aerial photos: http://www.tucsonmarketplaceatthebr...tion=com_content&view=article&id=55&Itemid=64
site plan; freeway monument sign
(site plans, photos, renders: http://www.tucsonmarketplaceatthebridges.com/)
Oro Valley Innovation Campus (NWC of E. Rancho Vistoso Blvd. & E. Vistoso Commerce Loop Rd.) - 160k s.f. bioscience-tech campus: four 20k s.f. buildings for labs, manufacturing and warehousing, plus ten 8k s.f. high-tech office buildings. Developer: Anthem Equity Group Inc.
Status: construction awaiting signed tenant contracts
http://anthemequity.com/innovation-campus/
(site map, render: Anthem Equity Group Inc.)
Mission District (west of I-10, btw. Congress St. and Cushing St.) - 14-acre, mixed-use: multi-family housing, retail, restaurants, office, hotel and parking garage.
Developer: The Gadsden Co.
First project: Parcel G, Sentinel Plaza - 6 stories, 143 units for low-income seniors, COMPLETED - July, 2012.
Future projects: Parcel A - West End Station (apartments/retail -
see below); Monier Apartments (residential/retail/office -
see below); Parcel B - parking garage/retail; Parcel C - boutique hotel; Parcels D, E - three 8-10 story towers for residential/retail/office; Parcel F - office.
Status: As of April, 2013, Mayor and Council are seeking an amendment to the 2008 development agreement to secure the developer's performance of its obligations under Phase 2 of the project.
http://dot.tucsonaz.gov/projects/project.cfm?cip=C91DC0D8-9E97-5E3A-A7B9DC4248A40A90,
http://gadsdencompany.com/index_pro_2a.html
(site plan: The Gadsden Co.; rendering: lasertrimman/Flickr)
West End Station (SEC of Congress St. and Avenida del Convento) - 4-6 stories, mixed-use with 30k s.f. retail, 239 apartments on Parcel A of Mission District.
Status: seeking development partner and financing
http://www.downtowntucson.org/2012/05/west-congress-is-primed-for-an-urban-apartment-scene/
(render: The Gadsden Co.)
Monier Apartments (Avenida del Convento, S. of Mercado San Agustín) - four stories, 169 apartments over ground-floor retail and office, with underground parking and rooftop pool. Developers: The Gadsden Co., Holualoa Companies
Status: estimated construction start - early 2014
http://gadsdencompany.com/index_pro_2a.html
early renders of Monier Brickyard Building
(renders: The Gadsden Co.)
Greenline on Congress (E. side of I-10, btw. Congress St. and Cushing St.) - 8.3 acres, transit-oriented mixed use: 86k s.f. street-level retail, 320 1-BR apartments, 120-room boutique hotel, Greyhound bus terminal, pedestrian bridge over Congress St. Developer: Peach Properties. Architect: FORS Architecture & Interiors.
Status: Rio Nuevo has agreed to take over title to the property from the city, and may submit a new request for RFPs.
http://peachprops.com/news/peach-properties-streetcar-route-development/
(site plan, render: Peach Properties)
PROPOSED
5th and Congress - $32M mixed-use project to redevelop the Rialto Block and the adjoining 200 block of Congress St., adding six new restaurants, two bars, three retail spaces and 20k s.f. of coworking/office space; build a six-story, 130-room boutique hotel over the subterranean Depot Plaza parking garage at Toole and 5th Ave.
Developers: Tucson Urban, North Face Investments. Architect: FORS Architecture + Interiors.
Status: seeking financing, local and state tax incentives; expected construction start by the end of 2013.
http://rionuevo-tucson.org/wp-content/uploads/2011/08/5th_and_Congress_Applications.pdf,
http://www.downtowntucson.org/2012/10/a-boutique-hotel-may-join-mlk-one-north-fifth-apartments/,
http://azstarnet.com/news/local/gov...cle_b9a71e40-5fae-5021-a0b0-06f99be7005c.html
west side of Rialto Block along 5th Ave.
(site plan, render: Tucson Urban)
Main Gate Square hotel (Tyndall Ave. & Second St.) - $35M, 9-story mixed-use project including 150-room hotel, 5-7 screen multiplex theater, retail, and two levels of underground parking. Developers: CBRE Hotels, Triangle Development.
Status: seeking proposals for development and ownership of a hotel on a long-term ground lease.
https://www.cbremarketplace.com/listings/10112/Internal Documents/UA Hotel Project.pdf
(render: Arizona Daily Star)
UA Centennial Hall renovation/expansion - $10M in upgrades to 86k s.f. performance venue built in 1936, including new seating and improved sight lines, improved acoustics, enhanced and expanded lobby and patron areas, and improved support spaces.
Status: feasability study showing potential improvement options due August 30, 2013; estimated construction timeline: TBD
http://www.pdc.arizona.edu/projects/Project.aspx?Project=08-8853
(photo: UA)
UA Health Education & Advanced Technologies Building - $111M, 200k s.f. inter-professional education and simulated practice building for health-related professions.
Expected construction timeline: TBD
Status: Design Professional negotiations are underway
http://www.pdc.arizona.edu/Projects/Project.aspx?Project=13-9193
The Armory (246 E. Broadway Blvd.) - five-story building with three stories of 170 market-rate apartments over two levels of parking. Developer: Peach Properties.
Status: developer has applied for HUD mortgage insurance for construction loan
http://peachprops.com/news/peach-properties-streetcar-route-development/,
http://www.downtowntucson.org/2012/07/peach-properties-bear-fruit-all-over-downtown/
earlier rendering; view of development site
(render: Peach Properties; photo: Downtown Tucsonan)
ON HOLD
Memorial Complex (714 N. Euclid Ave.) - proposed multi-story student housing complex, currently zoned for 4-6 stories. Developer: Mike Noonan. Architect: Bob Vint.
Status: on hold, pending a new development partner, construction financing
http://cms3.tucsonaz.gov/sites/default/files/planning/Euclid_4th Street - Memorial Complex.pdf
earlier rendering with 12 stories
(render: Vint & Associates)
Thrifty Block hotel (Congress St., btw. Stone Ave. & Scott Ave.) - five-story, 123-room Hampton Inn proposed for parcel originally slated for luxury condo project.
Developers: Bourn Companies, True North Hotel Group
Status: Rio Nuevo seeking to require developer to have a building permit on the site within two years; otherwise, property reverts to Rio Nuevo ownership.
development site on Congress St.
(photo: Arizona Daily Star)
Tucson Origins Heritage Park (W. of I-10, S. of Cushing St.) - numerous proposed cultural attractions, including UofA Science Center/Arizona State Museum, Arizona Historical Society Museum, Tucson Children's Museum; re-created Mission San Agustín chapel, convento, and garden.
Status: Mission San Agustín Garden being developed (
see above); other projects postponed until additional funding identified.
http://dot.tucsonaz.gov/projects/project.cfm?cip=C92193C9-ADBA-079B-69249E040D4A5076
site plan; render of Mission chapel and convento
(courtesy - City of Tucson: http://dot.tucsonaz.gov/projects/project.cfm?cip=C92193C9-ADBA-079B-69249E040D4A5076)