Well-heeled home buyers in the new Mercado District--enticed by Rio Nuevo's promises of a cultural plaza with numerous museums, as well as a Tucson Origins Heritage Park with a reconstructed mission, convento and gardens--now have their views of downtown blocked by a pile of dirt excavated for an unbuilt parking garage.
With most of the westside Rio Nuevo projects on hold, the silver lining in this cloud is the new streetcar line expected to reach Congress St. and Avenida del Convento, where the new Mercado San Agustín will be opening this fall:
The hole left after the city began construction on an underground garage.
(photo: Joe Pangburn)
'Hole' heartedly committed
By Joe Pangburn
Inside Tucson Business
June 12, 2009
In what might be characterized as a Tucson version of Boston’s infamous “Big Dig” highway project through its downtown, developers at the Mercado District at Menlo Park off Congress Street west of the Santa Cruz River have since the summer of 2007 been looking at a football field-sized hole dug 25 feet into the ground, with an accompanying mound of dirt. They and residents of the area are now wondering just how much longer this version of a big dig will be there. The hole was supposed to be for an underground parking garage on top of which would be part of the Tucson Origins park that would include a rebuilt Mission San Agustin and a separate part of the part would include a cluster of museums. It was all part of the 1999 voter-approved Rio Nuevo district. But construction has come to a stop. And city officials aren’t saying when or if anything will come of the hole and the dirt pile.
The City of Tucson spent about $1 million to start an agricultural area along the bank of the Santa Cruz River associated with the Mission San Agustín called Mission Gardens. But about all that is there is a wall that collects grafitti. Meanwhile, the hole and the mound of dirt remain eyesores to the families who purchased homes in what they thought would be a cultural center. The mound of dirt presents of view of downtown Tucson where only the top three floors of the UniSource Tower can be seen. “We’re sort of resigned to accepting that it is unlikely the city will be moving forward on the projects on this side,” said Dante Archangeli, owner of Tucson Artisan Builders. “I doubt it will ever happen,” said fellow builder in the Mercado District Paolo DeLorenzo. While the builders aren’t using the city’s plans as a selling point anymore, the hole and the dirt mound don’t do anything to help get people into the development. “We aren’t looking for any kind of benefit from the city,” said Archangeli. “We just hope they could take away the things that detract from us here. We are a Rio Nuevo project and we are out of the ground and we are doing well. I think people forget that.”
As far as the city is concerned, the priority for spending Rio Nuevo money is on completing a downtown hotel and convention center. For the time being, it won’t be spent on the Mercado projects. “The state Legislature has told us that the priority for Rio Nuevo is the downtown hotel and convention center,” said City Manager Mike Letcher. “We had to start aligning our resources to meet that priority.” Letcher said this summer the council will begin discussing possible public-private partnerships, outside of Rio Nuevo funding, to complete the cultural improvements. “A lot of that will be driven by the construction of the modern streetcar,” Letcher said. “Those projects are critical cultural assets the community has as a priority.” It is an issue that has to be addressed.” Commercial development in the area is largely tied to the completion off the modern streetcar route through to the front door of the current and future developments.
The first commercial component of that center is the Mercado San Agustin, on the corner of Congress Street and Avenida del Convento, is out of the ground and has been 100 percent leased since September 2008 despite not opening until this November. The project is the first wholly ground-up new commercial building to be built in downtown Tucson in more than 25 years. It is also downtown Tucson’s first public market and about to be officially the first Leadership in Energy and Environmental Design (LEED) Gold certified building. The $6.5 million, nearly 15,000-square-foot project developed by the Gadsden Company is designed to foster small business growth. “It’s a mix of wonderful tenants,” said Adam Weinstein, a principal of Gadsden. Tenants include: La Estrella Bakery, Casa Marita Restaurante Argentino, Sonora Snow Cones, El Tutu Taqueria, Marisol’s Mexican Imports, Nurturing Nature, Kokopelli Woodworking and Caravanserai among others.
The second commercial building in the Mercado District of Menlo Park is the Monier Brickyard Building, a $35 million, 300,000-square-foot building with space for retail, office and residential. This project is directly south of the Mercado San Agustin. “This project has always been timed to the completion of the modern streetcar,” Weinstein said. “Since there have been delays and timetables pushed back on that with the city, this project has also.”
Weinstein said his company has letters of intent for nearly 40,000 square feet of the 90,000 square feet of office space in the project. “But until the added value of the street car is in place, these companies won’t relocate there,” Weinstein said. “We may be in a position to lay track on the west side first because we have so much open land as opposed to other areas.” Track on the west side should start to go in the ground in December according to Weinstein and be complete within a year. The four-mile line will be run from the University Medical Center near East Speedway and Campbell Avenue to the Mercado District at Menlo Park by late 2011.
The largest development for Gadsden will be separate from the Mercado District, but sits just across the street. In August of last year, the City Council agreed to sell 14.3 acres of vacant land for $3.3 million to the Gadsden Company to build the Convento Neighborhood, a $300 million, eight-block community with homes, retail, office and a hotel. This is the lot where the city piled the dirt from the exacavation area. “It used to be 70,000 cubic yards, now it is down to 20,000 cubic yards,” Weinstein said. “We are diligently working with the city to have the dirt removed by year’s end.”
Ron Lewis, director of general services for the City of Tucson as well as the downtown operations team leader said
the dirt was originally intended to be used to grade the city’s proposed development. “Currently, we don’t have a plan yet to remove it at any time,” he said. “The stock pile will remain there until other projects become active and we can reasses how much dirt will be needed for those.” Transportation director Jim Glock also said at this time there was no plan for the future of the hole.