Tucson Development Thread


More Rio Nuevo delays? Well, not surprising. City Manager Mike Hein has now put off construction of the Tucson Origins project to reconfigure the site layout, among other things:



TucsonOriginsredo.png

(map: Tucson Citizen)


Hein slams brakes on Rio Nuevo mission project
He wants San Agustín, museum to open together

by TEYA VITU
Tucson Citizen
05.28.2008

Tucson Origins likely will not have visitor attractions until 2011. The project west of Interstate 10 and south of Congress Street is back to the drawing board at the instigation of City Manager Mike Hein, who put the imminent reconstruction of Mission San Agustín on hold.

Hein has scrapped the two-year-old vision to build the mission first, followed in subsequent years by the other museums. In that process, Hein also is rethinking where to place museums around the cultural plaza north of the mission. Hein in recent months became frustrated with Rio Nuevo and architectural planning that called for building the mission, an underground garage and an Origins visitor center without having any other museums in place. "They were talking of building a garage with nothing around it" he said.

Hein was full of questions himself when interviewed last week. He attacked the notion to charge $9 to $12 admission to the city's Tucson Origins Heritage Park - the southern portion that would include the mission, gardens and the Origins Center. "What do you mean 'charge?' " he rhetorically asked. Hein will push for free admission to the city heritage park. Neither the joint University of Arizona Science Center/Arizona State Museum nor the Arizona History and Tucson Children's museums would fall under the free admission mandate. "Where's the (history) museum going?" Hein asked after an initial question about mission construction.

Last year, the national design team, headed by the local architecture firm Burns Wald-Hopkins Shambach, presented a cultural plaza with the science center/state museum on the east side, the history museum and children's museum on the west side and the visitor center at the south end with the mission farther to the south. "It's a change from where we were headed," said Dave Burns, a partner at Burns Wald-Hopkins Shambach. "It's been very difficult to figure out where things are going. We have been instructed to go on hold."

Hein has become disenchanted with the notion of people having to pay to go into the Origins Center, which would have served as the gateway to the mission. "We have to bring something free," he said. So Hein proposes scrapping the Origins Center and moving the Arizona History Museum to the plaza's south end. "They have to provide a free outdoor interpretive exhibit and restrooms and room to store equipment for maintaining the (Tucson Origins) facilities," he said.

Hein wants the history museum, Mission San Agustín and underground garage to open at the same time. This will depend on the timeline for the Arizona History Museum, which is anticipated to open in 2011, said Bill Ponder, chief administrative officer at the Arizona Historical Society, which would build the museum. Ponder said the society intends to have a design team in place by August and potentially start construction on the history museum 14 months later - in fall 2009.

The mission is part of the $53.7 million in Rio Nuevo funding that the City Council allocated in November 2006 to build the public facilities at Tucson Origins: the mission and its gardens, the underground parking garage, a new bridge over the Santa Cruz River and a new street that runs through Tucson Origins and links the bridge and Grande Avenue. The council has committed an additional $130 million to build the UA Science Center/Arizona State Museum, and $60 million for additional Origins museums. The city has spent $15.6 million in Rio Nuevo funding on the Origins project, said Sylvia Amparano, deputy finance director. This involved planning, all the mission design work and landfill removal.

City Councilwoman Nina Trasoff, who chairs the council's Rio Nuevo subcommittee, sees merit in moving the Arizona History Museum toward the mission and shares Hein's misgivings about building an underground garage years before the museums are built. "It makes sense to have the history museum closer to the history," she said. "We're still in discussions about a lot of this. There are no hard or fast decisions that have been made." Trasoff wants the council to make some "hard decisions" in the next month or two in setting a schedule for Tucson Origins.

Mayor Bob Walkup has not had detailed conversations with Hein about these changes, but he is comfortable with what Hein is proposing. "First of all, I don't think anything is in jeopardy," Walkup said. "I think what Mike is doing is playing with the schedule a bit. I think it's the right thing to do. He will tell us the right way to sequence things and what makes sense and how to stay within budget." Hein acknowledged community desires to start construction on the West Side. "Could we move ahead with some of this (specifically the Mission San Agustín)?" Hein posed. "Yes, but it would be void of anything supporting it." Hein's pronouncements end two years' worth of mission construction and completion estimates that changed frequently.

Curiously, in June 2006, the mission's completion date was pegged for 2009-10, but rapidly the start and finish dates became much more optimistic. October 2006, Burns Wald-Hopkins Shambach anticipated starting some construction as soon as March 2007 with the mission possibly opening as soon as 2008. Two months later, the thought was mission construction would start in October 2007. Substantial site work was done in 2007 to do archaeological research and dig two massive holes to remove enough 1950s landfill that is would pile 65 feet high on a football field.

In April 2007, Rio Nuevo officials predicted a November start for the 600,000-adobe-brick mission, but in August the $21.5 million mission project was pushed back to December and ultimately to May-June 2008. In the opening months this year, Hein quietly put the brakes on mission work as well as site planning for the other museums. And no public officials have publicly spoken about the halt in work on Rio Nuevo's signature project - Tucson Origins (without the name at that time) was the principal project that voters approved in 1999 to create Rio Nuevo. "The thing that concerns us is the sensitivity of the order things are built out there," architect Burns said. "We have to figure out how things get built without impacting other things."
 
The city won't be buying Bert Lopez' Hotel Arizona to convert into a Hilton, but will move ahead with plans to build the 30-story Sheraton as the main convention center hotel and purchase the adjacent Norville property for the proposed arena:



HotelArizona-1.jpg

The Hotel Arizona, formerly the Radisson City Center, will not become part of the city's convention center complex,
which is to include a new arena, a new 30-story Sheraton and expansion of the Tucson Convention Center.
(photo: Tucson Citizen)


TCCandhotels.png



Hilton out, Sheraton in for convention hotel
City scraps plan to buy Hotel Arizona, renovate and rebrand it as main TCC hotel

by TEYA VITU
Tucson Citizen
06.06.2008

The Hotel Arizona is out of the equation for the Tucson Convention Center hotel and arena project. Negotiations to buy the Hotel Arizona fell apart because the city and hotel owner Humberto S. Lopez could not agree on a purchase price, said Jaret Barr, assistant to City Manager Mike Hein. "Their feeling of the value of the property and our feeling of the value of the property is far apart," Barr said. "The appraisal came nowhere close to what they wanted." Barr did not disclose either price, but initial talk was for the city to buy the 300-room, 14-story hotel at 191 W. Broadway for $28 million. Lopez was out of town and not available for comment.

The plan was to renovate the Hotel Arizona as a Hilton for the first phase of a project to bring as many as three hotel towers to the TCC area, build a new arena and expand the convention center. The city now plans to make a Sheraton to be built a few steps northwest of TCC the primary convention center hotel, Barr said.

Development agreements will go to the City Council on Tuesday to have Garfield Traub Development build the 30-story, 500-room Sheraton; to buy the 6.67-acre parking lot that sits behind the Evo A. DeConcini U.S. Courthouse from Allan Norville for $17 million; and to have Dev-Con Development serve as the master developer for the entire project. With council approval, Dallas-based Garfield Traub would have 180 days to draw up a preliminary conceptual plan for the $200 million hotel as well as fine-tune construction costs, assemble a financing plan and nail down a construction timeline.

The Norville parking lot, where the GJX gem show is staged each January, likely would be the locale for a new arena. The council expects to know by early August how big a $130 million arena would be. Norville's parking lot would give the city ownership of all the land south of the federal courthouse to Cushing Street and from Interstate 10 to Church Avenue. The agreement with Norville also calls for the city to find a new site for his gem show. The preferred option is building an exhibition hall on top of the convention center, Barr said.

Dev-Con Development would master-plan the project using a 5 percent management fee derived from contracts for urban planning and engineering and for infrastructure and landscaping projects around the convention center. The city would advance $200,000 to Dev-Con that would be reimbursed as contracts are issued, Barr said.
 
$200 million for a 30-story Sheraton? This sounds like Phoenix's hideous 30-story new convention center Sheraton, but at half the money. I shudder at what this will look like.

It might make that 1960s blue-slab-sided building (with no windows) in downtown Tucson look nice by comparison. Be very afraid, Tucsonians.

--don
 
Not sure why you suddenly care Don B. You haven't cared about keeping the Tucson page for the Emporis site up to date in forever, but you sure do LOVE Phoenix don't you. You put the Century Tower on hold, even though it's been DEAD for years now. You have the Diamond Rock Plaza down as proposed, when it's clear that's not going to happen. You don't even mention the proposed 30 story Sheraton. It sounds like your comment is more poking fun than anything. Come back when you actually have an interest.:hell:
 
^^Please note that the Tucson Sheraton, currently planned for 30 stories and 700* rooms, will not be nearly as large as the Phoenix Sheraton with 1,000 rooms and more than 80,000 s.f. of meeting space. (*The Citizen's article quote of 500 rooms looks like an error, and is at odds with the city's own RFP requirements as well as Garfield Traub's proposal, as both state 700 rooms.)

The oft-quoted $350M cost for the Phoenix Sheraton is the total debt (i.e., bonds) incurred by the city, and includes amounts for FF&E and contingencies--not unusual for municipalities that build their own convention hotels (e.g., Denver's Convention Center Hyatt cost $286M to build, but the city's total debt was $368M http://www.hotel-online.com/News/PR2008_2nd/Jun08_DallasCCHotel.html).

About a year ago, Southwest Construction pegged the cost to build the Phoenix Sheraton at $197.8M (http://southwest.construction.com/images/AZ_TP.pdf), so the $200M estimate for Tucson's hotel is not unreasonable; although with the spiraling cost of materials, new estimates will be probably be higher.
 
Last edited:
Downtown redevelopment is progressing
Our view: Postponed groundbreaking sensible change; plans need council vetting

Tucson, Arizona | Published: 05.30.2008

It seems as if Rio Nuevo, the city's ambitious redevelopment plan, takes two steps back for each step forward. But that's not so.
There is steady progress being made, though perhaps not as quickly or as gracefully as we all wish.
The most recent apparent setback is that City Manager Mike Hein has postponed the groundbreaking on the West Side site for a Tucson Origins Heritage Park and decided not to build the Origins Center, a structure that would have served as a entry point where visitors could orient themselves to the park. Visitors also would have been charged admission to the park, which will house a reconstructed Mission San Augustín and Convento and museums, including the University Science Center, the Arizona State Museum and the Arizona Historical Society Museum.
The Origins Center "wasn't needed and I think the City Council has been clear that they didn't want admissions charged," Hein told us on Wednesday. "That's the only thing we've scrapped."
He said the Historical Society Museum will instead likely serve as a "portal" to the park
The projects that were set for groundbreaking were the mission and an underground parking garage. Hein postponed the start of work, he said, because the layout of the site is not resolved and only the University Science Center and the Arizona State Museum, which will be in one building, are in the design process.
"There is no halt to the project. But you do not build a parking garage without knowing how you're going to pay for it. Yes, we will have TIF (tax increment financing) money for sure, but there will also be license agreements with museums for a certain number of spaces. We're looking at retail, a restaurant," Hein said. "You don't want an empty garage with no revenues to pay for it, and you don't want a convento with nothing else there."
Councilmember Steve Leal, a Democrat from Ward 5 and a member of the council's Rio Nuevo/Downtown subcommittee, told us that he heard about the possibility of a halt a week ago but did not know it was imposed until media reports Wednesday.
Leal said it was too significant an issue to be decided privately and that the council should have been consulted. The council voted on the project and the timetable, he said.
Only Mayor Bob Walkup and Vice Mayor Nina Trasoff, a Democrat from Ward 6 and chairwoman of the Rio Nuevo/Downtown subcommittee, knew about the schedule change, he said.
Hein said the postponement "isn't news" and that the council was aware of it.
"We're trying to stage everything appropriately so that one project doesn't get in the way of another," Trasoff said.
"It is like a three-dimensional chess board: One level is planning where things go; another is planning a timetable of what goes in when and how they interact; the third level is how we work out financing," she said. "We know we will have $550 million over the course of the TIF, but not all of that will be in our hands in the first five years."
Leal said the City Council wants to see "cranes in the air." So do we. We have been disappointed by Rio Nuevo's slow start.
If council members feel they need to be updated more often, they should be. And the planning process should be open and transparent.
But we must not overlook progress being made on Downtown redevelopment.
● The Fourth Avenue underpass work is well under way and tracks are going in for a modern streetcar that will link the university area to Downtown.
● On May 11, the council approved the concept of a pedestrian bridge over the Santa Cruz River along Cushing Street; an extension of Cushing would be the northern border of the Origins park.
● A month ago, the council approved $2 million for the Historical Society to begin the design process for its new museum.
● Hotel Congress owner Richard Oseran has received $280,000 in free rent to take over the 4,000-square-foot space that was formerly the Central Bistro restaurant across Toole Avenue from his hotel. He will open a market and restaurant.
● The former Martin Luther King Jr. building is under reconstruction as One North Fifth, an apartment building with retail shops on the ground level.
● The former federal court annex at 44 E. Broadway is under reconstruction as 44 Broadway, with loft residences and retail planned on the first level.
● The Mercado District at Menlo Park, a mixed-use project, is being built by Rio Development Co., south of Congress Street near the park site.
● The archeological work has been done on the park site and so has remediation work.
● The city will be using $530,000 from a Business Development Finance Corp. account to offer matching grants to finance facade improvements for property owners of Downtown buildings constructed before 1948.





Ambitious plan holds promise for Downtown

Our view: Arts agency, charter school, private company are joining forces; pact could benefit students, artists, city's core

Tucson, Arizona | Published: 06.06.2008

Here's a bit of Downtown redevelopment news that has nothing to do with Rio Nuevo or the city government.
A private citizen, his company, the nonprofit arts group whose board he chairs and a Downtown charter school are teaming up to make something exciting happen on a dingy block of Sixth Avenue between Congress and Pennington streets.
We hope it turns out to be as successful as its creators expect.
The Star's Rhonda Bodfield reported earlier this week that starting in the fall, some 60 students in Grades 6 though 8 will begin taking arts classes at ArtFare the Muse. High school students would follow the next year.
The students will come from the Tucson Academy of Leadership and Arts, a K-8 charter school with 100 students operating at 210 E. Broadway.
"Our story is about combining ArtFare's efforts with this charter school to create the first truly comprehensive arts charter school in Tucson and to revitalize this part of Sixth Avenue," Fletcher McCusker, chairman and CEO of Providence Service Corporation and board chairman of ArtFare, told us.
The school will sublease space at ArtFare, which has struggled in past years to make its rent. Most of the ArtFare classes and programs now go on at night, so they won't conflict with the school's classes, McCusker said.
Qualified artists who are associated with ArtFare will be invited to teach at the charter school, he said.
"In fact, many of them are former educators who became disenchanted with the traditional educational system," McCusker said.
The charter-school relationship will be worth about $100,000 a year to ArtFare, Bodfield reported.
McCusker envisions classes in everything from Big Band music and painting to theater, ballet, film production and photography.
"Of course, the school will have to attend to its core curriculum. Students have to pass the AIMS test," McCusker said. "They can't all be wandering around playing gypsy music."
The charter school has been rated as "underperforming." Its parent company, the Global Education Foundation, is contracting with McCusker's company to provide what he calls "back-office services."
Providence is publicly traded, based in Tucson and offers privatized social services, including mental-health care and juvenile justice, in 36 states.
The charter school will pay Providence a fee of 3 percent to 5 percent of revenue, which comes from state per-student payments, McCusker said. Providence will provide administrative staff, human-resources functions, record keeping, an office receptionist and such, McCusker said.
Providence already has recruited a new principal, Leon Butler, formerly principal of a "performing" Lake Havasu charter school.
Bodfield reported that Butler is already reworking the curriculum and adding teachers.
The plan still needs approval from the Arizona State Board for Charter Schools.
The school's per-student "tuition" income "doesn't begin to cover costs," said McCusker, who also sits on the board of St. Gregory College Preparatory School and is a member of the University of Arizona's Eller College Board of Advisors. "It will have to do fund-raising, and we think my name and the Providence name will give it momentum."
Bodfield noted that the Tucson Unified School District runs the Artworks Academy, an arts-based high school Downtown, at the Tucson Museum of Art. City High School, a Downtown charter school, features an arts-enrichment program.
Tig Collins, ArtFare director, pointed out to Bodfield that the Arizona Jazz Academy's middle-school and high-school bands meets at ArtFare after school and on weekends, and children participate in many of its programs, from martial arts to dance.
McCusker is excited about revitalizing the stretch of Sixth Avenue where ArtFare is housed in several buildings across from the Ronstadt Transit Center.
"Sixth Avenue was never in any of the Downtown redevelopment plans, and those are kind of neat buildings," he said.
Along with building improvements, his vision calls for a promenade area for street vendors, a café, some retail presence and wandering musicians, Bodfield reported.
Imagine that: A private effort to symbiotically prop up a struggling nonprofit, help a failing charter school blossom into something remarkable and revitalize a key section of Downtown Tucson.
If it works, it will be something we all should applaud — and an innovation other cities will want to replicate.
 
Future of TCC may be up on the roof

l87548-1.jpg


City floating idea of $54M exhibition hall on top of the convention center
TEYA VITU
Tucson Citizen


The Hotel Arizona could become an assisted-living home, and the GJX gem show could move onto the roof of the Tucson Convention Center.
Those are the latest notions floating about in connection with the city's plan to build a new arena, expand TCC and bring 700 more hotel rooms to serve the convention center.
The convention center and hotel project will be discussed at 2:30 p.m. Tuesday at the City Council's study session in the Council Chambers, 255 W. Alameda St.
That discussion will include a development agreement with Garfield Traub Development to build a 30-story, 707-room Sheraton hotel a few steps northwest of TCC. The tentative start date for construction is May 2010 with a potential opening date in May 2012, Rio Nuevo director Greg Shelko said.
The city's agreement to buy Allan Norville's 6.67-acre parking lot behind the Evo A. DeConcini U.S. Courthouse includes building an exhibition hall where he can stage his GJX gem show, which for years has filled a massive tent on Norville's parking lot.
The first idea is a $54 million tensile fiber membrane roof structure on top of the TCC. Tensile roofs were used for the Millennium Dome in London and the Olympic Stadium in Munich, Germany.
"We're not asking for the allocation of money now," said Jaret Barr, assistant to City Manager Mike Hein. "We are introducing the concept. We would only do it if it fits into the overall convention center plan."
If the council approves buying Norville's land for $17 million, he would lease it back from the city to continue staging his gem show there until a replacement hall is built, Barr said.
The city this week lost interest in buying the Hotel Arizona, so owner Humberto S. Lopez is getting a second appraisal and weighing his options for the property at 181 W. Broadway. Lopez wanted $28 million and he said the city offered about $21 million.
"I'm just going to go out and decide what I'm going to do," Lopez said. "If the highest and best use is an assisted-living center, that's what I'll do. If the highest and best use is to sell, that's what I'm going to do."
Lopez said the city's appraisal undervalued the hotel because it assumed the convention center would attract only low-budget conferences.
"Based on those assumptions, you can't justify building a new hotel," Lopez said of the city's plan to move forward with the Sheraton. "I think the city is going to be a loser on the deal."
 
Not sure why you suddenly care Don B. You haven't cared about keeping the Tucson page for the Emporis site up to date in forever, but you sure do LOVE Phoenix don't you. You put the Century Tower on hold, even though it's been DEAD for years now. You have the Diamond Rock Plaza down as proposed, when it's clear that's not going to happen. You don't even mention the proposed 30 story Sheraton. It sounds like your comment is more poking fun than anything. Come back when you actually have an interest.:hell:

Gee, thanks. Maybe it's because I have a life and can't devote more time to something which amounts to a volunteer project. You have to remember that I'm in law school, work part-time as a paralegal (in Prescott, of all places!) during the semesters classes are in session and full time during the summer, and run a photography business year round. I also am very active in charity organizations, including being the staff photographer for the Imperial Court of Arizona, amongst other things. Then there are the things I like to do for myself, such as computer gaming, hiking, playing D&D with friends, movies, etc.

If you don't like "the job" I'm doing, feel free to join Emporis and contribute your efforts for free to a company that profits from your labors, instead of pounding out ill-founded rants from your mommy's keyboard.

Now, if you don't mind, Sins of a Solar Empire is calling my name, and the Vasari need to be eliminated. Good day to you, sir.

--don
 
the city needs to take a chance and build the hotel ASAP so it will be a stimulator for other projects to get under way and encourage private sectors to invest more downtown. this time is perfect to encourage downtown and urban development while sprawl has slowed with our current market in oil and housing/construction. i just feel downtown tucson has so much potential but the city always finds a way to delay/cancel or underachieve projects. tucson downtown has not developed enough to represent how large and grandiose the city has grown in the last couple of decades.
 
Thats just it though, the city will not take a chance on anything, they rather do nothing than something even something small. and i agree, downtown Tucson has potential. i see it everyday when im at work.
 
Gee, thanks. Maybe it's because I have a life and can't devote more time to something which amounts to a volunteer project. You have to remember that I'm in law school, work part-time as a paralegal (in Prescott, of all places!) during the semesters classes are in session and full time during the summer, and run a photography business year round. I also am very active in charity organizations, including being the staff photographer for the Imperial Court of Arizona, amongst other things. Then there are the things I like to do for myself, such as computer gaming, hiking, playing D&D with friends, movies, etc.

If you don't like "the job" I'm doing, feel free to join Emporis and contribute your efforts for free to a company that profits from your labors, instead of pounding out ill-founded rants from your mommy's keyboard.

Now, if you don't mind, Sins of a Solar Empire is calling my name, and the Vasari need to be eliminated. Good day to you, sir.

--don

Nice try Don, that would be a great comeback if the Phoenix Emporis page was in just as poor a state as the Tucson page...but it isn't, and Tucson's page is 10 times smaller! You took the responsability of taking on the two pages KNOWING it was a volunteer job, so don't give me your cry baby sob story on how busy you are, you've been using the same excuse for months now. Quit then and give it to somebody who can handle it, if you're crying that you can't.

I wouldn't have even cared if you'd stuck to your own Phoenix thread and not come to the Tucson page and take a jab at our skyline. If you can't take the shit don't shovel it buddy.

"mommy's keyboard"..LOL!!! You go boy :haha:
 
^ Because of your nasty comments, I'm going to go one better: I'm going to purposely neglect the Tucson Emporis page from now on. I'm going to let it rot, yet remain an editor, which should really get your goat.

And to think I was about to post up a thread of very cool ground level Tucson pictures I took with my wide angle lens from two weeks ago. Not now or ever again, and don't worry, I won't return to this thread to "jab" at your skyline, as you think my one comment about the proposed downtown Tucson Sheraton was supposed to represent.

"How To Win Friends And Influence People," by aznate27. Not!

:haha:

--don
 
Hell...I was just looking forward for some of the DON's always MARVELOUS images. Way to go Nate.

On a side note, I was thinking of hitting up downtown this weekend and taking pics of what little progress we have going on here. I'll see what I can do but i'm working everyday this week so my best option would be Sunday.


Don,

you've seen the Tucson Sheraton rendering.....you know we're afraid. The Phoenix Sheraton does have a 70's feel to it though.
 
Something that I would like to see is the progress of the streetcar system. At first, its just going to run around the downtown Tucson area right?... and then later, a spur line will be run over to the UofA campus correct?

It would be nice if someone could post some progress pics or renderings again. I would especially like to see what the trains(cars) look like; I have sort of forgotten.
 
^ Tucson is considering a modern streetcar route.
See this webpage...
Edit: oh, I guess you were just unclear about tempedude's post... which is a little unclear (re "progress pics"). The modern streetcar line has not opened or even begun construction.
 
uh, see how much I know...

I am referring to the new expanded historical trolley route. (new track laid and some new stations too?)...supposed to be complete sometime early 2009?

And I guess what I am/was thinking is that the proposed modern streetcar route will connect UofA with the trolley system downtown. Do have it right this time around? :haha:
 
Last edited:
^ Because of your nasty comments, I'm going to go one better: I'm going to purposely neglect the Tucson Emporis page from now on. I'm going to let it rot, yet remain an editor, which should really get your goat.

And to think I was about to post up a thread of very cool ground level Tucson pictures I took with my wide angle lens from two weeks ago. Not now or ever again, and don't worry, I won't return to this thread to "jab" at your skyline, as you think my one comment about the proposed downtown Tucson Sheraton was supposed to represent.

"How To Win Friends And Influence People," by aznate27. Not!

:haha:

--don

So, basically you're going to do exactly what you've been doing as the editor for over a year...nothing. What a surprise. Way to stick it to me Don :rolleyes: . Believe me, I won't be missing anything, there hasn't been anything to miss.

And as far as your pics..there are are a few hundred other sites we all can go to with photographers just as good (and I suspect better) with plenty of pics of Tucson. Suggesting that your pics are a wonder to behold and we're missing out just shows your arragance.

Good riddance.
 
The pending relocation of Madden Media's headquarters to the historic MacArthur building is a glimmer of hope for expanding the downtown workforce:



McArthurBldg.jpg

The MacArthur building was built in 1907 at 345 E. Toole Ave., and was first known as Hotel Heidel. The 22,000-square-foot, three-story building between the Hotel Congress and the Historic Train Depot later became the MacArthur Hotel, and since the 1980s it has housed offices. The city bought it in 2005. It stands ready now for redevelopment. The leading bidder is Madden Media. (photo: Arizona Historical Society)



MacArthurBldg-today.jpg

The MacArthur building--a century later. (photo: Tucson Citizen)



Madden move would be boon to Downtown
Our view: City should strive to ink deal with local publisher for MacArthur building

Arizona Daily Star - Opinion
06.18.2008

Madden Media, for 25 years a Tucson-based national company, is on the verge of moving its headquarters into a historic building in Downtown Tucson. T's must be crossed, and i's dotted with the city, but CEO Kevin Madden told us "I'm hopeful that all of Downtown can be a happening place, and we want to participate in that." Assuming the deal goes through, it's great Downtown economic development news and should lift the spirits of at least a few of the nay-sayers on Downtown revitalization.

Madden bid the full appraised value, $1.7 million, for the historic MacArthur building, a three-story flatiron structure built across from the train depot at 345 E. Toole in 1907. First as the Hotel Heidel and later as the MacArthur Hotel, it served as a hotel for the railroad. It was converted into office space in the 1980s. The city bought the building and an adjacent lot for $2.9 million in 2005. MacArthur houses the city's department of urban planning and design, which Glenn Lyons, chief executive of the Downtown Tucson Partnership, said will move to another city-owned building at 149 N. Stone.

The city is building a parking structure on the adjacent lot. "We want to make it into a signature building — our worldwide headquarters," Madden said. "Ninety percent of our revenue comes from outside of Tucson. We are importing revenue; we do the work here and ship it all around the country."

The proposed deal will go before City Council on July 8, according to Lyons. A backup deal, also for $1.7 million, is on the table from Bourn Partners, who — unlike Madden — would need financing and tenants, Lyons said. Assuming the council signs off, Madden wants to begin demolition and reconstruction — updated air conditioning, sprinklers, et cetera — on Jan. 1, so the company's 80 local employees can move from their East Fort Lowell Road digs to the refurbished headquarters on June 1, 2009.

Madden Media publishes Tucson Home and Tucson Guide magazines as well as the Metropolitan Tucson Convention & Visitors Bureau's visitors guide. "Our contingencies have to do with being assured we be able to get through permitting, demolition and rebuilding so we can move June 1," Madden said. "Our lease is up at the end of June. ... That's the best time in our business cycle to move. If it gets postponed by much, my cost is enormous, incalculable. ... We are too busy to stop what we're doing and move for two or three weeks."

Lyons said some of the permitting work has already begun. "It's a tight schedule, so it's helpful to council to know that we can solve these issues sooner rather than later, even though council hasn't officially okayed the deal," he said. Madden's other issue is safe parking close to his headquarters. "We have a lot of very creative young people who work nights and weekends." The new parking garage in the adjacent lot south of the MacArthur building is under construction, and Presidio parking is a block or so west.

What made Madden decide to go Downtown? "Just the repeated statements that it's for real and because the (Rio Nuevo) money is there," he said. "We would really like to be a leader of this. "There will eventually be a big impetus for these employees to want to find someplace to live close to the office," Madden said. "The economic impact is going to be much further reaching than getting lunch, buying coffee, having drinks after work Downtown."

Lyons and City Manager Mike Hein appear to be doing all they can to make the deal come to fruition. We hope Tucson City Council is able to sign off on the deal. It's great news that a fine local company is willing to invest in Downtown; we expect many others to follow suit.
 