South Side big-box store may not open till 2009

By Rob O'Dell
Arizona Daily Star
Published: 12.21.2007


Welcome to page 26!!!

South Side residents who strongly backed construction of a major big-box store during two years of contentious city negotiations may have to wait until 2009 to shop there. Six months after the big-box won City Council approval — plus the OK for more grocery space than allowed by city law — some residents are questioning the lack of any development work on the 350-acre site at East 36th Street and South Kino Parkway.

But the players involved in building the retail center, housing subdivision and biosciences park have worse news for area residents: It's likely construction work won't even start for another year. That would push the opening of the big-box back until at least early 2009. Because of a large and complex flood-control project being built there by Pima County, preliminary development work isn't likely to start until the fall, with construction work not commencing until late 2008.

"It's really difficult for us to start development until those improvements are done," said Bruce Wright, associate vice president for economic development for the University of Arizona, which is building the biosciences park. Area resident Cecilia Campillo said the delay is hugely disappointing for the neighborhood, and that it reinforces the widely held feeling that "we're always waiting on the South Side for progress."
She said another grocery store is needed to lower high food prices on the South Side.

Campillo said the council talked and talked about the deal for two years before finally giving approval in April. Now that construction won't start for another year, Campillo said the project will have taken about four years to be completed from the time it was first proposed. "It's beyond patience," Campillo said. "We shouldn't have to wait until next November. But what do we expect with the leadership we have on council?"

Dubbed The Bridges, the project calls for a big-box store as part of 110 acres for a "power center" — to include 1 million square feet of retail space to be built by Eastbourne Investments Ltd. and its partner, Idaho-based Retail West Properties. The big-box might be a Wal-Mart, but that is not specified in the plans.

About 110 acres are proposed for an upscale KB Home housing development and a 65-acre biosciences park to be developed by the UA. KB Home, the UA and Retail West Properties said they are eager to start construction but need to wait until the Pima County Regional Flood Control District project is finished. The county hopes to complete the $4.5 million project before monsoon rains start in mid-summer, said Chris Cawein, deputy Flood Control District director. In addition, all involved said it was hard to get the three parties on the same page and then deal with the city and county governments.

"We can't wait to get started," said Eric Davis of Retail West Properties. "It takes a long time to get three entities like ours to agree on this."

He added: "This time next year we'll be building buildings."

While all parties agree the retail component will get under way first, KB Home's Tucson Division President John Bremond said his company wants to follow right behind the big-box with a residential project that would start construction in late 2008. The delays are standard operating procedure for these types of projects, Bremond said. The UA, for its part, would begin site improvements in late 2008and bring in a private-sector partner, which would begin development work sometime in 2009, Wright said.

To curb flooding that occurs downstream to the northwest of the project, the county is constructing a 5-foot-diameter concrete pipe buried 13 to 16 feet below ground that would carry water from the site, under Interstate 10 and south to the Tucson Diversion Channel, Cawein said. A detention basin will also be constructed on the site. Cawein said the county is "bucking the grade" of the site to change the flow of the water to the south instead of the northwest — which floods the nearby South Park neighborhood. That flooding would get much worse if the now-vacant 350 acres were fully developed, county officials said. Cindy Ayala, president of the nearby Pueblo Gardens Neighborhood Association, said the flood-control project is the most important piece right now because otherwise, "South Park would be flooded out." Ayala was sanguine about the construction delay. "We'd like to see something start," she said. "Things take time."
 
Two firms might link up on Rio Nuevo work

By Rob O'Dell
Arizona Daily Star
Published: 12.28.2007


Helped by a nudge from the city, two developers vying to build on 14 acres on the West Side may join forces to co-develop the last remaining available Rio Nuevo parcel west of the Santa Cruz River. Although both sides say the talks are preliminary, representatives from the Gadsden Co. of Tucson and Williams and Dame of Portland, Ore., both said the joint venture would include site development and infrastructure work on the 14 acres to get it ready for construction.

From there, each developer would build its own projects on the part of the site awarded to it by the city — a split that has yet to be determined. City officials said a final decision to award development rights could come within a month. Collaborating on infrastructure and then having the builders construct their own projects "would probably make the most sense," Williams and Dame spokesman Matt Brown said. "I don't think we would work together on every building," he added.

Brown said Williams and Dame began talking with the Gadsden Co. at the urging of city officials who asked the two finalists to look for a "way to combine the best elements of both proposals." But Brown said the two developers had not yet sat down to talk in person and hash out the details. He said that would come sometime after Jan. 1. The Gadsden Co.'s Jerry Dixon laid out the same case for working together, also stressing that talks are preliminary."There were elements of our plan that were good, and elements of their plan that were good," Dixon said. "Maybe together we could make a better project. That's the incentive for talking."

Gadsden's proposal includes 400 homes — 35 percent of which will be affordable "work- force housing" — and a 125-room boutique hotel along with commercial development. Meanwhile, a streetcar station is an important part of the Williams and Dame proposal, as the westernmost station of the planned modern streetcar connecting the University of Arizona with the west side of Rio Nuevo will be located on the site.

Williams and Dame's proposal features mixed-use commercial and residential, with retail on the first floor and residential units above. Plans also include a mercado and pedestrian areas. The city put out a request for bids in early 2007 for developers interested in building there. Three developers submitted proposals in late June, with the Gadsden Co. and Williams and Dame chosen as finalists in late August. A city panel is set to pick a winner in mid-January, if the two sides don't agree to work together beforehand.

The acreage is bounded by the Santa Cruz River, Congress Street and two planned new roads — the north-south Avenida del Convento and the east-west extension of Cushing Street. The property is just north of the planned Tucson Origins Heritage Park and several museums proposed for the West Side. It is directly east of the Mercado at Menlo Park, a mixed-use project now being built by Rio Development Co., which is run by Dixon's son.
City Manager Mike Hein said the city encouraged the two sides to talk about combining proposals but added it's not a requirement.

"Absolutely, I've been a proponent of having the private sector work together if it's in their best interest," Hein said. "But only they can determine that."
Asked if the move to combine the West Side proposals was similar to the way the city chose three of the four finalists when it awarded development rights in November to build a new convention center hotel, Hein said the two are somewhat similar. "I can see where people would draw that analogy, but the West Side is different," he said, adding it is confined to one site when the hotel proposals encompassed several locations.

Still, Hein said the city is ready to move in January if the two developers can agree. "If they move forward with a partnership we would probably move forward pretty quickly."
 
Phoenix developer to plan huge Southeast Side site

12,000-acre area may take 40 years to finish, could create 'second city'
218719-1.png

By Rob O'Dell
Arizona Daily Star
Published: 01.02.2008


advertisementGiant Phoenix mall developer Westcor will soon secure a permit to create a master plan for 12,000 acres of state land on the Southeast Side along South Houghton Road. Several Tucson officials say the project will be one of the biggest in Tucson's history, creating a "second city" with residential and commercial development along with open space.

The site is so large that development there is not expected to be completed for 40 years, said Deputy State Land Commissioner Jamie Hogue. Although the final papers have not been signed, officials from the State Land Department and Westcor will gather at City Councilwoman Shirley Scott's office at 8:30 a.m. Jan. 11 to celebrate inking the deal.

Westcor would not immediately develop the 12,000 acres, which run from South Harrison and East Irvington roads south to the Union Pacific Railroad tracks and east beyond Houghton Road to the Pantano Wash. A large parcel south of the railroad that straddles Interstate 10 will also be included. Instead, Hogue said Westcor would spend millions over the next year planning the future uses of the massive site, which incorporates nearly all of the state land on the Southeast Side.

City officials said Westcor, the developer of La Encantada shopping center in the Foothills, could spend as much as $12 million over the next year just to plan the site. "We're in the final stages of the process," Hogue said. "It will be a combination of all land uses, whatever is suitable." State Land Commissioner Mark Winkleman signed three orders Dec. 20 to declare the land suitable for development, to OK commercial development there and to approve Westcor's concept plan.

Mitch Stallard, vice president of Westcor, declined to give details of the company's conceptual plan, citing the fact that the permit hasn't been issued yet. He deferred most questions to the State Land Department, but said the two sides were on the cusp of an agreement. "Until the permit is granted there, we can't really talk about it," Stallard said, adding that lawyers for the two sides are finalizing the "ABCs of the deal." "We believe all the documents can be fully executed within two weeks," he said.

Westcor is a high-end shopping-complex developer based in Phoenix. In addition to La Encantada here, Westcor's other developments include Scottsdale Fashion Square mall and Kierland Commons in northeast Phoenix. Although Westcor would create the master plan for the 12,000-acre site, the state would retain ownership, Scott said. Parts of the property would then be sold to the private sector at auction, she said. "The state is in charge of the sale of that property," she added.

Hogue, the deputy land commissioner, said if Westcor does not win some of the land at auction, the company is eligible to be reimbursed for some of the planning expenses. She said this is the second-largest project the Land Department is planning; the largest is a huge project outside Phoenix.
"This is probably 40 years of land," Hogue said. "This isn't something where we go out and sell it all tomorrow."

Tucson City Manager Mike Hein said it's an open question as to what happens to the Houghton Area Master Plan, a much-touted city planning effort that covers part of the area Westcor will receive a permit for. Scott said she believed some principles of the Houghton master plan will be incorporated into Westcor's plans, but said the Houghton plan only covers a small portion of the whole Houghton Road Corridor. Mayor Bob Walkup touted the project during his January 2007 State of the City speech, although it has since been expanded from 8,000 acres to 12,000 acres. He said the project would bring "the highest-quality master planning and managed growth" to Tucson, and upon completion will bring new residences, stores, businesses and jobs.

Scott said the 12,000 acres could eventually be a "second city" or employment and commercial hub of Tucson. "I'm pleased a company of this stature stands ready to receive this permit — finally — to plan the Houghton Corridor," she said. The railroad tracks extend diagonally southeast from the UA Science and Technology Park.​
 
Last edited:
Tucson's upcoming roll-of-the-dice to expand its convention center and build an accompanying new hotel reflects a similar pattern in metropolitan areas across the country. However, the financial payoff of those investments is often less than spectacular:


RichSinger.gif

Rich Singer: "People are shocked when I say Tucson isn't in the convention business.
There's a huge upside for growth here." (photo: Kelly Rashka)



The Risks of 'Revitalization'
Tucson is about to commit hundreds of millions of dollars to a new convention center. Will this be money well-spent--or will it become another boondoggle like Tucson Electric Park?

By DAVE DEVINE
Tucson Weekly
January 10, 2008

For decades, Tucson has stayed out of the national convention race. But now the city plans to enter the intense, costly and financially risky competition for convention business--in a big way. "People are shocked when I say Tucson isn't in the convention business," says Tucson Convention Center director Rich Singer. "There's a huge upside for growth here."

Heywood Sanders, professor of public administration at the University of Texas at San Antonio, believes otherwise. He's done a detailed analysis of the financial performance of convention centers and publicly owned adjacent hotels, and he concludes: "The capacity of boosters to participate in foolishness (is amazing)."

To introduce Tucson into the nationwide convention competition, Singer believes the community should remodel, in phases, the existing TCC, which opened in 1971. The cost of those remodels: up to $123 million. Singer also thinks the city should use its Rio Nuevo funds and tax-free bonding capacity to build a new, publicly owned convention-center hotel priced at $200 million, while erecting a new arena estimated to run $130 million.

Singer points out the potential attractiveness of Tucson if these improvements are implemented, based on survey results from a nationwide group of meeting planners. "But we have to do them all," he insists. "That's the beauty of it. We're fixing everything. ... The variety of projects (in Tucson) is really important to downtown. The diversity of people they will attract will make it work."

Sanders, who knows quite a bit about Tucson's proposed convention-center upgrades, is skeptical--especially when it comes to the convention-center hotel idea and its optimistic financial predictions. "If I was on your City Council," he says, "I'd be really scared."

The 707-room hotel, to be owned by the city but managed by Sheraton, will not only cover its own expenses, but also earn a profit, backers say. The Tucson City Council has already endorsed the project. These profits, boosters say, could be used to help renovate the existing Hotel Arizona, next to the convention center, and buy a strategic piece of vacant property nearby. Alternately, the profits could help cover the cost of the proposed new arena.

But Sanders can list case after case of convention-center hotels which were predicted to be profitable but actually turned out to be money losers--in cities from Omaha, Neb., to Myrtle Beach, S.C., to Sacramento, Calif. As one specific example of fiscal reality, he points to Overland Park, Kan. Opened in December 2002, their 412-room convention hotel was paid for with close to $92 million in bond funds. According to projections, the revenues of the facility should have easily covered the bond's debt service.

That hasn't happened, admits Kristy Stallings, deputy city manager of Overland Park. Approximately $5 million in guest-tax money has been poured into the project to cover the bond payments. Despite that subsidy, Stallings labels the hotel a success. "The hotel is actually doing very well," she says, "and is the market leader in all measures that matter."

Charles H. Johnson IV agrees with that assessment. His Chicago consulting firm did feasibility work for the Overland Park hotel as well as for the Tucson Convention Center, and he considers the Kansas project a success. Stallings blames the decline in travel after the Sept. 11 attacks, along with the ensuing downturn in the nation's economy, for Overland Park's publicly owned hotel performing below expectations. "It didn't generate the revenues forecast," she says, "but that's always a risk."

Those are risks more and more municipal governments are willing to take as they get into the convention-center hotel business. "But as cities across the country rush to build hotels and claim convention riches," notes the Baltimore Sun in a 2005 article, "some find horror stories and others, a mixed verdict."

Singer doesn't believe that will occur in Tucson. When asked about the chances of the convention-center hotel not making a profit, he says: "I don't see that happening." Such optimism is based on several factors. First, the planned remodeling of the TCC is expected to bring in a substantial number of new meeting-goers who will want to stay in the hotel. Added to that is the lack of quality hotel rooms currently existing downtown. Finally, Singer hopes to make Tucson a regular stop on the East Coast-West Coast rotation of some convention groups.

These factors were highlighted in a convention-center feasibility report prepared last March by C.H. Johnson Consulting. It concluded: "With these expansion recommendations, a headquarters hotel and an arena function removed from the center, the TCC will become a highly effective and balanced venue."

The Johnson firm also took a look at the convention-center hotel proposal. In its June 2007 analysis, it predicted the facility would have annual income above expenses of more than $11 million. That figure, however, does not include debt service on the bonds which would be used to construct the hotel.

Since Johnson's study was released to the Weekly only recently, Sanders in Texas hasn't seen it, but he is skeptical of its findings nonetheless. Based on his analysis of other predictions made by Johnson's firm, Sanders says: "Their forecasting record is open to some serious questions. ... In case after case, their forecasts didn't happen."

In response, Johnson calls Sanders "a thorn in the industry for a few years," and rolls off several convention-center projects he's been involved with which he says have seen substantial growth in revenues. These include Austin, Texas; Nashville, Tenn.; San Jose, Calif.; and Portland, Ore. However, Johnson admits he's using anecdotal evidence, since his firm usually doesn't track what happens after its projections are made.

According to additional information supplied to the firm by some of its clients, the convention center in Jackson, Miss., had 8 percent more event days in 2006 than the Johnson company forecast. Between 2003 and 2006, Osceola County, Fla., also collected considerably more in taxes than the firm had predicted.

If the convention-center hotel in Tucson is as risky of a business venture as Sanders predicts, the development team behind the Sheraton proposal has given City Hall a possible way out: They have offered to assume ownership of most of the hotel if the city contributes financially to the construction costs. "That private/public approach requires a pretty significant infusion of dollars," says the city's finance director, Jim Cameron. "It makes more sense to go public ... because it creates advantages and benefits from the hotel's revenue stream."

Sanders doesn't believe that revenue stream is likely to even cover the costs of the bonds which will be sold to pay for the hotel's construction. He insists there will have to be government backing of the bonds if they are to be sold, and that backing may have to be used repeatedly, as in the case of Overland Park.

Government backing of bonds is exactly what Phoenix is doing with their publicly owned Sheraton convention-center hotel, now under construction. The 1,000-room facility will be paid for with $350 million in bonds, approximately 55 percent of which will be backed by rental-car and hotel-tax receipts. "I don't know anybody who has really focused on the bond backing," Cameron says about Tucson at this point. "I don't think it's necessary right now."

If the local backing of the bonds is required, Cameron thinks the tax incremental financing provided to downtown's Rio Nuevo district might be one potential source of funds. "But we have many other projects," Cameron says of this pot of money, "so we don't want to tie it up."

Without City Hall pledging some local revenue to help pay for the hotel if needed, Sanders says it just won't be built. He says that bond underwriters learned their lesson from a financially disastrous convention-center hotel experience in St. Louis a few years ago. "The (governmental) backing is needed, because these hotels perform rather more modestly than predicted, often doing half to two-thirds of the business anticipated."

This financial give-and-take should sound familiar to anyone who has been around town awhile. A decade ago, county officials promised that no additional taxpayer money outside the identified revenue streams would be needed to pay for the southside baseball stadium, Tucson Electric Park. In addition, officials forecast a retail renaissance along Ajo Way near the ballpark. However, these commercial improvements have largely failed to materialize. Instead, only county-owned facilities moved into the neighborhood.

At the same time, the revenues for the park fell well short of projections (See "Squeeze Play," Feb. 24, 2000). That led to some restructuring of the stadium debt, but even that wasn't enough. Almost $6 million in cash had to come out of county coffers to pay for the park. In addition, two years ago, $485,000 in county general-fund money was used to help pay the debt service on the bonds. To compound these problems, the publicly owned stadium is now in the process of losing two of its three professional-baseball tenants, one of which is heading to a Phoenix suburb.

The uncertain future of Tucson Electric Park could cast a monsoon-sized shadow over the TCC proposal. But in Tucson, governmental monetary and redevelopment forecasts always seem to be sunny, at least at first. Even Sanders believes the proposed convention-center hotel may succeed, but not because of its proximity to the TCC. Instead, he indicates tourism and other factors might make the hotel profitable, just as they did in Austin. On the other hand, Sanders also says: "There's no body of evidence that a publicly financed hotel makes any difference in the increased performance of a convention center."

Several of those involved with the industry strenuously disagree, including Rick Vaughan, of the Metropolitan Tucson Convention and Visitors Bureau. "Hotel rooms are always an issue," Vaughan says, citing responses from meeting planners about holding their get-togethers at the TCC. "They tell us they're not coming because of the hotels."

Vaughan believes implementation of all of the proposed improvements--the convention-center remodeling, the convention-center hotel and the new arena--will change the perception of Tucson in meeting planners' eyes. "They will at least allow us to be in the game," he says.

The feasibility study done by the Johnson consulting firm on the proposed convention-center improvements noted that the facility now "is a poor performer nationally and within its peer set." To correct that supposed shortcoming, the study recommends constructing 21,000 square feet of additional meeting rooms to basically triple that space. Adding more meeting rooms to the TCC, though, has been a bone of contention for years. In 1994, Tucson voters by a 2-to-1 margin defeated a request to sell general-obligation bonds to do just that.

The Johnson convention-center study also calls for developing a 28,000-square-foot ballroom to complement the present 20,000-square-foot one. At the same time, it recommends enlarging the current 114,000-square-foot exhibit hall by about 20 percent. If these improvements are implemented, the Johnson report states the TCC will "approximately double the economic and fiscal impact of the facility to the economy."

The study estimates $102 million in new annual spending will occur in Tucson, and will result in 1,460 new jobs when these changes are made. It also forecasts $6.1 million in additional taxes should be generated each year. Those attending TCC events--a number which is anticipated to go from 175,000 to 360,000--will pay these taxes. Some of them, of course, will be from outside of Tucson. "Those people come to town and spend money," Singer from the TCC says about these conventioneers and meeting-goers. "It's the greenest form of economic development. Their money generates taxes, which is money we can spend on ourselves."

Based on his review of actual convention-center performances nationwide, Sanders casts doubts on this optimistic scenario. In 2005, the Brookings Institution published a report by him titled "Space Available: The Realities of Convention Centers as Economic Development Strategy." Sanders pointed out that the supply of available square footage in convention centers around the country was growing at a much faster rate than demand. In addition, his research showed that the number of people attending conventions "has actually plummeted."

Many in the convention industry quickly attacked these findings. Singer says about Sanders: "His statements were correct, but he cherry-picked his examples. Plus, he doesn't talk about second-tier cities (like Tucson) or the winners. He isolated failures to make his case."

Replying, Sanders declares: "I haven't been criticized by independent or academic (analysts), just industry people who have trotted out little substantive evidence." One point Sanders makes in his research is that as convention centers across the country have enlarged their facilities, the competition for business has led to shifts in the way promoters of the mammoth centers behave. Instead of restricting themselves to gatherings that attract huge numbers of attendees, Sanders writes, these centers "are expanding in order to accommodate simultaneous small- and medium-sized events, the kinds of events that now use far smaller centers."

Such an expansion of a major facility is now underway in Phoenix. Transforming itself from the 68th- to the 20th-largest convention center in the country, the city is almost tripling its space to 872,000 square feet. As a result, officials hope to increase the number of annual convention-goers from 135,000 to 375,000, a number more than five times higher than that projected for Tucson. "It provides an economic engine for taxes," suggests Douglas MacKenzie, spokesman for the Greater Phoenix Convention and Visitors Bureau, of the $600 million expansion. "The dollars (spent by visitors) go directly into the community."

Officials from both Tucson and Phoenix downplay the potential competition for convention business between the two cities--but they also did the same regarding spring training baseball. "I think our markets are different," MacKenzie says. "Every city is competitive, and Phoenix offers a high level of product. I'm sure there will be some competition."

Vaughan, of the local visitor's bureau, agrees, but lists several advantages Tucson can provide to attract new conventions. "It doesn't take you 45 minutes to get to the desert," he says, in comparison to Phoenix's downtown. "Plus, we offer something unique not experienced anywhere else."

That might be, but according to a report recently released by two convention-industry groups, the business is currently in a "buyers' market" for space. Sanders says that means that a center wanting to attract users often has to offer deeply discounted rates, and the price of hotel rooms must also come at bargain prices.

A February 2007 Washington Post article highlights these problems for the 4-year-old convention center in the nation's capital. Instead of being the economic bonanza promised by backers, the newspaper states: "Convention attendance is dropping, the surrounding neighborhood is yet to be transformed by the promised new development, and conventioneers are filling fewer hotel rooms than expected."

Ignoring those potential problems, elected officials across the country continue to approve expansions of convention centers. "The Answer Is Always Yes," was the headline of a 2005 Forbes magazine article on the outcome of convention-center proposals. "Politicians, playing local hero, are incapable of finding reasons not to build," the article states.

Sanders observes: "Tucson can conclude this is a pot of gold for downtown, since there is a religious-like belief these projects will revise downtowns. But the history is, it doesn't work. Instead, it's a highly competitive market, and (these projects) are the equivalent of rolling a whole lot of dice, each of which has to come up right."


But Johnson's convention-center study estimates that if the improvements are made, tens of thousands of additional out-of-towners will use the TCC. As people in the convention industry like to point out, these people are the biggest spenders in the travel business, dropping an average of $275 a day.

At the same time, the proposed downtown arena is expected to attract many more people to the area. Projections predict that annual attendance at arena events will escalate from the present 168,000 to 688,000, with about 40 percent of those the illusive fans of a still-undetermined minor-league hockey team.

According to the theory that convention centers can help revitalize downtowns, all those additional people should bring vitality back to the area. As Vaughan says, "The perception of downtown now is there's nothing to do. This project helps build excitement for locals."

In Sanders' opinion, though, money to be spent on the convention center and the proposed adjacent hotel could be invested more wisely elsewhere. "Today, as all cities are obligated to compete with dozens of others," he writes starkly in his Brookings Institution report, "the prospects of real economic development and opportunity based on the convention strategy appear nil." Sanders proposes spending the money "to build flexible local economies and workforces capable of adapting to social and economic change." That philosophy, however, doesn't appear to be politically palatable, especially in an era where keeping up with the competition is seen as essential.

Another factor in determining what Tucson does at the TCC is the source of funds it will use for many of the improvements. That Rio Nuevo tax incremental financing money is restricted mostly to brick-and-mortar projects. But if Sanders is correct, the promised financial and redevelopment rewards forecast for downtown and the TCC won't be realized even after all the money is spent.

When that has happened in other cities, he indicates, the financial race simply escalates: The next step advocated by politicians and convention-center boosters is often the expenditure of even greater amounts of public money. "The argument is they must do something more," Sanders says. His research has shown communities keep throwing taxpayer dollars at attracting the elusive convention business, through adding more downtown attractions, installing new center management or increasing the facility's promotion budget.

But Tucson hasn't even begun the process yet. Eventually, though, the City Council will be asked to finalize the community's entrance into the convention-center race. By all estimates, the council will vote yes--just like almost every other elected body in the nation that is asked the same question. The results won't be known for years, but if Sanders is right, the community could be left with another Tucson Electric Park--a facility built on boosters' dreams which faded in the reality of the Sonoran Desert.
 
I don't find any of this article to be incouraging, pretty depressing actually :(


Rio Nuevo: City gets tough on progress of projects
City gets tough on progress of projects
TEYA VITU
Tucson Citizen


Time is money.
That's the message City Manager Mike Hein is driving home with the newest development agreements for Rio Nuevo projects involving private sector developers and city-owned land.

Town West Design Development's El Mirador hotel-condo-brew pub proposal at the north end of downtown is the first development agreement to face stepped-up financial penalties and precise timeframes for potential penalties that could exceed $360,000.

"Town West will have financial penalties if they miss dates," Hein said.

Development agreements expected in the coming months for a Tucson Convention Center hotel and the 14.3 acres on West Congress Street will have similar precise timeframes/penalties, unlike earlier development agreements that are peppered with "shalls" and "musts," but with scant consequences to back them up.

"We will be more rigorous with our management to make sure they conform to the terms," Rio Nuevo Director Greg Shelko said.

Rio Nuevo has endured drawn out housing proposals from 2003-04, with predictions they would be done by now but the ground remaining untouched.

Three years ago, Bourn Partners outlined that The Post loft on Congress Street would be finished now, but Bourn is still waiting for a contractor bid with hopes to start construction in coming weeks.

Presidio Terrace has had completion dates announced for 2007, 2008 and 2009, but developer Peggy Noonan never got a shovel into the ground before Shelko pulled the plug on her development agreement in November.

Hein acknowledges that even though The Post development agreement called for construction to start in July and be finished by December 2008, ownership of the property passed to Bourn in the agreement and the only prescribed penalty for missing timelines is forfeiting a $40,000 bond.

"In that specific agreement, there is very little remedy," Hein said. "Peggy Noonan symbolizes the fact that we are taking things more seriously."

Shelko insisted there had been rigorous attention to other development agreements, citing frequent talks with the Bourn and Noonan teams throughout last year. But he said Rio Nuevo intends to push proposals to commitments at a brisker pace.

"We've probably been far too generous in the period of time from 'we love your project' to getting to a contract," Shelko said.

Rio Nuevo has seven high-profile development agreements in play for downtown private sector mixed-use housing project that involve retail, office, hotel and entertainment uses.

This is look at two of the seven agreements based on their requirements and status.

El Mirador

Town West Design Development

• Project description: Three connected seven-, nine- and 15-story towers with a street-level brew pub, 100 condos and 220 hotel rooms. A fourth building proposed across Ninth Avenue from the rest of El Mirador would have an additional 50 condos. At Franklin Street and Stone Avenue at the north end of downtown.

• Timeline: 21 months to close on the purchase of city-owned land at Franklin Street and Stone Avenue. Construction must be done within 39 months of closing or by November 2012.

• Current status: Development agreement was approved Nov. 27 and Town West is in the first nine-month contingency period, where a development plan must be completed and a preliminary conceptual architectural plan must be submitted.

• Will pay: $700,000 for 3.6 acres of city-owned land at the end of a 21-month closing period that started Nov. 27.

• Prognosis: Uncertain. How much will be condo, how much will be hotel is likely to continue changing, and Town West president Jim Horvath openly acknowledges the time extension options as well as having no compunctions about paying penalties if deadlines are missed.

• History: This started as a Nimbus Brewing Co. proposal to build a brew pub, restaurant, seven stories of condominiums, space for a specialty grocery store and other retail stores. Managing partner Jim Counts in September 2005 projected a construction start in spring 2006 with an opening date at the end of 2007. The property remains untouched.

Counts brought in Town West in early 2006 after he missed a December 2005 deadline to have financing in place, stirring the wrath of the City Council.
September 2006: El Mirador would have 140 condos in six-, 10- and 12-story towers.

June 2007: That changed to seven, nine and 15 stories with a 220-room hotel in the lower towers, 100 condos in the 15-story tower and 50 condos in a fourth building proposed across Ninth Avenue from the rest of El Mirador.

"If everything remains status quo, I don't know if condos are viable, but the hotel is viable and the retail is viable," Horvath said. "We're hoping the housing market improves over the next three years. We can adjust (the hotel-condo mix) for the economic need. We do hope in the next two-three years to have more demand in the housing market."

• Penalties:
>Town West put up a $15,000 bond at the end of November that would be forfeited if a conceptual architectural plan and development plan does not get city approval in nine months.

> Three four-month periods follow, each requiring a $15,000 bond, with deadlines for preliminary financing, construction documents, final financing commitments, beginning marketing and presales and obtaining a building permit.

Those four $15,000 bond periods add up to 21 months with allowance for two six-month extensions that could each incur another $15,000 bond.
Any time a deadline is missed, all accumulated bond payments are subject to forfeiture. That could be as much as $90,000.

> Town West has to put up another $300,000 bond or letter of credit upon closing of the sale. This requires construction to finish within 39 months, by November 2012 (or November 2013 if both six-month extensions are used).
"At the end of the day, if the market isn't there, there are provisions," Horvath said. "We can hold on to a point until the market and economy are viable to build. This agreement gives us 33 months with all the extensions to get to a point of construction. If not, we pay a penalty and still own the land. We hope within the five years span (to complete the project)."

The Post

BP Post Investors (Bourn Partners)

• Project Description: A six-story building with 52 condos and street-level retail and a restaurant.

• Timeline: First proposal came in 2004 when the city sought developments for the Thrifty Block on Congress Street at Scott Avenue. Development agreement on April 18, 2006: 15 months to close on purchase, plus 18 months to compete construction or 33 months to be finished or December 2008. Under the agreement, construction was supposed to start in July.

• Status: out for bid for a contractor to start construction.
"Best case, we can start some time in January," said Don Bourn, managing partner at Bourn Partners.

• Paid: $100 for a half acre at Congress Street and Scott Avenue (formerly the Thrifty Block).

• Prognosis: Uncertain start date for construction, which depends on a favorable construction price.
• History:
The Thrifty Block was demolished in September 2004 at which time Bourn Partners proposed an eight-story complex with 60 condos with an estimated completion date for The Post in 2007.

What happened? Two things: Real estate went in the tank, but before then The Post was delayed by about two years as Bourn unsuccessfully tried to acquire the Chase Bank garage, which would have allowed The Post to be larger.

February 2006: a brief flirtation with a 13- or 14-story building with 90 to 95 condominiums that fell to the wayside when Bourn did not win some $4 million in public incentives or the Chase garage.

August 2007: six stories, 52 condos

Bourn submitted a $40,000 bond to assure The Post would be finished by December 2008. That will not happen, but don't expect Bourn to suffer any penalties.

"The Post met every obligation up to and including closing of the real estate," Rio Nuevo director Greg Shelko said. "For The Post, it should not be portrayed as an issue of contract compliance. They should be applauded for hanging in there in this tough market. It would be terribly unfair of the city to penalize Bourn."

Bourn has $17 million in financing in place and pre-sold about half the condos.

"We're out to bid with a contractor," Bourn said "We're getting numbers in (soon). We're hoping to have a price in the next couple weeks. If there are price issues that need to be worked through, that could take some time. Best case, we can start some time in January. Construction pricing is so erratic right now."

Here are the remaining five Rio Nuevo projects Presidio Terrace

Reliance Commercial Construction (Peggy Noonan, president)

Project description: A seven-story luxury housing complex with 92 condos and nine townhomes on a former Tucson Museum of Art parking lot at Paseo Redondo and Main Avenue.

• Timeline: Development agreement from Oct. 18, 2005: Set a closing date six months later with construction supposed to start 15 months after that or by August 2007. The development agreement was terminated in November.

• Would have paid: $734,000 for a former Tucson Museum of Art parking lot

• Prognosis: Uncertain. Rio Nuevo wants to have a new development team in place for the 14.3 acres on West Congress Street before looking for a new developer for Presidio Terrace. And then the new developer has to face off with the El Presidio Neighborhood, which was resistant to Noonan's proposal.

• History:
September 2004: Noonan hoped to break ground in spring 2005 and finish fall or winter 2006.

May 2006: Start construction in early 2007

June 2006: Noonan expects to start construction in spring 2007, with people able to move in 18 to 24 months after.

November 2006: Start construction in summer 2007, finish in mid-2009.

September 2007: Shelko gives Noonan 30 days to satisfactorily fulfill financing, marking and design requirements.

November 2007: Shelko terminates the development agreement with Noonan. No work was ever done at the site.

"That contract was extended one year in a two-year contract," Shelko said.
Mercado District of Menlo Park

Rio Development Co.

Project description: Five developers building different style homes but all fitting a historic regional feel from 100 years ago.

• Timeline: Development agreement from Oct. 13,2003, calls for five model homes to be finished within two years but spells out no time requirements for any subsequent homes in the 99-home development.

• Paid $1.475 million for 13 acres on West Congress Street near Grande Avenue.

• Prognosis: 16 of 99 proposed homes have been built. Intention is to finish most of rest in the next two or three years.

• History:
September 2004: Estimated completion date was 2007.

Depot Plaza

Williams & Dame Development Co./Peach Properties and Tucson Community Services Department

Project Description: A three-tower project just east of the Ronstadt Transit Center. This includes the former Martin Luther King Jr. Apartments, which will have 96 market-rate apartments, a new tower with 45 market-rate apartments and 11 affordable-housing apartments and an four-story public housing tower with 68 apartments for low-income seniors and the disabled.

• Timeline: Development agreement from Nov. 21, 2006: complete rehabilitation of former MLK apartments, 1 N. Fifth Ave., and a commercial strip along Congress Street in two years (November 2008). The second tower must be completed in four years (November 2010)

• Will pay: $630,000 for 30,000 square feet of real estate that includes MLK and the land where W&D will build a second tower.

Prognosis: Optimistic, if there is such a thing. Williams & Dame has a solid track record in Portland, Ore., where the developer played a key role in creation of the Pearl District.

Penalties: Williams & Dame has to pay a $25,000 bond upon closing for each land purchase for MLK and the second tower.

• History:

In 2006, the intention was to demolish the former Martin Luther King Jr. Apartments and build two private-sector market-rate apartment towers and one public housing tower for the elderly and disabled.

Depot Plaza originally was a public-private partnership with downtown developers Doug Biggers and Tom Powers. They sold out to Williams & Dame Development Co. in 2006.

Williams & Dame decides to redevelop the existing MLK rather than demolish it.

Nov. 21, 2006: Williams & Dame project manager Matt Brown commits to having the MLK ready for residents in 12 to 14 months. Now W&D says July 2008. Federal government approval slowed things a bit because MLK was a federally subsidized public housing. W&D started work inside MLK in October.

Tucson Convention Center hotel

• Timeline: A final agreement with three development teams is expected to go to the City Council in February. A precise design and construction schedule is unknown at this time.

West Congress

Gadsden Co. or Williams & Dame Development Co.

Project description: mixed-use development for 14.3 acres on West Congress Street, between Interstate 10 and the Mercado District of Menlo Park

• Timeline: A development team should be chosen by the end of January with a development agreement finalized two or three months later. Construction would be expected to start 18 to 24 months later or late 2009-2010. Both teams want to have a substantially finished housing-and-commercial for the state centennial year in 2012.

• Price: to be negotiated
 
it just makes me wonder why we have so many flakey developers that just push back their projects further and further. we need to seek out bigger companies instead of local smaller companies. they blame the market, but why cant they just build rental units in the mean time. and then just convert to condos when the market improves. im glad there impleneting penaltys..
 
It appears that more Tucsonans are preferring to fly out of Tucson Intl. rather than Phoenix Sky Harbor, although TIA is still only the nation's 67th busiest airport, handling just over one-tenth of the passenger volume of Sky Harbor:


Tucson airport traffic sets record with addition of 10 destinations
The Business Journal of Phoenix
January 16, 2008

Passenger traffic at Tucson International Airport reached a new high in 2007, exceeding projections with 4.43 million travelers, compared to 4.23 million for 2006.

"This is an increase of 4.81 percent over 2006," said Bonnie Allin, Tucson Airport president and CEO. "Since 2003, we've witnessed a 26.3 percent increase in passenger traffic.

"The continuing growth in passengers this past year is directly attributable to the introduction of daily nonstop service to ten new destinations, including nine with the start of service by ExpressJet Airlines last April, and Southwest Airlines' new service to Oakland in November," said Allin. "In addition to the new destinations, several carriers increased service to popular existing routes, including Los Angeles, Chicago, Denver and San Diego."

Thirteen airlines provide 89 daily nonstop departures to 28 destinations from Tucson.
 
I like TIA. It's a nice airport and the fact that it's not over crowded like Sky Harbor or Hartsfield in ATL makes it that much better. TIA is in the process of a major renovations and will even include a second terminal within 10 years. It's good that they renovation now before it's gets more destinations.
 
Another Downtown business is shut down

By Rob O'Dell
Arizona Daily Star
Published: 01.17.2008


A second Downtown business has closed down this week — Simply Convenient, an all-purpose convenience store used by many Downtown workers and visitors. The store closed Monday according to the city's business license department — the same day as Casablanca Mansion, which was shuttered after restaurateur Jeff Wer failed to come up with nearly $16,000 in back taxes.

It seems Simply Convenient was also shut down because of a lack of payment. A note on the door of the business announced the "notification of a landlord lien." The notice said the leased premises and all inventory, equipment, and furnishings on the premises … are now in the possession of the landlord." Dana Elcess of Chapman Management Group, who was listed on the notice, said she couldn't comment about the lien, and her supervisor did not return calls for comment.

Joe Brescia, owner of Simply Convenient, 25 N. Stone Ave., could not be reached for comment Wednesday. Simply Convenient sold typical convenience-store items and recently was the only convenience-type store Downtown. The store also had a salad bar, and until a year ago had a deli that sold sandwiches. A year ago, store employees said the deli was costing too much money, and the owner did not want to raise prices on customers to pay for the increased cost of running it.

On Wednesday, the store was dark and nearly completely empty. All the shelves were bare, and the beverage coolers in the back of the store were empty. No cigarettes were left in the racks above the checkout counter, and the ever-popular lottery ticket stand was gone, too.

About the only things that remained were the fountain-drink machines and empty boxes piled up on the floor. The abrupt closure caught Downtowners by surprise. During one 15-minute period around lunchtime, at least a dozen people stopped by the store and lamented its departure.

"That is sad," said Kim Hawthorne, who works for First Credit Union nearby. Hawthorne said she often went to Simply Convenient to buy drinks during her breaks. Lyle Rayfield, who works for the city's Office of Equal Opportunity Programs in the Pioneer Building at North Stone and East Pennington Street, said she tried to support the small business because the owner, Brescia, and his staff were so friendly. Rayfield said she normally came to buy lottery tickets, adding that many in her office came almost daily to eat or buy something. Councilwoman Nina Trasoff, a big Rio Nuevo redevelopment backer who has often touted Downtown progress, said two stores closing on the same day amounted to "an unfortunate and unhappy coincidence."

Trasoff said many business are being hurt by the closing of Downtown exits to Interstate 10, along with the closure of the Fourth Avenue underpass for construction. But she said some businesses are faring well in this tough climate. She said businesses need to take advantage of the free consulting services provided by the Tucson Transportation Department for those affected by Downtown construction.

"I'm sorry to lose any businesses Downtown," Trasoff said, adding this was particularly sad, given that Downtown is at the beginning of dramatic changes that will transform the city's core.
 
Another adaptive re-use project for downtown Tucson:


BaptistChurchtobecondos.jpg

Barnett and Shore Contractor workers are gutting the First Baptist Church Educational Building, which is destined to become
condominiums. Home developer Chris Kemmerly and partner Steve Quinlan, chairman of the Long Companies, plan to retain its 1950s feel.
(photo: Arizona Daily Star)


Downtown church's Sunday school to become condos
By Bonnie Henry
ARIZONA DAILY STAR
01.24.2008

"Edgy" was probably not what members of Downtown's venerable First Baptist Church had in mind when its education wing was built back in the early 1950s. But that could be the next look for this former Sunday school, which home developer Chris Kemmerly and Long Companies Chairman Steve Quinlan have picked up for $3 million. "It's a great old building and we want to maintain the '50s feel," said Quinlan, who plans to add a third story to the education wing and transform it into about 40 lofts, ranging in price from $200,000 to $800,000.

Its address on the southeast corner of North Sixth Avenue and East Fifth Street puts it in a prime central location — close to the University of Arizona, Downtown, and the Fourth Avenue shopping district. Just north of the old education building is First Baptist Church itself, which was not included in the sale.

The 30,000-square-foot property that did sell includes a former playground to the south, the education wing and the adjoining Sleeth Chapel to the east, which was recently demolished. "It didn't blend in well with the rest," said Quinlan, adding that the chapel site will become an entrance to the new lofts. As for the education wing, about all that remains are its exterior yellow brick walls. "It will be a shell, with nothing left," said Quinlan. However, when workers removed the ceilings, "We unearthed all this wonderful concrete and brick support structures," said Quinlan. "We'll expose that."

Initial plans also include a lap pool and garden area. Michael Franks of Seaver Franks Architects is the architect. "He usually does some pretty interesting, edgy things," said Quinlan. "We might go edgy." Preliminary sketches should be out by summer, with construction expected to begin in 2009, said Quinlan.

The property sold last July, three months after First Baptist put it on the market as the church coped with a dwindling membership and ever-climbing maintenance costs on the 82-year-old building....
 
COOL! always glad to see adaptive reuse and hist. preservation.
is the church bldg still utilized for worship? hope so.
 
Now that Williams and Dames has pulled out, the Gadsden Co., as the only remaining bidder, will probably be awarded the contract for this project. Interesting decision, as the city had asked the two developers to work together on a proposal to jointly develop the parcel (somewhat similar to the city's efforts to combine parts of various developers' proposals for the convention center expansion and hotel).


GadsdenMercadorendering.jpg

The Gadsden Co.'s proposal for West Congress Street includes a public market, a boutique hotel and 400 houses.
Gadsden's proposal likely will win by default because another developer has dropped out.
(photo: the Gadsden Co.)


Developer drops West Congress proposal
by TEYA VITU
Tucson Citizen
01.29.2008

Williams & Dame Development has withdrawn its proposal for the 14.3 undeveloped acres on West Congress Street, west of Interstate 10. The Portland, Ore., developer cited a desire to focus more on its Depot Plaza development, renovating the former Martin Luther King Jr. Apartments as the One North Fifth Apartments, said Matt Brown, project manager for Williams & Dame. The company was one of two finalists vying to build on the land south of Congress. The parcel is wedged between the Tucson Origins project and the Mercado District of Menlo Park, a housing project being built by Williams & Dame's competitor.

Gadsden Co. will likely be the default choice. The Rio Nuevo selection committee is preparing a recommendation for the Feb. 21 meeting of the City Council's Rio Nuevo subcommittee, Rio Nuevo Director Greg Shelko said. "I don't think there is anything unfavorable about this," Shelko said. The selection committee, composed of three Menlo Park residents and four city employees, is completing the evaluation process with Tucson-based Gadsden. "(Gadsden partner) Jerry Dixon is a very credible developer in this community," said Councilwoman Nina Trasoff, who chairs the subcommittee. "He's coming in with a $300 million project. I'm looking forward to moving ahead with this."
 
Last edited:
thats too bad that W&D pulled out cuz they have done some good stuff. i just hope that the Gadsden co can pull it off... i hope it just gets done... i know that they are doing some work on the Mercado District.. so hopefully they can tie everything together.. i wouldnt want it to look like a different city just one street down...lol
 
The Old Pueblo Trolley (not to be confused with the new streetcar line) is being extended into the downtown area, with the new tracks expecting to be in service in 2009, once the Fourth Ave. underpass construction is complete:


Trolleyconstruction.jpg

The tracks extending the Old Pueblo Trolley to downtown should be laid by March.
The trolley will loop through Fourth Avenue and downtown.
(photo: Tucson Citizen)


NewTrolleyroute.png




City: Trolley tracks to be done by March
by GARRY DUFFY
Tucson Citizen
01.30.2008

The maze that is the intersection of Congress Street at Fourth Avenue will be opened to traffic in March - with the addition of new tracks to extend the Old Pueblo Trolley into the downtown area.

New tracks for the historic trolley will run from the current terminus on Fourth Avenue between Eighth and Ninth streets, through a widened, reconstructed Fourth Avenue underpass, and west on Congress Street, south on Fifth Avenue. They will turn east on Broadway and north to reconnect at Fourth Avenue south of the underpass for the return trip to the University of Arizona Park Avenue gate.

The setting of the tracks in concrete and repaving of Congress and Fourth south of the underpass with asphalt should be completed in early March, Mike Skilsky, project engineer for the Tucson Transportation Department, said Tuesday. "We've been working six 10s," Skilsky said, referring to the six 10-hour days a week for crews of the contractors, a joint effort by Sundt Construction Co. of Tucson and Stacy and Witbeck Inc. of Oakland, Calif.

The vintage, restored trolley cars of the all-volunteer Old Pueblo Trolley won't roll on the new tracks until the Fourth Avenue underpass reconstruction project is completed in spring 2009, Skilsky said. Getting them laid now averts having to excavate the improved downtown streets later on.

Bringing the trolley into the downtown area has been a mission for the Old Pueblo Trolley volunteers. They started planning the trolley circuit between UA and downtown 25 years ago, Dick Guthrie, president and CEO of the organization, said Tuesday. "This is really a milestone," he said.

The extension into downtown is a separate project from the modern streetcar approved by voters in the Regional Transportation Authority election in May 2006. Both will share the same tracks on Congress, and possibly other segments of the routes, as well, Shellie Ginn, TDOT urban corridor project manager, said Tuesday.The streetcar won't be operational until at least 2011. Funding will be provided by the RTA from the half-cent sales tax approved by voters in 2006, and, hopefully, from federal transit funding the city is seeking. When completed, the streetcar will run between the University Medical Center area on Campbell Avenue, west through the UA campus on Second Street, south on Park Avenue, west on University Boulevard, south on Fourth Avenue through the new underpass. It will then head west on Congress through downtown, and loop back from Rio Nuevo downtown rejuvenation projects near the Santa Cruz River. Design work on the streetcar project is in its early stages, Ginn said.

The Fourth Avenue underpass project will double its width for added motor vehicle capacity and safety, and include bicycle and pedestrian walkways in addition to the trolley tracks.
 
I think it's really cool that the historic trolley and the new streecars will share the same tracks.

Btw, are they using the existing tracks on Congress, or are they tearing those up and laying down new tracks?
 
That's cool for Tucson, I didn't know they were doing that. A little trolly line like that is great , and the eventual addition of the streetcar is even better.
 
okay, thank you for that lesson, i didnt know that. but they are laying new tracks cuz iv seen them...
 


Back
Top