Springbank Dam

I would disagree. I would much rather have a river that the population can use for canoeing and other water sports. This would add a life to the river we haven't seen in years.
 
I would disagree. I would much rather have a river that the population can use for canoeing and other water sports. This would add a life to the river we haven't seen in years.

I agree with you I would like the river used for different water sports. I don't fully support the idea that this fish was that big either just because the dam was broken. The river in general is getting healthier from all sorts of reasons.
 
There is little doubt that the primary reason for the improved health of the river is the shutdown of the dam.

This has been seen in other river systems when old dams were removed.

There is still plenty of opportunities to Kayak and Canoe on the river today.
 
Seems that Springbank Dam is done like dinner. Other than the uppity canoe club that don't want to move to Lake Fanshawe, everyone else seems to be happy with a free flowing river. Even Mattress Brown has backed off his election plebe to restore the dam.
 
Update on the additional $1.6M costs on the Springbank Dam decommission project.

Springbank Dam Decommissioning and Bank Restoration Project (RFT-2024-
070) construction contract value with 2220742 Ontario Ltd o/a Bronte
Construction BE INCREASED by $1,649,048.54, including contingency, for a
total contract value of $5,999,910.10 (excluding HST) in accordance with Section
20.3 (e) of the Procurement of Goods and Services Policy;


The contractor commenced the Springbank Dam decommissioning project in summer
2024. The scope of work included removal of the four gates, hydraulic equipment, and
mechanical room. During construction it was discovered that the concrete deck was in
worse condition than originally assessed. The engineers determined that the deck
would require extensive concrete repairs that may only last up to 5 years and
recommended safety netting below each opening to protect the public from the risk of
falling concrete into the river.
To ensure longer term sustainability of the remaining dam structure, it is recommended
to remove the concrete deck from the dam as part of the construction project. Removing
the deck now will protect public safety and allows the City to benefit from cost and time
savings as well as reduced future environmental disturbance in the Thames River.

https://pub-london.escribemeetings.com/filestream.ashx?DocumentId=115647
 