Builder puts Kanata plans on full hold
http://www.ottawacitizen.com/Builder+puts+Kanata+plans+full+hold/2699446/story.html
Mattamy shuts Fairwinds sales office, lays off staff, citing delays ‘we don’t control’ in Hazeldean sewage-pumping station
BY NECO COCKBURN, THE OTTAWA CITIZENMARCH 18, 2010 11:04 PM
OTTAWA — A much-delayed Kanata housing development has now been “fully put on hold,” according to the developer, and some home buyers face a tight deadline as they try to figure out what to do.
Home buyers in Phase 5 of the Fairwinds community have been told that Mattamy Homes can’t predict when the project can go ahead because it needs approvals beyond its control in order to get the ball rolling, according to Frank Cairo, Mattamy’s senior vice-president of land development and marketing.
Some buyers previously had closing dates pushed back, but Mattamy has now closed its sales office in Fairwinds and reallocated or laid off the development’s construction-related staff, and says it doesn’t know when the homes will be built.
Mattamy says it needs upgrades to the city’s Hazeldean sewage-pumping station tobe finished before it can go ahead with getting necessary municipal and provincial approvals on its plans to expand its own Fairwinds pumping station and service the site. The company can’t apply for building permits until the site is serviced, said Cairo.
“We’ve basically told our homeowners that in light of these external approvals that we don’t control, we can’t predict closing dates at this time, and we can’t even predict the duration of delay. We’ve tried to do that in the past and we’ve been incorrect in our assumption,” Cairo said, adding that about 40 home buyers are affected.
Cairo said residents have three choices. They have until March 25 to leave the deal and get their deposits back, or to transfer to a lot in Mattamy’s Half Moon Bay development in Barrhaven. Or they can stay in the current agreement and essentially remain in limbo.
But if their current closing date is reached and the company can’t set a new one, it won’t meet legal obligations under the agreement and the deal is “null and void,” said Cairo.
“Mattamy is looking to work with our homeowners and if there’s another option available to us prior to the closing dates terminating to keep the deals alive, we will.”
Cairo said a deadline was set because the company wants to give buyers first dibs on a new housing phase that’s opening up in the Half Moon development. Cairo said most of the buyers have taken the company up on its offer to transfer to the development or get their deposits back.
But some residents aren’t happy with the situation and feel they’re being pushed out of the deal.
R.J. Rousseau, who’s had his closing date pushed back twice after putting $25,000 down on a house in February 2008, said the company hasn’t presented him with the option to stay in the deal past his closing date in December. A letter sent to him by Mattamy last week offers only the cancellation or transfer options.
Despite being offered a discount on a Barrhaven home, Rousseau said that subdivision is “considerably” more expensive, and today’s housing prices are higher than when he first signed on to Fairwinds two years ago.
The delays have had “considerable” impact, he said. “This is my life they’re playing with.”
Cairo said, “We appreciate and feel for our homeowners deeply. There’s nothing more we want to do than deliver these houses.”
Development in Kanata West has been bogged down in controversy and delay for more than eight years.
The land drains into the Carp River. Council halted most Kanata West development in May of 2008 after it came to light that computer models of potential flooding of the Carp were flawed, though Fairwinds was allowed to continue.
In July 2008, Ontario’s environment ministry put its own hold on Kanata West — including the Fairwinds Phase 5 area south of Poole Creek — pending a more thorough environmental assessment.
After an independent engineering firm came up with a report that called for additional water storage capacity to be created on the land in order to guard against flooding, various west-side projects were put back on the planning track.
The provincial order was lifted late last year, Cairo said, adding “there are still outstanding approvals in the watershed that need to be resolved.”
Stittsville-Kanata West Councillor Shad Qadri said the Hazeldean pumping station upgrades should be finished by year’s end, and he’s trying to set up a meeting between city officials and the would-be homebuyers.
One of his concerns “is with the provincial government.”
“Why are we allowing the developers or the builders to sell building lots before they are approved (for construction)?” he said. “That’s where the consumer unfortunately gets caught in the middle, and this is a classic example of that.”
[email protected]