I took a drive by this site this morning and MoeMar has started excavation on the land designated for apartments, so it looks like they'll be starting their next multi unit building. I can't remember seeing any information on the size/number of units.

No, they haven’t started working on the area designated for apartments. They’re building the road parallel to Runnymede. Same thing I said when I made the map.
 
No, they haven’t started working on the area designated for apartments. They’re building the road parallel to Runnymede. Same thing I said when I made the map.

It looked like they were working close to the traffic circle. Maybe I was wrong and they aren't going to start their apartment building just yet.
 
It looked like they were working close to the traffic circle. Maybe I was wrong and they aren't going to start their apartment building just yet.

Maybe next year, they’ve been installing the underground utilities for the new road. It appears it’ll just be the section between the two roads that come off Runnymeade
 
The proposal is to rezone PID 05029319 from R1 – Single Unit Dwelling to R3 – Multi-UnitResidential for the purpose of two apartment buildings.

52883303174_8431950f23_z.jpg


52883589728_9606dc284f_z.jpg" width="640" height="390"


Located at about 742 Hillsborough road.
https://townofriverview-pub.escribemeetings.com/filestream.ashx?DocumentId=18575

Here is a set of renders of this proposed apartment complex on Hillsborough Road:


Source: Town of Riverview PAC Agenda
 
Yes the building on Coverdale Rd. by the golf course is taking a long time; Thrive Properties have a lot of irons in the fire. They're just finishing the first building at the Trailways up on Gunningsville Blvd., so now maybe some of those workers will be able to help get the Tides building over the finish line. I'd say they should be ready to lease by this fall.
And so when will they start the 10 floor building at the chocolate river station?

I saw the other day that the "Trailway" is fully leased already so I suspect the golf course property will quickly follow suit. :shrug:
 
I saw the other day that the "Trailway" is fully leased already so I suspect the golf course property will quickly follow suit. :shrug:

Given the location and the views from those north side balconies, I wouldn't be surprised if they're already fully leased. I've seen furniture and people on the balconies of the Trailway, so it's pretty much finished. I guess some of those workers could be transferred to the Tides on Coverdale to finish up that building.
 
No, but I have no doubt it will be before Christmas (likely November sometime).

Back in April when this was posted, I had my doubts that this large project could be completed in time for Christmas. But the volume of work that they are doing on this build is pretty impressive. I think you will be proven right. It's a highly active site.
 
50 years on, Riverview has grown from just 3 houses to largest town in New Brunswick
Residents value small-town feel, but Riverview also has big-city challenges
CBC News · Posted: Jul 09, 2023 9:00 AM ADT | Last Updated: 3 hours ago
https://www.cbc.ca/news/canada/new-brunswick/riverview-city-town-growth-rural-1.6900281

historic-photo-of-riverview.jpg

Once upon a time in Riverview (probably from the 1950s). CBC photo

I think the title of the article is a little misleading. Riverview may have been incorporated as a town 50 years ago, but, there were villages in the area for some time before this that were amalgamated to form the town. I think to find a time when the area was essentially rural, you would have to go back to the 1950s, and not the 1970s.

Despite this, the growth of the municipality has been impressive. At a population of 20,000 souls, Riverview is the fifth largest municipality in the province (after Moncton, Dieppe, Saint John and Fredericton). Riverview is larger than four cities in the province. It should really be elevated to city status too.
 
Here is a set of renders of this proposed apartment complex on Hillsborough Road:


Source: Town of Riverview PAC Agenda

The public hearing for this development is going on at the moment. The neighbours opposing it are very vocal and look organized. They’ve threatened lawsuit too.

Would be interesting to see how the council votes.
 
The public hearing for this development is going on at the moment. The neighbours opposing it are very vocal and look organized. They’ve threatened lawsuit too.

Would be interesting to see how the council votes.

What legal ground would they have to stand on? This is interesting. This is a place where an apartment building actually fits. It’s not too big, no additional traffic on to local streets, and there is a tree buffer around the site.
 
The public hearing for this development is going on at the moment. The neighbours opposing it are very vocal and look organized. They’ve threatened lawsuit too.

Would be interesting to see how the council votes.

A lawsuit on what grounds? They are probably just speaking out of their ass...........

I find the increasing aggressiveness of NIMBYs in southeastern NB distressing. It's not just about tomatoes any more.............
 
PAC recommended it for rezoning. Unfortunately, council does not agree that it's a good place for an apartment. Looks like the vote was 6-1 against the development.
 
The concrete footings have been poured for at least two of these buildings on Pine Glen Road, eventually bringing more people into the Findlay Park area.
51363744480_ed623edb46_b.jpg
 
I am hoping once the project is complete the Tides building looks a little better. I find it rather clunky and uninspiring.
 
I am hoping once the project is complete the Tides building looks a little better. I find it rather clunky and uninspiring.

Agree! When they started the exterior, I thought is was terrible. I didn't like the white bricks at all. But as they keep working on it, it's starting to grow on me. Maybe when it's totally finished and nicely landscaped, it'll look good. It's been a construction site for way too long!
 
Still no structural steel up for the new Kent in Findlay Park. Site prep is complete, and the foundation was laid several weeks ago. I wonder what the hold-up is???
 
Still no structural steel up for the new Kent in Findlay Park. Site prep is complete, and the foundation was laid several weeks ago. I wonder what the hold-up is???

The last couple of times I've been by they've been working on the entrances, which look very wide. They're going to really hustle if they're looking to be open by Christmas!
 