Melo Inks Utilities Deal For 710 Units At Square Station

Melo Group finalized a deal this week to provide water and sewer service for 710 residential units at Square Station, which will begin construction soon down the block from the Arsht Center.

The developer will pay a connection charge estimated to be $744,435, along with a Biscayne Basin connection charge of $451,560.

Carlos Ferreira de Melo and Martin Ferreira de Melo signed the agreement on June 13. The county approved it this week.

Square Station is also supposed to include 15,000 square feet of commercial space, but the utilities deal only calls for the residential units. The project will also include 946 parking spaces.

DKo4fXR.jpg

Credit: https://imgur.com/DKo4fXR
============================
NXT
 
Thank you GD for the updates. Your blog is phenomenal. It's great to get a status update on the dozens upon dozens of projects by simply searching your blog by project name and getting so many high res photos from a drone. What drone do you use if you don't mind me asking (I'm a drone nerd and love my Phantom 3 Professional)
 
Last edited:
Thank you GD for the updates. Your blog is phenomenal. It's great to get a status update on the dozens upon dozens of projects by simply searching your blog by project name and getting so many high res photos from a drone. What drone do you use if you don't mind me asking (I'm a drone nerd and love my Phantom 3 Professional)

My pleasure. I'm glad you are enjoying the site and the construction updates!
 
^ Hopefully something tall will be built there since the site is zoned for up to 649 feet | 198 meters high.
By the way are those tennis courts in blue?
 
Miami-Dade commission gives thumbs up to Douglas Metrorail Station redevelopment

Project will have 970 residences, 150-key hotel, retail and a public plaza
July 19, 2016 05:45PM
By Sean Stewart-Muniz


Link-at-Douglas-1.jpg

Rendering of the Link at Douglas

The Link at Douglas is a go.

County commissioners on Tuesday approved a deal paving the way for 13th Floor Investments and the Adler Group to build their 7-acre development at the Douglas Road Metrorail Station.

The deal boils down to a ground lease for Adler and 13th Floor to redevelop county-owned land at the Metrorail station, which is currently occupied by a parking lot and the county’s Water & Sewer Department headquarters.
Under the approved deal, Adler and 13th Floor have a lease on the land for 30 years, plus two options to extend the term for another 30 years each.

The two partners now have the green light to move forward with their massive mixed-use development, complete with 970 residences, a 150-key hotel, 70,000 square feet of retail space and a public plaza.

According to a news release from the developers, Link at Douglas will be built in four phases.
The first phase will include a residential tower, the hotel and a portion of the retail section that will include a “premium supermarket.”
Driftwood Hospitality Management, which primarily owns and operates hotels under brands like Marriott and Hilton, will be a partner in the project’s hotel portion.

The deal appears to be a fruitful one for the county: Link at Douglas is expected to create 1,400 jobs during its development, according to the county, along with a minimum of 223 permanent positions once it’s completed.
Along the way, $464 million in revenue is projected to flow during the first 30 years to the county’s Department of Transportation and Public Works, which will be the only public entity to see proceeds from the project.

The deal came with other county-mandated stipulations: 13th Floor and Adler will have to reserve at least 12.5 percent of its 970 residential units for workforce housing, spend $14 million on improving the Metrorail station and make a $600,000 contribution to the Underline Project.
The two previously made a $25,000 donation to the Underline, which is a planned 10-mile linear park that would run underneath the elevated Metrorail lines.

13th Floor and Adler had been competing with the Related Group for the project, which came about from a “request for proposals” issued two years ago by Miami-Dade. Besides the economic windfall, the county’s goal for the project is to promote “maximum patronage of the transit system” that links the nearby neighborhoods Coral Gables and Coconut Grove to downtown Miami.

http://therealdeal.com/miami/2016/0...-up-to-massive-douglas-station-redevelopment/

orange-line-map.jpg

http://www.miamidade.gov/transit/images/orange-line-map.jpg

Douglas_Road_Metrorail_Station_Miami_Volare_Realty.jpg

http://9762-presscdn-0-23.pagely.ne...oad_Metrorail_Station_Miami_Volare_Realty.jpg
 
Last edited:
Awesome pics ! The artist rendition of these building sure looks different than the reality. I live a block away, and the bubble balconies are barely noticeable.

Thank you! That's what people are mentioning too, but it's still early and the bubbles are visible on the back. It's hard to see them on the front, but that is because the blue plastic is still on.
 
Thank you! That's what people are mentioning too, but it's still early and the bubbles are visible on the back. It's hard to see them on the front, but that is because the blue plastic is still on.

Not that its a bad thing. I would prefer the bubbles not be obvious and cartoonish like the rendering.
 


Back
Top