Sun Times is reporting that Fifield has a plan for the Kennedy cap between Washington and Adams. He has a cost figure of $60M for the 3-block stretch, which I think is wildly optimistic (the similar Woodall Rodgers Park in Dallas cost $90M for half the acreage). There's also the matter of getting IDOT to accept ramp closures, or the park will have do a ton of structural acrobatics and will be chopped up by ramp cutouts.

There's also the matter of structural depth - Fifield's plans (by SMDP) show a flat park, but to get enough structure to span the Kennedy and hold soil for trees, you would need a pretty thick deck. Unless you can depress the expressway further (which requires longer ramps and reconstruction of utility lines) I think the park would have to be above the grade of the existing street overpasses..

park2q.jpg


park1e.jpg

Uh, thanks for the info and images but I think one BIG thing might have been missed: what is that shiny new tower in the rendering above, seemingly between Presidential Towers and the new park??? Is that a Fifield proposal? Has anything ever been discussed before for that parcel?

EDIT: Just found the images below on SMDP's website:

West-Loop-Master-Plan-02.jpg


West-Loop-Master-Plan-01.jpg


West-Loop-Master-Plan-03.jpg


West-Loop-Master-Plan-04.jpg


http://www.smdpstudio.com/
(under 'new West Loop master plan')

I wonder if this whole thing is just something very speculative :shrug:
 
Last edited:
Sun Times is reporting that Fifield has a plan for the Kennedy cap between Washington and Adams. He has a cost figure of $60M for the 3-block stretch, which I think is wildly optimistic (the similar Woodall Rodgers Park in Dallas cost $90M for half the acreage). There's also the matter of getting IDOT to accept ramp closures, or the park will have do a ton of structural acrobatics and will be chopped up by ramp cutouts.

There's also the matter of structural depth - Fifield's plans (by SMDP) show a flat park, but to get enough structure to span the Kennedy and hold soil for trees, you would need a pretty thick deck. Unless you can depress the expressway further (which requires longer ramps and reconstruction of utility lines) I think the park would have to be above the grade of the existing street overpasses.

Just looking at the renderings it appears that they're messing with the grades a quite a bit. A flat park would be preferable but they would have to lower the highway which would be enormously more expensive. Given the spans required (assuming ramp closures make room for columns) it seems doable.

I'd prefer any solution like this run from the south side of Lake to Jackson but if this can be accomplished for a semi-reasonable budget it deserves to get pushed forward.
 
Uh, thanks for the info and images but I think one BIG thing might have been missed: what is that shiny new tower in the rendering above, seemingly between Presidential Towers and the new park??? Is that a Fifield proposal? Has anything ever been discussed before for that parcel?

Didn't Hines buy that piece of land from MR Properties? IIRC, a large office tower was proposed for that site.
 
Sun Times is reporting that Fifield has a plan for the Kennedy cap between Washington and Adams. He has a cost figure of $60M for the 3-block stretch, which I think is wildly optimistic (the similar Woodall Rodgers Park in Dallas cost $90M for half the acreage). There's also the matter of getting IDOT to accept ramp closures, or the park will have do a ton of structural acrobatics and will be chopped up by ramp cutouts.

There's also the matter of structural depth - Fifield's plans (by SMDP) show a flat park, but to get enough structure to span the Kennedy and hold soil for trees, you would need a pretty thick deck. Unless you can depress the expressway further (which requires longer ramps and reconstruction of utility lines) I think the park would have to be above the grade of the existing street overpasses.

park2q.jpg


park1e.jpg

Way back I looked at this in one of my planning studios. It's very difficult. I did have to raise the grade of the park to buy structural depth and also raise the grade of the sidewalks with the park so that the parks could be ADA accessible. Didn't matter so much the roads or shall I shall overpasses appeared depressed from the park because it was safer. The trees and soil were within cellular containers nested within the park substructure over the freeway lanes.

I also acknowledged modern FHWA standards for on and off ramps, so they grew a little. I also had to provide emergency egress because I was creating a tunnel. So the park would be littered with hatches or possibly have egress stairwells pop up in a few of the structures they proposed. And those hatches have to be on the perimeters of the park unless they can bore exit passageways beneath the existing freeway. Ugh it gave me headaches. Good luck to them.

In my project I tried to assume the number of freeway lanes and ramps were fixed and could not change. But I knew this was short sighted. I don't believe that congested and confusing mess is all that safe or efficient. It would be better to rebuild the whole thing to modern standards, new drainage and utilities and a new lower elevation. But a the same time you need to extend ramp approaches and acceleration lanes to accomplish that.

One thing I did to help with that was complete elimination of center ramps and some of those side ramps. Only Monroe and Randolph were directly connected with what I designed as "super ramps" which dumped you onto a service street that would connect all those intermediate streets. This achieved the following:
1. Eliminated Blind views turning onto city streets from offramps
2. Reduced the number of pedestrian crossings
3. No more unsafe merging into the far left lane of the freeway.
4. Allow local and express separation on the Kennedy
5. Double decel / accel lane length for ramps
6. Allow queuing to occur on service drive rather than city streets during congested rush hour.
 
One thing I did to help with that was complete elimination of center ramps and some of those side ramps. Only Monroe and Randolph were directly connected with what I designed as "super ramps" which dumped you onto a service street that would connect all those intermediate streets. This achieved the following:
1. Eliminated Blind views turning onto city streets from offramps
2. Reduced the number of pedestrian crossings
3. No more unsafe merging into the far left lane of the freeway.
4. Allow local and express separation on the Kennedy
5. Double decel / accel lane length for ramps
6. Allow queuing to occur on service drive rather than city streets during congested rush hour.

Yeah, this is what I was anticipating as well. I think you would need a collector street on the surface if you want to eliminate ramps. The ramps themselves could also get wider to allow for more queuing.

The other problem is the facing buildings. Building a park is nice, but so many of the buildings along the trench turn their backs to the highway, even the modern ones like Skybridge. If the city has a long-term planning vision for a cap, they should be pressuring the development proposals accordingly.

I hope the upcoming Circle Interchange project takes this into account and anticipates some consolidation of ramps.
 
I don't think this project is real, at least not in the configuration as currently shown. If you look at the renderings above, the site plan doesn't match the rendering of the park, or the overall aerial rendering either. If this is a real proposal, then it appears to require additional refinement and considering that I don't believe that this was reported anywhere but the Sun Times, I think it's fair to say this is just speculative. For now.
 
How realistic is any reconstruction of the downtown expressway, given that (1) money was just expended on rebuilding many of those ramps last year (chiefly on the southbound side) as well as in recent years (center ramps and northbound side), and (2) the Circle Interchange looks like it's now proceeding as a real project (albeit early stages), despite it surely being crucial that the interchange and the trench be planned (and maybe even constructed) in concert with each other?

I love the idea Hayward described, but are we talking about 2020 or about 2040?
 
How realistic is any reconstruction of the downtown expressway, given that (1) money was just expended on rebuilding many of those ramps last year (chiefly on the southbound side) as well as in recent years (center ramps and northbound side), and (2) the Circle Interchange looks like it's now proceeding as a real project (albeit early stages), despite it surely being crucial that the interchange and the trench be planned (and maybe even constructed) in concert with each other?

I love the idea Hayward described, but are we talking about 2020 or about 2040?

Is that a rhetorical question or are you just splitting hairs about whether or not this is actually a feasible endeavor? To be honest I'm not certain, thus the questioning...
 
^ I wasn't responding to you specifically, just the whole discussion. My question is not really rhetorical, given that the talk seems to be treating it as a possible reality now.
 
Good article - much more than just a detailed walkthrough. I didn't know the city's biggest wine selection is 35000+ bottles at Italian Village. I also chuckled at the comparisons with the Del Frisco hometown (Dallas) style, eg. the troughs in the bathrooms and rancher versus banker tastes.

========================

Meanwhile, around the corner -- Starbucks de luxe (not its real name) plans to open on Rush on 12/5. 'Tis the season of the flagships all around downtown it seems. (Old Navy's grand opening at Randolph and State this week also joins Burberry from earlier this month.)
 
^ I wasn't responding to you specifically, just the whole discussion. My question is not really rhetorical, given that the talk seems to be treating it as a possible reality now.

Idk, I just feel like there is nothing substantial here, other than these (admittedly very nice) renderings. I'm just playing devil's advocate, because as much as I would personally LOVE to see a park over the highway here (I've even worked on a speculative design of my own over two years ago! Sketches, some simple 3D modeling, nothing more really), I'll wait until something appears on Crain's :haha:
 
Indeed, I recently saw a lovely, skillful rendering of a deck over the south end of Grant Park, covering the Metra tracks from 9th to Roosevelt. But I didn't see the point of even posting about it.
 
^if you have the ability/permission to do so Mr. D, please do post - even speculative designs are always great to look at and I'm sure others in the forum would appreciate anything new; I know I would.
 
Does anybody know what is up with stay bridge? I saw a lone construction worker staring at the building just now.

They get deliveries of stuff maybe once a week or so. There appears to be some activity on the interior, perhaps remediating the impact of weather-related deterioration. It could be that they're waiting for a full plan from engineers, or waiting on city inspections or permits. There is some slow work going on, but it's painfully slow. I was hopeful when they re-took the parking lane that they were on the cusp of a faster work pace, but so far not. They did rebuild the ground house around the construction elevator (or whatever that's called).

I'm not sure how they'll address the fireproofing on the steel beams that's been knocked off. would they have to completely remove it, scour off the surface rust, and re-apply? Or can they just knock off any loose bits and re-spray?
 