Scaffolding going up next to the 725 Granville main (?) entrance next to the Canada Line station exit. I assume they are opening it up for the new CRU entrance.
Pic by me today:
Wording suggests a fashion retailer.
Scaffolding going up next to the 725 Granville main (?) entrance next to the Canada Line station exit. I assume they are opening it up for the new CRU entrance.
Okay, my money's on either Uniqlo or Simons, one of the two.
DATE: April 13, 2026
ATTENTION: All Office Tenants – Pacific Centre
WHAT: Canada Line Doors Replacement
WHY: We will be undertaking a short project to replace the Canada Line doors that provide access from the Canada Line station into the CF Pacific Centre shopping mall, which is located below the TD Plaza at the corner of West Georgia and Granville Streets. This project is part of our ongoing commitment to enhancing the entry experience, building security and the overall reliability of our facility hardware.
To minimize disruption to your daily commute, all work has been scheduled during off-peak and non-retail hours.
WHEN:
• 7:00 p.m. Sunday, April 19 to 7:00 a.m. Monday, April 20
• 7:00 p.m. Monday, April 20 to 7:00 a.m. Tuesday, April 21
• 7:00 p.m. Tuesday, April 21 to 7:00 a.m. Wednesday, April 22
• 7:00 p.m. Wednesday, April 22 to 7:00 a.m. Thursday, April 23
IMPACT: The Canada Line doors will be inaccessible during the dates and times listed above. Commuters are asked to use the escalators within the transit station to reach street level.
We apologize for this temporary inconvenience and appreciate your patience as we work to upgrade our building facilities.
By me today.
I'm hoping for automatic doors.
Effective dates: April 22, 2026 to June 20, 2026 FULL TIME to be extended once the granville corridor is open.
Permission is granted to the permit applicant to place 8' tall wall in front of 725 Granville St to enclose storefront as they demo the existing facade and reinstall.
Phase 1 of enclosure will be installed from April 22 to June 7, 2026 with the enclosure being adjusted for Phase 2 to 1m off PL on or before June 7 until Granville corridor for FIFA is completed July 20th.
1.8m sidewalk path must be maintained at all times.
IMO, during business hours, the passage should just be open at all times to facilitate foot traffic flow and minimize people having to touch things. Whether that's sliding glass doors that can be manually closed by a security guard or mall staff, or a retractable gate, or both...
The issue with that is it wreaks havoc with the HVAC systems and creates all sorts of pressurization problems in the mall.
I am sure it is only a result of the shrink wrap. It will expand back once the air is released. You'll see. :tup:I don't want to alarm anyone, but I think the Four Seasons tower is shrinking.
Simons said the new CF Pacific Centre store will span approximately 92,000 square feet across three floors