The Government Accountability Office on Wednesday denied a protest filed by Sletten Construction of Great Falls over the contract award for construction of a new federal courthouse in downtown Billings.
The GAO’s dismissal of the protest means that planning and construction on the courthouse can resume, according to the General Services Administration, the agency that is in charge of the project.
“What does this mean to Billings? It means that GSA will move forward as originally planned,” GSA spokeswoman Sally Mayberry said. “Next steps include having GSA’s project team meet with the project stakeholders and contractors to work out the new plan for project completion.”
Sletten was one of six finalist companies for the courthouse contract, but in late December the GSA chose Mortenson Construction of Minneapolis and awarded the company a $59.4 million contract. Sletten’s bid was $8 million less, company officials said.
A few weeks later, Sletten filed its protest. The company claimed that the GSA violated the terms of its own request for proposals by failing to consider price, especially as the proposals became more equal on technical grounds during the scoring. The GSA has said repeatedly that it used a “best value” approach and that price was just one of several factors used to score the proposals.
The GAO, known as the investigative arm of Congress, had 100 days to investigate Sletten’s protest after the company filed it in January. GAO head procurement attorney Ralph O. White said Wednesday that the agency’s ruling is sealed until both Sletten and Mortenson have a chance to review it. Proprietary information will be redacted, and a copy of the ruling should be released by next week, White said.
Sletten CEO Erik Sletten declined to comment, saying that his company hadn’t reviewed the ruling yet.
The GSA released a statement after receiving the GAO’s ruling. GSA spokeswoman Mayberry said the courthouse project can now continue as planned. She said there will be a stakeholders’ meeting in early May where everyone involved in the project will regroup and plan the next steps.
“GSA’s goal is to focus on getting people to work and getting the project under way as soon as possible,” Mayberry said. “More information will be available once the project team has had the opportunity to meet and assess the revised project schedule.”
The 146,700-square-foot courthouse will be built on a 63,000-square-foot site next to the Yellowstone County Courthouse. The GSA paid $3 million for the site, which was pieced together like a jigsaw puzzle from different landowners. Half a block of North 26th Street near the courthouse has already been permanently closed to traffic, and the site is ready for construction. Two buildings were dismantled to clear the site.
he new courthouse will replace the James F. Battin Federal Courthouse, which is laden with asbestos and will likely be torn down someday. The new courthouse will house the federal courts, the U.S. Attorney’s office and the U.S. Marshal. The Bureau of Indian Affairs and the Bureau of Reclamation, now in the Battin courthouse, will be moved to new offices eventually.
For several years, those involved in the project were expecting a privately owned courthouse that would be leased back to the GSA. But a year ago, Sen. Max Baucus, D-Mont., announced that the GSA would spend up to $80 million in stimulus funds on a courthouse owned by the GSA.
Had the GAO agreed with Sletten’s protest, the GSA could have been ordered to restart the bidding process. GSA officials were worried about that prospect, because the lengthy process would have to be completed before the end of the fiscal year on Sept. 30.