Aura?


I read that 80% or more of the condos at Aura had deposits down on them already. With that in mind, why are they having such trouble securing financing? Did they not charge enough for the condos, and there's not enough money to be made? Just wodnering

No one seems to really known what is going on. I doubt Nassi himself knowns. Let's see..

preconstruction costs locked in = check
rival's project down the street in the crapper = check
city subsidy errrrr funding gap loan in place = check
site purchased and ready for immediate work = check
building upwards of up to 70 - 80% sold through = check
according to Nassi main construction loan in place = check

and yet silence??????
 
I say Nassi and Moe need to form a partnership......(the think big and accomplish nada committee)......

as for Aura......Nassi Nassi Nassi......tick tick tick.....

hmmm and I remember all the talk of 2 buildings going up simultaniously on the 600 block......and all the conflicts it would cause......
 
I say Nassi and Moe need to form a partnership......(the think big and accomplish nada committee)......

as for Aura......Nassi Nassi Nassi......tick tick tick.....

hmmm and I remember all the talk of 2 buildings going up simultaniously on the 600 block......and all the conflicts it would cause......


Yeah that's such a great excuse for the delay... One trip to Vancouver puts that theory to bed!
 
^ The only person who has ever said that is web... nothing has ever been
said or written saying that the delay is because two buildings can't rise at
the same time. The delay has to do with financing, always has been.
 
de-watering??????

Yesterday, I had dinner and drinks with a structural engineering buddy that works for an engineering firm in town, so he sometimes gets to hear tidbits. He said indeed that the Aura site is being de-watered. That should take about two months before site excavation begins which should take another two months, he says. So, basically, Aura will start going up in about 4 months.

According to him, Nassi was basically waiting to see what poker hand will be dealt with John Saca's Towers project. Had those buildings gone up, there would be no Aura. Aura has also added more people switching from the Towers project.

Ironically, he told me more than a year ago that the Towers would not be built because of the high water table at that location makes it cost prohibitive to construct twin 54 story towers and make any profit. Five blocks away and a 54 story tower(s) would have been more cost feasible because of the lower water table, he said.
 
Don't take this personal otnemarcaS, but your buddy's full of it. There is no
de-watered equipment at the site. The site had a drainage line put in for a
parking lot, but they have stopped short of paving over the lot. Nassi has till
August to secure the loan needed to fill the gap to then start the project.
I don't think Nassi planned it this way. The price of the land has gone up several
million since the first agreement was struck to by the land from Taylor.

Also, Boston and NYC have high water tables and that has not stopped
those cities from building big... it can be done.
 
Yesterday, I had dinner and drinks with a structural engineering buddy that works for an engineering firm in town, so he sometimes gets to hear tidbits. He said indeed that the Aura site is being de-watered. That should take about two months before site excavation begins which should take another two months, he says. So, basically, Aura will start going up in about 4 months.

According to him, Nassi was basically waiting to see what poker hand will be dealt with John Saca's Towers project. Had those buildings gone up, there would be no Aura. Aura has also added more people switching from the Towers project.

Ironically, he told me more than a year ago that the Towers would not be built because of the high water table at that location makes it cost prohibitive to construct twin 54 story towers and make any profit. Five blocks away and a 54 story tower(s) would have been more cost feasible because of the lower water table, he said.



I'm a little confused with your statement. Did your "engineering buddy" say that they plan on de watering soon or that they were currently de watering?
Because with all due respect, they are not currently de watering that site.

When they do, it should be clearly visible and i just drove by the site yesterday and they definitely were not in the process of de watering 601 CM (that I could see)..

It does however look like they are still dewatering parts of 500 CM, even while foundation work continues.

I hope it still Aura happens, but unless anyone has any new updates, Nassi still doesn't own the land or hold the option to buy it and still hasn't picked up his permits.
 
Don't take this personal otnemarcaS, but your buddy's full of it.

Agreed...

Ironically, he told me more than a year ago that the Towers would not be built because of the high water table at that location makes it cost prohibitive to construct twin 54 story towers and make any profit. Five blocks away and a 54 story tower(s) would have been more cost feasible because of the lower water table, he said.

The above statement does not make sense. The water table issue becomes relavent in terms of how deep you are excavating, not how high you are building. The cost prohibitive portion could be the need for an exteremely thick foundation to counteract buoyancy effects of the high water, but the site looks like it was only excavated one level below existing ground (approx. elev. 23' MSL), which would place the bottom of the pit at about elev 5' MSL or so. This is below winter high groundwater for the area but not that far below (the excavation for the CalPERS expansion headquarters was below elev 0' MSL as a comparison). The height and mass of the building would actually help with the buoyancy issue, because you have the entire weight of the building counteracting the upward force of the water.
 
Don't worry folks, nothing taken personal by me. I can't say that I completely agree or disagree with your disagreement of my friend's statement .... just putting out what he had said from what he knows. I believe he might have said they are getting ready to de-water the site and that should take about two months. I can ask him again when I see him again.

We were at Crawdads on the river and another friend in the group of four had purchased one of the condos at the Towers. So there was some intriguing conversation about Saca not being able to pull off this project. In a nutshell, he said the cost of driving in the deeper piles for that high water table location and getting the site ready was already so high even before construction that it just wasn't going to pencil out financially. My other buddy that bought a condo insisted that the timing of the project (later in a down market rather than in, say, 2002) plus Calpers withdrawal doomed the project. My engineering friend is familiar with, and has worked with, some of the firms or people involved with the Towers project site so he does get to hear inside construction info around town.
 
Don't worry folks, nothing taken personal by me. I can't say that I completely agree or disagree with your disagreement of my friend's statement .... just putting out what he had said from what he knows. I believe he might have said they are getting ready to de-water the site and that should take about two months. I can ask him again when I see him again.

We were at Crawdads on the river and another friend in the group of four had purchased one of the condos at the Towers. So there was some intriguing conversation about Saca not being able to pull off this project. In a nutshell, he said the cost of driving in the deeper piles for that high water table location and getting the site ready was already so high even before construction that it just wasn't going to pencil out financially. My other buddy that bought a condo insisted that the timing of the project (later in a down market rather than in, say, 2002) plus Calpers withdrawal doomed the project. My engineering friend is familiar with, and has worked with, some of the firms or people involved with the Towers project site so he does get to hear inside construction info around town.

I dont know much about construction costs and what goes into pre-construction cost analysis, but I highly doubt the Towers folks forgot to include in their estimate the impact of a high water table. If they did forget then they deserve this project falling apart.
 
Nassi has tillAugust to secure the loan needed to fill the gap to then start the project. I don't think Nassi planned it this way. The price of the land has gone up several million since the first agreement was struck to by the land from Taylor..

It would be a shame if Aura doesn't happen because Taylor is hoping to cash in big on the property at 601 CM.

Though i imagine if Aura doesn't happen, it will be because Nassi wasn't able to get financing from lenders and not because Taylor is looking for more $$$ for the property.
 
Aura Dewatering

As a former buyer of an Aura unit (who backed out last December and purchased an L Street Lofts unit when it became clear that the Aura project was not going to happen any time soon), the dewatering and excavation explanations do not make sense, unless the project has been redesigned. The original construction and engineering drawings that I saw last year, confirmed by verbal representations from the sales manager, indicated that the Aura project was to be an above-ground project. The excavation was to be about three feet below surface level, at most.

SacUrbnPlnr
 
I dont know much about construction costs and what goes into pre-construction cost analysis, but I highly doubt the Towers folks forgot to include in their estimate the impact of a high water table. If they did forget then they deserve this project falling apart.

Yeah, I'd highly doubt this also. During due-diligence, you'll often do your cost projections in-house to get a basic idea of what you can do with the site. Some of these are more detailed than others. But by the time you get to the in-house approval (from your acquisitions committee or forward planning committee or bank loan committee, whatever you want to call it), you need to have a thorough understanding of what it's going to cost and you usually have hired some kind of outside cost consultant that specializes in the field and market to give you an accurate assessment. Certainly that was the case on a project the size, scope and cost of the Towers (or Aura). For a Sacramento-based firm not to have taken into account the water table is unfathomable. Just for starters, they would never be used again in the market and might as well pull-up stakes.

Now that doesn't mean you can't massage the numbers to get approval or funding. It happens. You also always include a contingency for unforeseen events that can range from 5% to 20% depending on risk (e.g. - if there is a lot of rock/boulders visible on the surface - your grading contingency is going to be high because even with the best testing, you're going to find a lot of boulders you didn't count on. These are referred to as, "rock jobs.").

But any PM or bank in Sacramento is going to demand a budget line item that accounts for extra costs from water-table related items.
 
601 Cm?

I could be reading this entirely wrong - but I thought this was peculiar... Doing a permit search on 601 Capitol Mall I stumbled across what looks like a new building entirely. 621 Capitol Mall (US Bank building) is split into two parcels. There are no permits showing for the address of 601, but there is one showing on 621 that has a different "land area" number than all the rest of 621's permits. I'm not positive what that means, but I think it means a different piece of land entirely.

The following is a new permit, or inquiry pertaining to that parcel that doesn't seem to match the description of either Aura or the US Bank building. Let me know what you guys think this may mean...

Permit Number: COM-0711097
Type / Classification: Building Commercial New Building / Industrial
Address: 621 CAPITOL MALL SACRAMENTO, CA 95814
Parcel Number: 00601510140000
File Date: 7/17/2007
Status: BLDG_Com - Estimate
Status Date: 7/17/2007
Description: Industrial Fee Model 5

Total Sq Ft: 550,000 (US Bank is about 365,000)
Name: San Joaquin Partnership


:shrug:
 