Per your email, I am following up to regarding the status of the Emory Proton Therapy Center. The building is 80% complete and ready for equipment. We continue to work on closing our next round of financing so that the equipment can be shipped and installed. When the equipment arrives, there will be meaningful activity at the site and we would expect to treat our first patient approximately 15-18 months afterwards.
Several options have been considered for the North Avenue/Peachtree corner. The current design calls for a 5 story parking garage that will be wrapped (and hidden) by retail on Peachtree and a glass concourse on North Avenue. We have been approached by several developers about putting a boutique hotel, MOB (Medical Office Building), additional parking, etc. on the site. Once the financing on the primary facility is closed, we will evaluate all of the options and make a final decision.
Thank you for your inquiry and your interest. It is my hope that the project will be moving forward shortly.