Going vertical: Look for a flurry of activity next week at 500 Capitol Mall, site of a planned 25-story office tower.
Structural steel crews will be arriving Monday. By Tuesday, "it will be gangbusters," says Dave Glazier, superintendent of contracting firm Rudolph and Sletten, which is handling the job.
In fact, Glazier expects the front portion of the building's first eight floors to be framed within two weeks.
By year's end, a 600-foot-high crane will be brought in to begin work on the upper floors.
Anticipated completion date: spring 2009.
DALINSAC, where did you get this info... from the Bee or a website?
This sounds ridiculous. Why would a 400' tower have a 600' crane?
Bob's usually better about this stuff. It should be around the 500' mark because
621CM crane was 488' at its highest point... and yes, steel is starting to go up today :cheers: