401 Interchanges


Couple photos of the construction at 401 and 4, one showing the 4 work and the other the new Glanworth Dr overpass being built. Can't remember when I was last over here because I was surprised to see progress this far along. I think most of my trips to and from St Thomas recently have been no further west than Wonderland, but mostly the more easterly routes.

54439742171_4cc599d319_z.jpg


54439992483_70ced68f6c_z.jpg
 
401 eastbound has now shifted over to the middle section across the CN and Pond Mills overpasses and the highway is 2 lanes each way. I went through about 4pm today and it was flowing fine but I suspect there will be some times this backs up pretty decently. The former eastbound lanes have already been ripped out and I suspect after next week when Pond Mills Rd is closed that it won't be long before those remaining old overpass structures are dismantled.
 
Signs up for the 401 to be closed between VMP and Wellington Monday April 28 overnight into Tuesday morning, presumably for installation of bridge spans at Highbury. Seems odd to me to close it on a Monday night for that.
 
Last edited:
A few drone shots today showing the demolition of the remaining sections of the CN and Pond Mills overpasses as well as Highbury overpass progress.

54511861662_597faa2934_b.jpg


54512988913_6cc2a71e03_b.jpg


54512910554_881b1822b5_b.jpg
 
The new beams on the eastbound side were placed over Pond Mills Rd on Thursday. I didn't happen to notice if they have been done over the railway tracks yet, although based on my photos from a couple weeks ago, I would say they haven't progressed far enough yet to put them in.
 
can't quite remember, how many lanes are these bridges going to have? and are they being shifted?
 
can't quite remember, how many lanes are these bridges going to have? and are they being shifted?

I think they are being built to be able to be 10 lanes wide in the future. I doubt the highway will actually be that wide anytime soon, but I think they plan to have a continuous extra lane each way between Highbury and Wellington after. Pond Mills would also have the ability to be widened to 4 lanes under the highway if that need was ever deemed necessary.
 
can't quite remember, how many lanes are these bridges going to have? and are they being shifted?

Djeffery is correct... the 401 will just have 3 through lanes in each direction (as it exists today)... but there will be a fourth continuous lane.... I found this from a notice that was posted when construction began.

• Addition of continuous speed change lanes between the Highbury Avenue westbound on-ramp and the Exeter Road westbound off-ramp, and between the Wellington Road eastbound on-ramp and the Highbury Avenue eastbound off-ramp
 
The new Colonel Talbot - 401 overpass bridge deck is nearly ready for the concrete pour as most of the steel rebar is now setup.
 
MTO has been making progress removing the center barrier from just east of Wellington to now east of Highbury. Crews have steadily been cleaning it out.
 
They have now just passed Highbury as they work their way west installing the new center concrete dividing wall on the 401. Crews have been working removing the northbound lanes of the Highbury overpass bridge abuttments.
 
I am sorry, but what are we actually getting when this project is all done? Are they adding any lanes or doing anything that justifies the time it has taken to do this?
 
This project stretches from west of the Pond Mills/rail corridor bridges to east of Highbury and involves replacing and widening of the bridge overpasses and realignment of the Highbury and 401 interchange.
 
I am sorry, but what are we actually getting when this project is all done? Are they adding any lanes or doing anything that justifies the time it has taken to do this?

There will be a continuous auxiliary lane between the Wellington (Exeter) and Highbury interchanges when done.

In terms of actual interchange improvements, not really. The stoplights remain on Highbury.
 
Yeah, it's more about widening the 401. I think the only kind of improvement on Highbury will be a longer approach to the 270 loop ramps that had pretty short approach lanes before.
 
Yes as @Djeffery mentioned... there are long-term plans to widen the 401 to 8 or 10 lanes in this area (can't remember the number) so this new bridge will enable that when the time comes.

Google says that the Highbury bridge was built in the early 60s... so it probably needed replacement due to its age anyway.

For Highbury itself, it will be widened to 6 lanes between Bradley Ave and Wilton Grove Rd as part of this construction.
 
Hopefully the Bradley overpass on Highbury gets replaced soon as part of widening Bradley east of Wellington to VMP eventually. Maybe by 2050 long after all the new housing along Bradley is built out and the new industrial parks are full. :uhh:
 
You think Bradley will be built out with housing by 2050? There's enough land between Jackson and Old Victoria for 2-3 more Summersides and they have been building Summerside since the mid 90's.
 
Hopefully the Bradley overpass on Highbury gets replaced soon as part of widening Bradley east of Wellington to VMP eventually. Maybe by 2050 long after all the new housing along Bradley is built out and the new industrial parks are full. :uhh:

It's being rehabbed as part of the Highbury rebuild project. You could build a twin bridge next to it if you want to widen Bradley east past Highbury. It needs 4 lanes now from Highbury westward now.
 


Back
Top