[St Thomas] 1029 Talbot St - HighLands Tower - 14s (Under Construction)

Still working on the L1 footings and foundation walls and posts. Have started forming the ground floor slab on the north end of this 14s 162 unit apartment building in St. Thomas. Vandel Construction has the general contractor contract for this build.



LFP article from last fall on the start of the project.


https://lfpress.com/news/citys-talle...-building-boom


The project also has a website:


https://www.highlandsapartments.ca/#contact
Reply With Quote
     
     
  #2  
Old Posted Mar 13, 2024, 9:20 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,800
Have now got the NE corner of this building ground floor slab poured. Still working on the remainder of the L1 level forming. Progress is rather slow on this build.
Reply With Quote
     
     
  #3  
Old Posted Mar 30, 2024, 1:04 AM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,800
Interesting they are going with precast concrete walls and posts and floor slabs for this building. The ground floor is now complete and they have already installed the 2nd floor precast slabs. Still working on the underground parking level with all the walls and posts now poured but not the L1 floor as of yet.
Reply With Quote
     
     
  #4  
Old Posted Apr 10, 2024, 10:26 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,800
They have now installed the 2nd floor precast walls and posts on this 14s building.
Reply With Quote
     
     
  #5  
Old Posted Apr 15, 2024, 9:19 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,800
St Thomas expecting continued growth. Article also has photo of the new Highlands Tower now under construction.



https://london.ctvnews.ca/greater-th...wave-1.6847784
Reply With Quote
     
     
  #6  
Old Posted Apr 16, 2024, 1:35 PM
MolsonExport's Avatar
MolsonExport MolsonExport is online now
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 44,927
St. Thomas is on a roll. I recall the dark days of the Great Recession, when large factories were closing in St. Thomas, and unemployment was surging.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 5:04 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.