Originally Posted by urbancore
what would you guess is the typical time between site plan filing and breaking ground? 1-2 years?
|
Since Hanover has a good track record in actually building what they propose, I would say 1 1/2 years.
The site plan for their sister project - Hanover Republic Square - took 16 months to get approved. It was first filed in August 2018, and approval happened in December 2019. If you consider the time from when they filed their first demo permit to the time they received their construction permits, it took 19 months.