240 Oakland Ave - 6s

Bluestone Properties has the tower crane up for their new 6s apartment building.

https://pub-london.escribemeetings.c...cumentId=57246
Reply With Quote
     
     
  #2  
Old Posted Jul 28, 2019, 3:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
First floor walls now well underway. Looks like BlueStone is using Concrete Forming as contractor.
Reply With Quote
     
     
  #3  
Old Posted Sep 14, 2019, 5:04 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
3rd floor walls now started on the 6 story apt building. Should be topping out the mechanical penthouse in Dec.
Reply With Quote
     
     
  #4  
Old Posted Sep 24, 2019, 6:20 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Some of the 4th fl walls now started.
Reply With Quote
     
     
  #5  
Old Posted Nov 4, 2019, 5:07 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Looks like the final floor is now starting.
Reply With Quote
     
     
  #6  
Old Posted Nov 13, 2019, 8:01 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
About 40% done with final floor walls.
Reply With Quote
     
     
  #7  
Old Posted Dec 1, 2019, 8:10 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Final floor walls done. Most of roof installed and appear to have started on mechanical penthouse. Focus will now definitely change to exterior and windows.
Reply With Quote
     
     
  #8  
Old Posted Dec 21, 2019, 8:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
This is topped out now with mechanical penthouse completed. Exterior finishing and windows up next.
Reply With Quote
     
     
  #9  
Old Posted Feb 12, 2020, 9:01 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Tower crane has been removed now. Window installation moving along. Expect to be renting in the spring.
Reply With Quote
     
     
  #10  
Old Posted Mar 1, 2020, 3:14 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Stone exterior for first two floors now mostly installed.
Reply With Quote
     
     
  #11  
Old Posted Jun 12, 2020, 11:09 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Exterior now finished. Final finishing on interior and now leasing.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 8:06 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.