Western University - Entrepreneurship and Innovation Centre (Complete)
Excavation has started for the new 100,000 square foot Entrepreneurship and Innovation Centre located between the Library and Student Services Building along Western Rd. Norlon Builders Construction appears to be the contractor.
I've heard about this project, I'm very interested in how it will affect development in the region in the future. I read about a similar example of regional development at the expense of an elementary school on a student resource https://samplius.com/free-essay-examples/elementary-school/ with free essay samples. It attracts young families to migrate to the region and thus improves population density.
Last edited by SamuelBell; Aug 16, 2022 at 2:42 PM.
It's odd that Western choose to give up a basement level for this new building. Seems to be a big waste of what would be invaluable square footage to not have a basement level.
It is strange (no basement level). There are some buildings at UWO with 2, and even 3 basement levels.
I walk past this every day. The project is moving along fast.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
As a bonus, it will help to hide the street view of the bunker-like external ugliness that is the Weldon Library.
If only they could do something similar to hide the hideous Social Science Centre.
Quote:
Originally Posted by MolsonExport
Western's trio of fugly concrete bunkers
warning: ugly building alert!
uwo
blights on an otherwise beautiful campus
reddit
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Forming for the 3rd floor slab is nearly complete now with just some left on the south end. Should see some of the 3rd floor walls and posts poured by end of the month.
They now have some of the 4th floor posts poured and forming well underway on the north end. Forming for the 4th floor slab is also up on the south end.
Forming for the 4th floor roof slab now well underway on the north end. The 4th floor wall and posts forming is also progressing well on the south end.
Have now got all the 4th floor walls and posts poured and the north end appears to have the 4th floor roof slab poured as well. Still alot of forming left for the south end roof slab to be setup.