  #21  
Old Posted Feb 11, 2020, 8:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Excavation is under way for the phase east of the YMCA. Believe there are 2 buildings in this phase.
Reply With Quote
     
     
  #22  
Old Posted Feb 12, 2020, 1:45 PM
User_Name User_Name is offline
Registered User
 
Join Date: Sep 2018
Posts: 22
Quote:
Originally Posted by jammer139 View Post
Excavation is under way for the phase east of the YMCA. Believe there are 2 buildings in this phase.
Yes, they are starting with a large underground parking structure, then the 17 storey apartment building at the back of the site. Then the commercial building fronting Southdale.
Reply With Quote
     
     
  #23  
Old Posted Feb 25, 2020, 3:44 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,081
They are moving alone quickly on this project, impressed how much dirt has been moved and the amount of equipment there.
3 concrete trucks were lined up on site this morning when I drove by
Reply With Quote
     
     
  #24  
Old Posted Apr 27, 2020, 8:32 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
York has tower crane installed for this first phase. Couldn't see if they have started on footings yet.
Reply With Quote
     
     
  #25  
Old Posted Apr 28, 2020, 6:54 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,081
Quote:
Originally Posted by jammer139 View Post
York has tower crane installed for this first phase. Couldn't see if they have started on footings yet.
I have not looked in the pit yet, but the crane is active and there have been trucks and concrete on site randomly the past week or so.
I work around the corner so drive by this daily
Reply With Quote
     
     
  #26  
Old Posted Jun 10, 2020, 7:32 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Footings, posts and walls now poured for what looks like the L2 level of underground parking.
Reply With Quote
     
     
  #27  
Old Posted Jun 28, 2020, 7:44 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Getting L2 level floor ready for slab pour. Also have dug a deep hole to the south of the L2 level walls. Not sure what this is for as the apartment tower is further south of the building fronting Southdale Rd.
Reply With Quote
     
     
  #28  
Old Posted Jul 9, 2020, 8:31 PM
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,536
Base for a second crane now installed at the very southeast corner of the hole.
Reply With Quote
     
     
  #29  
Old Posted Jul 13, 2020, 2:47 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Almost done the steel rebar for a large floating slab pour. Should be poured this week. Strange location as the plans showed the 17s tower further south and oriented east west. The 3s office building fronts Southdale Rd and appears to be following the plan.
Reply With Quote
     
     
  #30  
Old Posted Jul 21, 2020, 7:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Floating raft slab poured today and the 2nd tower crane is now up. Also forming underway for what looks like the L1 floor slab under the 3 storey building that will front Southdale.
Reply With Quote
     
     
  #31  
Old Posted Aug 5, 2020, 9:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Getting very close to pouring the L1 floor slab under the building fronting Southdale. Preparing the L2 floor slab for the parking garage now. Should be pouring that next week. The floating slab foundation has got alot of rebar installed and appears close to the concrete pour under what may be the residential building. The orientation is different then what was shown in the early plans. They may have changed it.
Reply With Quote
     
     
  #32  
Old Posted Aug 16, 2020, 11:59 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
L1 floor slab under office building is poured. Footing slab is partial poured on west side of what may be second building.
Reply With Quote
     
     
  #33  
Old Posted Aug 18, 2020, 12:51 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Ellis Don sign up on the tower crane. Looks like they are helping York with this project too.
Reply With Quote
     
     
  #34  
Old Posted Aug 30, 2020, 7:22 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Starting on L1 walls and posts now. Working on foundation still under the apartment building.
Reply With Quote
     
     
  #35  
Old Posted Sep 5, 2020, 7:47 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Floating slab under the 17s apartment now poured. More progress on the L1 walls and posts under the commercial building.
Reply With Quote
     
     
  #36  
Old Posted Sep 16, 2020, 1:19 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Updated Urban Design Brief for the phases of this project.


https://www.london.ca/business/Plann...2020-09-16.pdf
Reply With Quote
     
     
  #37  
Old Posted Sep 17, 2020, 3:30 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Pouring the last section of the L1 slab for parking garage today. Alot of the L1 posts and walls are now poured or formed.
Reply With Quote
     
     
  #38  
Old Posted Sep 19, 2020, 8:44 PM
FWD15 FWD15 is offline
Registered User
 
Join Date: Jan 2017
Location: London
Posts: 43
Looks like both buildings are progressing together now.

Reply With Quote
     
     
  #39  
Old Posted Sep 24, 2020, 2:53 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
Progress on L1 level walls with steel rebar being installed in prep for the forming.
Reply With Quote
     
     
  #40  
Old Posted Oct 2, 2020, 5:04 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,786
The ground floor slab under office building has now been poured. Progress continuing on L1 wall forming and pouring for parking garage and under apartment tower.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 10:27 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.