O-Train South Extension - Construction Update
July 3, 2020
In the south, there is ongoing work at the Walkley Maintenance and Storage Facility (MSF) and on multiple rail bridges including Airport Parkway, Uplands Road, Lester Road, Leitrim Road, Bowesville Road, Earl Armstrong Road, and Limebank Road.
Existing Trillium Line:
Gladstone Station
▪ Rock excavation is underway through the use of hoe ramming and controlled blasting.
Carleton Station
▪ Work is starting at Carleton Station to create a laydown area. MUP and pedestrian detours will be implemented to reroute the public away from construction.
Dows Lake Tunnel
▪ Preparations are underway for the removal of rail in the Dows Lake Tunnel.
▪ Rail and track ties have been removed from outside the south entrance of the Dows Lake Tunnel.
Ellwood Diamond
▪ Crews have removed the northbound and southbound sections of rail and track ties to accommodate the construction of the new rail bridge between Mooney’s Bay Station and Walkley Station which will carry Line 2 over the VIA rail corridor.
▪ Caisson work is currently underway.
Walkley Maintenance and Storage Facility (MSF)
▪ Crews continue to work on the MSF Main Building foundations including concrete work for the light and heavy maintenance pits, elevator pits, grade beams and underfloor services.
▪ Civil works for the underground utilities including watermain, storm drainage and sanitary system are continuing.
▪ Rail removal near the MSF is underway.
Trillium Line South Extension:
Airport Parkway Rail Bridge
▪ Retaining wall construction is complete.
▪ Crews completed the installation of rail bridge girders during the daytime on June 16 and overnight on June 17.
▪ Precast concrete span girders are hoisted at night with a 500-tonne crane.
Airport Elevated Guideway
▪ 13 of 17 caissons have been poured to date.
▪ 8 of 17 columns have been poured to date.
▪ Column work is complete at the Airport loading dock and crews are constructing the pier cap.
Uplands Drive Rail Bridge
▪ Crews completed the installation of rail bridge girders overnight on June 8.
▪ Retaining wall construction continues.
Lester Road Rail Bridge
▪ Pier cap construction continues.
▪ Preparations are underway for installation of rail girders on July 2.
Bridge superstructure work continues at Lester Rail Bridge. Girder installation took place on July 2, 2020.
Leitrim Road Rail Bridge
▪ 2 of 4 caissons are complete. The 2 remaining north caissons are pending watermain reconfiguration.
▪ Preparations are underway for 2 of the 4 columns.
▪ Construction of retaining wall is underway.
Bowesville Road Rail Bridge
▪ Crews completed installation of rail bridge girder installation overnight on June 10.
Earl Armstrong Rail Bridge
▪ 4 of 4 caissons are complete.
▪ Work on 4 columns and pier caps continue.
Limebank Elevated Guideway
▪ 5 of 10 caissons are complete.
▪ Crews have started constructing 5 of 10 columns.
▪ Ground improvement work for the Limebank Road embankment continues.
Guideway between Leitrim Road and Earl Armstrong Road
▪ Ground improvement work is underway at the Earl Armstrong Road embankments.
Guideway between Hunt Club Road and Leitrim Road:
▪ Embankment work is ongoing.
https://mailchi.mp/95d2467ff0a5/o-tr...0?e=a999a549a3