  #161  
Old Posted Sep 3, 2021, 10:21 PM
sparky212's Avatar
sparky212 sparky212 is offline
Registered User
 
Join Date: Jul 2008
Location: London Ont.
Posts: 506
Reply With Quote
     
     
  #162  
Old Posted Sep 6, 2021, 6:00 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,116
Exciting to see the progress. Thanks for sharing that photo!
Reply With Quote
     
     
  #163  
Old Posted Sep 6, 2021, 7:16 PM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,243
Nursing a sore knee from work, so I didn't walk to the best vantage point, so this is from Lerners parking lot.





Reply With Quote
     
     
  #164  
Old Posted Sep 7, 2021, 1:31 PM
plcan1 plcan1 is offline
Registered User
 
Join Date: Jan 2019
Posts: 18
Thanks for update pictures
Reply With Quote
     
     
  #165  
Old Posted Sep 13, 2021, 8:40 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,094
Dump trucks and excavator on site today removing the next 3 meters of soil from the pit. Most of the ground floor posts and walls are now poured and the focus is on forming and steel rebar for the 2nd floor slab under the south tower.
Reply With Quote
     
     
  #166  
Old Posted Sep 17, 2021, 2:21 AM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 44
was able to sneak a quick picture while in 500 talbot today.

Reply With Quote
     
     
  #167  
Old Posted Sep 17, 2021, 12:18 PM
inimrepus inimrepus is offline
Registered User
 
Join Date: Jan 2017
Location: Earth
Posts: 175
Yep, sure looks like a nice hole
Reply With Quote
     
     
  #168  
Old Posted Sep 17, 2021, 4:01 PM
GreatTallNorth2 GreatTallNorth2 is online now
Registered User
 
Join Date: May 2006
Posts: 1,745
Wow, 2023 looks pretty optimistic.
Reply With Quote
     
     
  #169  
Old Posted Sep 17, 2021, 4:02 PM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,832
Quote:
Originally Posted by GreatTallNorth2 View Post
Wow, 2023 looks pretty optimistic.
is 2023 not for the first building that's already above grade?
Reply With Quote
     
     
  #170  
Old Posted Sep 17, 2021, 5:04 PM
GreatTallNorth2 GreatTallNorth2 is online now
Registered User
 
Join Date: May 2006
Posts: 1,745
Quote:
Originally Posted by Innsertnamehere View Post
is 2023 not for the first building that's already above grade?
Yes, but its 40 floors and at the rate they are going, that will be hard to meet that timeline.
Reply With Quote
     
     
  #171  
Old Posted Oct 2, 2021, 1:34 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,094
Looks like they have poured a section of 2nd floor slab in the SW corner of the south tower now. Foundation crew progressing now with the next row of horizontal cable bracing into the caisson pit walls. Will probably be starting the next stage of excavation down to bottom depth in a couple of weeks. Might see them use a conveyor belt to remove the soil from that depth as you won't be able to get real heavy equipment down.
Reply With Quote
     
     
  #172  
Old Posted Oct 6, 2021, 12:51 PM
Puddin74 Puddin74 is offline
Registered User
 
Join Date: Jul 2021
Location: London
Posts: 13
Current Schedule is shooting for:
9 Storey Podium (middle part) - Occupancy Aug 4/23
40 Storey Building B - Occupancy Mar 7/24
29 Storey Building A - Occupancy May 23/24

Then a month later all Deficiencies should be completed
Reply With Quote
     
     
  #173  
Old Posted Oct 6, 2021, 1:13 PM
GreatTallNorth2 GreatTallNorth2 is online now
Registered User
 
Join Date: May 2006
Posts: 1,745
Quote:
Originally Posted by Puddin74 View Post
Current Schedule is shooting for:
9 Storey Podium (middle part) - Occupancy Aug 4/23
40 Storey Building B - Occupancy Mar 7/24
29 Storey Building A - Occupancy May 23/24

Then a month later all Deficiencies should be completed
Absolutely insane. 4+ years to build this??
Reply With Quote
     
     
  #174  
Old Posted Oct 6, 2021, 7:21 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,094
Not really surprised by this timeline.


They delayed the full pit excavation while waiting on change application to demolish the old law office house which failed.


High water table changed engineering plans and resulted in only 3 underground levels.



CF their main contractor was stretched thin with tower 3 up in Hyde Park and finishing the Mosaik buildings on Sugarcreek.


Pandemic delays across all sub contractors.


Skilled worker shortage in region. Ie: Concrete formers, Steelworkers, General Laborers etc



And now they have CF starting another new building on Morgan Ave in south London. CF does not have a large work force. Drewlo is even smaller with their construction team.


Classic Project Mgt constraint triangle diagram - https://www.smartsheet.com/project-time-management
Reply With Quote
     
     
  #175  
Old Posted Oct 9, 2021, 8:15 PM
GreatTallNorth2 GreatTallNorth2 is online now
Registered User
 
Join Date: May 2006
Posts: 1,745
Just wondering - did the 40 floor tower get bumped to 135 metres?
Reply With Quote
     
     
  #176  
Old Posted Oct 10, 2021, 12:05 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,094
Have not seen any mention of change from 129m to 135m.



Quote:
Originally Posted by GreatTallNorth2 View Post
Just wondering - did the 40 floor tower get bumped to 135 metres?
Reply With Quote
     
     
  #177  
Old Posted Oct 10, 2021, 12:09 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,094
Forming started for 3rd floor slab above parking entrance off Fullerton. Forming 2nd floor walls and posts along south side now. Still working on steel rebar for 2nd floor slab on the north side of the south tower. Drilling and installing the horizontal cable braces into the pit walls at the next depth. Once complete should see pit excavated to final depth and final row of cable braces drilled and installed.
Reply With Quote
     
     
  #178  
Old Posted Oct 10, 2021, 7:49 PM
GreatTallNorth2 GreatTallNorth2 is online now
Registered User
 
Join Date: May 2006
Posts: 1,745
Sparky212 "Centro in London got the bump to 135m according to the city website"

^This was in the "Tallest Building U/C in Your City"
Reply With Quote
     
     
  #179  
Old Posted Oct 11, 2021, 3:10 AM
sparky212's Avatar
sparky212 sparky212 is offline
Registered User
 
Join Date: Jul 2008
Location: London Ont.
Posts: 506
I found it in the city documents for the building
Reply With Quote
     
     
  #180  
Old Posted Oct 11, 2021, 9:45 PM
TallerIsBetter TallerIsBetter is offline
Registered User
 
Join Date: Oct 2015
Posts: 182
That's cool. Is there a link? Was it just the south tower or is the North tower increased some as well?

Thanks for the info. Taller is Better!!
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 2:57 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.