2nd floor walls along north end nearly all poured now. The 2nd floor elevator and stairwell walls completed. Have started forming around the core for 3rd floor slab. Unlikely to see any of the 3rd floor slab poured until Jan.
Reply With Quote
     
     
  #162  
Old Posted Jan 7, 2021, 5:59 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Now have the 3rd floor slab at north end poured. Some of the 3rd floor wall forms and steel rebar also up as well as elevator shaft forming. Forming and steel rebar for south end of 3rd floor slab and parking ramp underway.
Reply With Quote
     
     
  #163  
Old Posted Jan 8, 2021, 4:35 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Lots of cement trucks as it looks like they are pouring the parking ramp upto the 3rd floor today.
Reply With Quote
     
     
  #164  
Old Posted Jan 19, 2021, 5:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Looks like they have poured the south end 3rd floor slab now. Forming continues for 3rd floor walls on north end.
Reply With Quote
     
     
  #165  
Old Posted Feb 1, 2021, 9:46 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Now have 3rd floor wall forms up for west and south walls. Jack posts started for the 4th floor slab on north end.
Reply With Quote
     
     
  #166  
Old Posted Feb 14, 2021, 3:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Forming and steel rebar for 4th floor slab now well underway on north side.
Reply With Quote
     
     
  #167  
Old Posted Feb 23, 2021, 8:50 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Looks like the 4th floor elevator shaft walls being poured today. Good progress on forming the 4th floor walls on north side. Can't tell if the south side 4th floor slab has been poured or the ramp up to 4th floor level.
Reply With Quote
     
     
  #168  
Old Posted Mar 4, 2021, 7:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
North end 4th floor walls mostly poured now as is the elevator core walls. Have started forming that end for the 5th floor slab.
Reply With Quote
     
     
  #169  
Old Posted Mar 12, 2021, 5:54 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Forming and steel rebar slowly moving towards the south end walls of the 4th floor. Most of the 4th floor walls should be poured by end of March with 5th floor slab forming and steel at north end. Last parking ramp from 4th to 5th floor should also be forming by then too.
Reply With Quote
     
     
  #170  
Old Posted Mar 23, 2021, 8:24 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Looks like some of the 5th floor slab is now poured on north end. Forms for all the 4th floor walls are now up. Can't tell how many have been poured. The 5th floor is the final parking level in the podium base so the final ramp is being formed now. With the completion of the 5th floor walls the 6th floor will be the first residential floor and the pace should quicken.
Reply With Quote
     
     
  #171  
Old Posted Mar 28, 2021, 6:32 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Some of the 5th floor wall forms are now up for the elevator shaft and north end walls.
Reply With Quote
     
     
  #172  
Old Posted Mar 31, 2021, 8:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Looks like they poured some of the 5th floor walls on north end today.
Reply With Quote
     
     
  #173  
Old Posted Apr 11, 2021, 2:21 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Steel rebar and forming of the 5th floor walls continues to move towards the south end of building. Not clear if they have finished pouring the 5th floor slab at south end or last parking ramp as of yet.
Reply With Quote
     
     
  #174  
Old Posted Apr 22, 2021, 5:18 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Have started forming for the 6th floor slab at north end. They don't appear to be finished the south end 5th floor wall pours yet. Will be a milestone with the first 6th floor slab pours given that will mark the transition to residential floors and different forming methods from the parking level podium levels. 26 residential floors averaging around 3 weeks per floor will have this topping out around summer 2022.
Reply With Quote
     
     
  #175  
Old Posted Apr 23, 2021, 2:55 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
LFP article with nice current photo of this building. - https://lfpress.com/news/local-news/...ue-to-covid-19
Reply With Quote
     
     
  #176  
Old Posted Apr 27, 2021, 5:47 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,115
Quote:
Originally Posted by jammer139 View Post
LFP article with nice current photo of this building. - https://lfpress.com/news/local-news/...ue-to-covid-19
Thanks for sharing! Here's the picture

Reply With Quote
     
     
  #177  
Old Posted Apr 27, 2021, 8:56 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 10,952
^^ That sure doesn't look like a residential building with solid concrete and no windows.
Reply With Quote
     
     
  #178  
Old Posted Apr 27, 2021, 9:41 PM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,828
Quote:
Originally Posted by ssiguy View Post
^^ That sure doesn't look like a residential building with solid concrete and no windows.
Parking podium that will likely have fake windows like Rennaissance does.
Reply With Quote
     
     
  #179  
Old Posted Apr 28, 2021, 6:45 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
The 6th floor wall forms are now started on the north end. Still not clear if they have poured the 6th floor slab on the south end, but they must be getting very close.
Reply With Quote
     
     
  #180  
Old Posted Apr 29, 2021, 12:57 PM
inimrepus inimrepus is offline
Registered User
 
Join Date: Jan 2017
Location: Earth
Posts: 150
Quote:
Originally Posted by Djeffery View Post
Parking podium that will likely have fake windows like Rennaissance does.
Those are fake? I always assumed they were real. I used to live at the building at Dundas and Waterloo and I loved having the windows on the second floor of the parking garage.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 3:44 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.