  #1741  
Old Posted Jul 18, 2007, 5:21 AM
vanman's Avatar
vanman vanman is offline
Registered User
 
Join Date: Sep 2006
Location: Vancouver BC
Posts: 6,485
I've been down there myself(hehe) and I can tell you the tunnels are quite large.They have to be at least 10 feet in diameter.
     
     
  #1742  
Old Posted Jul 18, 2007, 5:34 AM
mr.x's Avatar
mr.x mr.x is offline
Registered User
 
Join Date: Dec 2003
Location: Stockholm
Posts: 12,805
"The first tunnel is 2.5 kilometres long and has taken 10 months to complete. Approximately 10,000 pre-fabricated concrete lining segments have been used to make the tunnel walls. The tunnel is 5.3 metres in internal diameter and varies in depth between 10 and 30 metres."

http://www.tc.gc.ca/mediaroom/releases/nat/2007/07-h059e.htm



5.3 metres = 17.39 feet
     
     
  #1743  
Old Posted Jul 18, 2007, 5:34 AM
The_Henry_Man The_Henry_Man is offline
HA
 
Join Date: Mar 2006
Location: St. Cloud, MN/Richmond, BC
Posts: 873
Man, I really hope there can be some sort of an open house for the public to walk around the tunneled/elevated areas before rail/electricity is installed, just like what they did for the tunneled section of the M-line.
     
     
  #1744  
Old Posted Jul 18, 2007, 5:50 AM
vanman's Avatar
vanman vanman is offline
Registered User
 
Join Date: Sep 2006
Location: Vancouver BC
Posts: 6,485
They said on the news today that they won't allow the public into the tunneled section, cause they claim that the construction is a 24 hour operation and it would be too disruptive. They said however that there will be public walk throughs of elevated sections for parents with children (WTF?).
     
     
  #1745  
Old Posted Jul 18, 2007, 6:58 AM
BetterHereThanThere BetterHereThanThere is offline
Registered User
 
Join Date: Jul 2007
Posts: 4
my first post

and i got nothing to say...cool...yeah, let me go with cool...
     
     
  #1746  
Old Posted Jul 18, 2007, 6:21 PM
mr.x's Avatar
mr.x mr.x is offline
Registered User
 
Join Date: Dec 2003
Location: Stockholm
Posts: 12,805


Canada Line: Going deep beneath the surface

Denise Ryan, Vancouver Sun
Published: Tuesday, July 17, 2007

Canada Line construction may have cored and split this city, driven businesses from the Cambie village and made commuting a living hell, but Steve Crombie, vice-president of public affairs for InTransitBC, is anxious to show another side of the story.

Fourteen metres below ground at the bottom of a spiderweb of scaffolding, in the tunnel entry pit, is a small shrine.

A roughly constructed wooden box filled with faded plastic flowers and a statue of a saint sit crookedly on top of an electrical box. Saint Barbara, says Andrea Ciamei, project manager of tunneling, is the patron saint of miners.
"We bring her with us every place we go," says Ciamei in a heavy Italian accent.

Ciamei is in charge of a crew of about 50 so-called "tunnel rats," international workers who travel with him from country to country, job to job.

Their specialty is the dangerous work of building the tunnels many will use but few will ever see. Saint Barbara, says Ciamei, brings good luck, protection and safety.

It's a small sign that something magic, something other than logic, precision and expert engineering may be at work here.

Indeed, what is happening below the frustrating maze of fencing and Jersey barriers that keep our cars snarled up in traffic, is a tidy, clockwork operation.
At the entry pit, temporary track is already in place. Trains of coupled boxcars pull into circular tunnels. They carry precast cement segments; each train carries six sections that make one segment. Twenty-four hours a day, the trains move these segments into the earth.

As the tunnel-boring machine pushes forward at the head of the tunnel, the muck - soil and water - is pushed out behind it onto a screw conveyer that brings it to a belt, and so out of the tunnel.

Approximately 75,000 cubic metres of muck has been removed so far. The precast segments are erected inside a metal shield which is then removed.
Forty-six metres below False Creek, the tunnel is clean and neat, a kind of peaceful place, wending unevenly below the waterway, following the natural curves of the earth.

The side-by-side tunnels have fire doors every 46 metres. In case of emergency, riders will be able to hop from a smoke-filled tunnel to a separately ventilated exit route.

Roger Woodhead, technical director and the engineer behind much of the construction, is obviously proud of how things are coming along. But, he admits with a laugh, "Sometimes I have nightmares about it."

Construction presented some special challenges. Bored tunnels must be deeper below ground; cut-and cover allows tunnels to be dug closer to the surface, he explains.

"People feel safer closer to the surface."

Around the waterways, archeological monitors had to be present to ensure no first nations sites were disturbed (they weren't); layers of "glacial till," dumped here millions of years ago, created a set of variable substances that had to be dealt with in different ways.

Farther up the line, in Richmond, where elevated guideways soar over the Arthur Laing Bridge, the engineering problems were different. Special piles with cement filled "bulbs" at their base were designed to withstand earthquake motion.

"The guideways may move in the event of an earthquake, but they won't fall over," says Woodhead. Another innovation is the cable-stayed bridge over the north arm of the Fraser River - the only bridge of its kind in North America.
"In order to build this bridge," explains Crombie, "we had to keep the towers low due to air traffic, and wide apart because it's an active waterway."

The solution was to design a unique span that uses both post tension and cables. But what Crombie and his team may be most proud of is that the controversial cut-and-cover construction on Cambie is months ahead of schedule.

The Cambie section's original completion date had been April 2008; that has now been pushed up to December.

"In and out in under a year," says Crombie. "Restoration has already begun."
It's good news for commuters and businesses along Cambie, and it's the kind of good news that matters to Crombie and his team who, like the rest of us, are still having a few problems getting to work each day.

[email protected]

© Vancouver Sun 2007
















For the Global BC News Hour story video, click the link below and find "Canada Line tunnel tour".

http://www.canada.com/globaltv/bc/video/index.html
     
     
  #1747  
Old Posted Jul 18, 2007, 7:28 PM
ckkelley's Avatar
ckkelley ckkelley is offline
Bridge Walker!
 
Join Date: Feb 2006
Location: The Forest City
Posts: 1,037
Quote:
Originally Posted by mr.x2 View Post
"The first tunnel is 2.5 kilometres long and has taken 10 months to complete. Approximately 10,000 pre-fabricated concrete lining segments have been used to make the tunnel walls. The tunnel is 5.3 metres in internal diameter and varies in depth between 10 and 30 metres."

http://www.tc.gc.ca/mediaroom/releases/nat/2007/07-h059e.htm



5.3 metres = 17.39 feet

Thanks mr. x2!
__________________
Just chimin' in.
     
     
  #1748  
Old Posted Jul 18, 2007, 8:06 PM
deasine deasine is offline
Vancouver Moderator
 
Join Date: Mar 2007
Posts: 5,747
i just hope it opens earlier... =D any news on the train designs yet? =(
     
     
  #1749  
Old Posted Jul 18, 2007, 8:15 PM
mr.x's Avatar
mr.x mr.x is offline
Registered User
 
Join Date: Dec 2003
Location: Stockholm
Posts: 12,805
Quote:
Originally Posted by deasine View Post
i just hope it opens earlier... =D any news on the train designs yet? =(
it'll probably be revealed December or January.
     
     
  #1750  
Old Posted Jul 18, 2007, 10:41 PM
djh djh is offline
Registered User
 
Join Date: Jul 2003
Location: Vancouver
Posts: 1,976
"The Cambie section's original completion date had been April 2008; that has now been pushed up to December."

Hmm...does that mean the completion date has been moved further back (i.e., finish later than planned) to December 2008, or moved forward (i.e., finish earlier than planned) to December 2007?
     
     
  #1751  
Old Posted Jul 18, 2007, 10:58 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,614
Forward to Dec 2007.
     
     
  #1752  
Old Posted Jul 18, 2007, 11:20 PM
The_Henry_Man The_Henry_Man is offline
HA
 
Join Date: Mar 2006
Location: St. Cloud, MN/Richmond, BC
Posts: 873
Double-post.
     
     
  #1753  
Old Posted Jul 18, 2007, 11:21 PM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 40,038
its been moved to 2007

on the news they said they were ahead and cambie would be open to full traffic in time for christmas shoppers
__________________
belowitall
     
     
  #1754  
Old Posted Jul 18, 2007, 11:35 PM
The_Henry_Man The_Henry_Man is offline
HA
 
Join Date: Mar 2006
Location: St. Cloud, MN/Richmond, BC
Posts: 873
I was just looking at some of the pics of the restored/repaved Cambie St, esp down at 59-64th Ave section, and if it just me, or is it that the road seemed to be slightly narrower than before the C-Line constructed started?
     
     
  #1755  
Old Posted Jul 18, 2007, 11:38 PM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 40,038
it was always pretty narrow - i don't recall it ever having room for street parking
__________________
belowitall
     
     
  #1756  
Old Posted Jul 19, 2007, 12:09 AM
The_Henry_Man The_Henry_Man is offline
HA
 
Join Date: Mar 2006
Location: St. Cloud, MN/Richmond, BC
Posts: 873
^There were room for 3 lanes each way, esp from 41st to King Edward.
     
     
  #1757  
Old Posted Jul 19, 2007, 5:20 AM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 40,038
i am thinking of next to Queen E Park...

anyway

in the article in the 24 hrs newspaper - they say that they will be finished 4 months early July 2009 - so does that mean they will start service 4 months early?
__________________
belowitall
     
     
  #1758  
Old Posted Jul 19, 2007, 5:30 AM
deasine deasine is offline
Vancouver Moderator
 
Join Date: Mar 2007
Posts: 5,747
No.... we can't just assume this stuff. Of course that may happen, but according to InTransit representative or that guy on Global TV, they are still trying to get service in November. If everything goes faster and better, they might put it in service earlier tho
     
     
  #1759  
Old Posted Jul 19, 2007, 6:44 AM
squeezied's Avatar
squeezied squeezied is offline
Registered User
 
Join Date: Jul 2006
Location: Vancouver, BC
Posts: 1,625
well given almost every project is completed after its predicted date, "ahead of shcedule" should then mean "on schedule"
     
     
  #1760  
Old Posted Jul 19, 2007, 6:49 AM
The_Henry_Man The_Henry_Man is offline
HA
 
Join Date: Mar 2006
Location: St. Cloud, MN/Richmond, BC
Posts: 873
Quote:
Originally Posted by deasine View Post
No.... we can't just assume this stuff. Of course that may happen, but according to InTransit representative or that guy on Global TV, they are still trying to get service in November. If everything goes faster and better, they might put it in service earlier tho
I also wish it can be in service in July 09 if construction/testing is finished by July 09, but we still have to consider any difficulties in changes of coordination for bus services that's connected to the C-Line (ex- should 91B line or 481 (Steveston-UBC) service start earlier too to synchronize with the earlier C-Line opening date?).
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 2:08 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.