Hamilton is breaking the RFQ into two processes to get construction started as soon as possible. Metrolinx wants "Swept Path" as phase 1.
Metrolinx considering Alliance contract to de-risk Hamilton LRT project
https://canada.constructconnect.com/dcn/...s-for-alliance-contract-for-hamilton-lrt
Metrolinx and the City of Hamilton have spent the last half year picking up the pieces of the Hamilton LRT project, resurrected last year by the Ontario government, with most of the project slated to be the same as originally planned but with a major change in the procurement model.
As explained by Metrolinx’s technical project lead Kris Jacobson during a recent webinar, the project owners have decided the utilities-relocation phase of the $3.4-billion project is so fraught with risks that procurement will have to be split into two packages, with the utilities phase procured under the Alliance model.
Alliance, characterized by extensive collaboration from all stakeholders, offers a “no-blame, no-claim environment, where it is our role to just basically get this work done,” said Jacobson.
He said Alliance has elements of progressive design, integrated project design and integrated project delivery.
“From a packaging perspective, we’ve identified that the risk associated with moving those utilities around is just too significant to bundle it as part of the overall scope of the project like we were in the past and using a more traditional P3,” he told members of the Hamilton-Halton Construction Association assembled virtually for day one of the association’s annual Construction Forecast.
“We don’t know what exists underneath the corridor with all of these utilities
The Hamilton LRT will run 14 kilometres from McMaster University in the west to Eastgate Square to the east, with 17 stops. A significant portion of the corridor will be only 20 metres wide, with the double-track guideway located in the centre occupying 10 metres, leaving five metres on either side for two single lanes of traffic.
blah blah blah....
The Swept Path timetable calls for an RFQ in the spring of 2022, an RFP going out in August 2022, design and cost development from March 2023 into 2024, and construction starting in early 2024.
The second contract, for the Stops, Rail and Systems phases along with operations and maintenance, will be procured through a traditional P3 DBFOM model. The RFQ would go out in early 2023, the RFP period would start in May 2023, design work would ensue through 2024 and construction is targeted for a late 2024 start.
“Since we de-risked the project by moving all the utilities out of the way, by creating a sanitized corridor down the middle of the road, it should be relatively straightforward for a second contractor to come in and actually build the rail,” said Jacobson.
Building demolitions have started and other enabling works will be launched this year.
Other civil projects to be undertaken include construction of an operations, maintenance and storage facility; replacement of the existing Longwood Road Bridge; a new Highway 403 LRT flyover bridge; a new CP overpass bridge; and reestablishment of 62 traffic signals and thousands of streetlights