Quote:
|
Originally Posted by FourOneFive
i wonder when they'll begin excavation for the underground parking garage and 11 story mid-rise. it seems they have to use the entire site for equipment/ construction material storage.
|
Webcor posted this article on 8/1/06 it says that the mid-rise will start in October.
Webcor Drives 950 Piles for 301 Mission Project in San Francisco
08/01/2006 Daily Pacific Builder
SAN FRANCISCO - Almost 950 piles for the Tower at 301 Mission St. here have been completed, and exca¬vation, shoring, and
foundation work for the mid-rise and amenities portion of the project is scheduled for an October start, according to the project's general contractor, Webcor Builders.
301 Mission is a condomin¬ium/mixed-use project that will include a 645-ft., 60-story tower plus a 12-story amenity building. The two buildings will be connected by a tbree-level podium. The project also includes an atrium and five levels of below grade parking. `
Total area is approximately 1,150,000 sq. ft.
Webcor added in its recent update that the elevator matt/pile-cap was tied with rebar and the concrete was placed at the end of May. The bottom climbing crane was erected and certified within a week after this pour took place.
The project worked through some last minute technical rebar challenges and placed the 6,200 cu. yd., 10-ft. matt/pile-cap for the Tower in mid-June as scheduled.
Placement of the vertical rebar for the main core of the Tower began soon after the matt/pile-cap pour for B 1 level. After the completion of the rebar, the first stage of three for the core climbing system was erected and concrete placed in early July. Next core pour (the second stage of the climber system) was scheduled at press time. After the third pour, the core climbing system should be completed and will pace three floors ahead of the deck pours.
Shotcrete for the exterior walls on the B 1 level started work the first week of July and was scheduled to be completed at press time. Work on the structural columns and walls started the second week of July and will also be completed at press time.
Forming for the first level deck was scheduled to begin this week once all the vertical work has completed.
Site excavation began on the project last fall. According Handel Architects, the design creates a significant architectural landmark for the transformation and redevelopment of the Transbay Terminal district in San Francisco. 301 Mission St. is being developed by Millennium Partners, which completed the Four Seasons Hotel & Tower on Market St. with Handel Architects in 2001.
The tower will be the fourth tallest building on the city's skyline. The exterior design creates the impression of a translucent crystal, delicately detailed and taut in character, incorporating a variety of glass and metal fins to craft a sense of lightness and transparency. The tower's slender proportions, combined with clean lines and sleek profile, visually reinforce the elegance of the tower's crystalline character and enhance the skyline as an architectural landmark. The exterior profile of the tower has been sculpted with chamfered corners and faceted planes creating a perception that the tower's silhouette shifts as the light changes throughout the day.
The project is scheduled for completion in April 2009.