Quote:
Originally Posted by Davis137 View Post
It's awesome how fast this has started rising now...I think it's at it's 10th floor, with only 5 left to go until topout. Funny thing is, it's already almost as tall as the buildings beside it, which have a higher floorcount...
The other buildings are residential and this is institutional, which means higher ceilings and thicker floors with more HVAC, wiring, sound/fire proofing etc. That's just the way it goes, really.
Reply With Quote
     
     
  #142  
Old Posted Jul 14, 2011, 1:49 AM
Davis137's Avatar
Davis137 Davis137 is offline
Registered User
 
Join Date: Aug 2008
Posts: 2,363
Fair enough...I really like the streetwall presence this adds to Nicholas/Lees and the transitway...it looks like it's going to be really nice when viewed from Col By....
Reply With Quote
     
     
  #143  
Old Posted Jul 14, 2011, 3:02 AM
bobert_d bobert_d is offline
Registered User
 
Join Date: Dec 2010
Posts: 18
SITE (the glass building that is the first uOttawa building you see coming down Nicholas) still always impresses me whenever I go down the transitway, this should hopefully make the rest of the ride through campus that much better.
Reply With Quote
     
     
  #144  
Old Posted Jul 14, 2011, 11:56 AM
LeadingEdgeBoomer LeadingEdgeBoomer is offline
Registered User
 
Join Date: Mar 2010
Posts: 1,336
bobert_d wrote

Quote:
SITE (the glass building that is the first uOttawa building you see coming down Nicholas) still always impresses me whenever I go down the transitway, this should hopefully make the rest of the ride through campus that much better.
I read some time ago that the SITE building has a dupicate. It is at Lakehead University and used for a different academic pupose than the Ottawa one.

At the time the province was funding a new building for each. Both unis liked this design, so the province saved itself a bit of money by using the design twice.
Reply With Quote
     
     
  #145  
Old Posted Jul 14, 2011, 12:24 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
Quote:
Originally Posted by LeadingEdgeBoomer View Post
bobert_d wrote



I read some time ago that the SITE building has a dupicate. It is at Lakehead University and used for a different academic pupose than the Ottawa one.

At the time the province was funding a new building for each. Both unis liked this design, so the province saved itself a bit of money by using the design twice.
The one at Lakehead looks very similar, they're definitely twins, but maybe not *identical* twins. ;-)
Reply With Quote
     
     
  #146  
Old Posted Aug 14, 2011, 6:52 AM
ServiceGuy ServiceGuy is offline
Registered User
 
Join Date: Dec 2009
Posts: 335
A little different view than the Nicholas side...


Reply With Quote
     
     
  #147  
Old Posted Sep 19, 2011, 2:12 AM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 519
Taken today (Sep 18) from the somerset footbridge.


Reply With Quote
     
     
  #148  
Old Posted Oct 11, 2011, 2:20 AM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,254
Reply With Quote
     
     
  #149  
Old Posted Oct 11, 2011, 2:29 AM
S-Man S-Man is offline
Registered User
 
Join Date: Mar 2011
Posts: 1,639
If it's an Ottawa U building, my guess is any slant will be to the left
Reply With Quote
     
     
  #150  
Old Posted Oct 11, 2011, 4:50 PM
teej1984 teej1984 is offline
Registered User
 
Join Date: Aug 2011
Location: Sandy Hill, Ottawa
Posts: 310
Quote:
Originally Posted by waterloowarrior View Post
This is kinda old news... Le Droit (Ottawa' French daily) reported on this at the start of summer!
Reply With Quote
     
     
  #151  
Old Posted Oct 11, 2011, 5:01 PM
Ottawan Ottawan is offline
Citizen-at-large
 
Join Date: Aug 2009
Location: Expat (in Toronto)
Posts: 738
Quote:
Originally Posted by teej1984 View Post
This is kinda old news... Le Droit (Ottawa' French daily) reported on this at the start of summer!
Well it would be unreasonable to expect University Administration to take less than a couple months to get the English translation of their press release out.
Reply With Quote
     
     
  #152  
Old Posted Oct 11, 2011, 8:02 PM
LeadingEdgeBoomer LeadingEdgeBoomer is offline
Registered User
 
Join Date: Mar 2010
Posts: 1,336
Ottawan wrote

Quote:
Well it would be unreasonable to expect University Administration to take less than a couple months to get the English translation of their press release out.

Balderdash--all this was reported in the Citizen in sept 2010, There is nothing new at all in this Oct 2011 CitiZen ariticle. They are just rehashing what was said in 2010. Both articles basically say the building will not be finished by the original 2011 date.

Quote:
U of 0 doing ‘best’ to finish new building

By Nick Taylor-Vaisey, The Ottawa Citizen September 28, 2010 6:44 AM


OTTAWA — Months of delays on the University of Ottawa’s newest building could mean its federal funding will be cut off next spring, even before the structure is more than a few floors off the ground.

The $112-million Vanier Tower, the largest construction project in the school’s history, was delayed almost immediately after work began on the building’s foundations.

The project received

$30 million from the federal government’s $2-billion Knowledge Infrastructure Program, part of its larger stimulus program to juice the economy out of recession.

The taps run dry on that funding at the end of March 2011.

Claudio Brun del Re, the school’s director of physical resources, said the university broke ground on the new arts and social-sciences building the day after the funding announcement. But almost immediately, he said, workers ran into problems with its foundations.

The northern portion of the site near the Rideau Canal sits on limestone, but the southern portion hits shale a few feet beneath the ground. Engineers ran into problems with the stability of that layer of shale, which didn’t provide the load-bearing capacity required for the foundations.

The problem arose last November, and it delayed the project for five months as engineers searched for solutions. Work resumed in April, and the project has been in full production since.

“We’re doing everything we can to accelerate our work,” said Brun del Re. “We’re pre-ordering as many materials and long-delivery items as we can. We’re making sure everything will be available on site at the earliest possible time.”

The delays mean the school won’t finish the project by September 2011, as originally planned. While the first few floors of the 15-storey tower will be ready for occupancy next fall, many will still require substantial work.

The delays might also mean next spring’s funding deadline will pass before the university can spend all the federal money dedicated to the project. The March deadline was imposed in an effort to get the federal money into the economy as quickly as possible; the funding is supposed to flow as projects progress, but the government has repeatedly said that if work is still going on after the deadline, the money will stop.

“We’re optimistic that the financial requirements can be met by the deadline,” Brun del Re said, but in an e-mail, he added that forecasting is difficult, because even spending the funding “is not a singular coordinated initiative, but rather a myriad of smaller individual initiatives.”

Although he was reluctant to criticize the government and “bite the hand that feeds” the university, Brun del Re said the stimulus deadline was ill-conceived.

“(The government’s) expectations that there are going to be no risks at the best of times is probably unrealistic,” he said. “You shouldn’t be faulted for doing the best you can.”

Darryl Boyce, Carleton University’s assistant vice-president of facilities management and planning, said that the Carleton projects met similar delays as the U of O project.

Boyce said that the federal government’s strict deadline “made things more stressful.” He explained that Carleton had problems with both buildings in its stimulus-funded “Waterfront Project.”

“They were both a struggle to get out of the ground,” he said. “I think if you talk to other KIP projects, there are probably a number of projects where getting out of the ground posed the most challenge.”

Brun del Re also said that some projects on other campuses are also facing delays, but he couldn’t cite examples.
© Copyright (c) The Ottawa Citizen


Read more: http://www.ottawacitizen.com/
Reply With Quote
     
     
  #153  
Old Posted Oct 11, 2011, 8:12 PM
Ottawan Ottawan is offline
Citizen-at-large
 
Join Date: Aug 2009
Location: Expat (in Toronto)
Posts: 738
Quote:
Originally Posted by LeadingEdgeBoomer View Post
Ottawan wrote




Balderdash--all this was reported in the Citizen in sept 2010, There is nothing new at all in this Oct 2011 CitiZen ariticle. They are just rehashing what was said in 2010. Both articles basically say the building will not be finished by the original 2011 date.
I actually never doubted any of this. My post was just an attempt at a little humour. As a Carleton grad, taking jabs at Ottawa U is a patriotic duty.
Reply With Quote
     
     
  #154  
Old Posted Oct 13, 2011, 4:28 PM
alphachap alphachap is offline
Registered User
 
Join Date: Mar 2011
Posts: 19
2011-oct-09


Reply With Quote
     
     
  #155  
Old Posted Oct 13, 2011, 9:10 PM
S-Man S-Man is offline
Registered User
 
Join Date: Mar 2011
Posts: 1,639
I guess the shale conditions were the reasons the LRT tunnel was shortened in that area.
Reply With Quote
     
     
  #156  
Old Posted Nov 1, 2011, 10:24 AM
alphachap alphachap is offline
Registered User
 
Join Date: Mar 2011
Posts: 19
taken 2011-oct-31





Reply With Quote
     
     
  #157  
Old Posted Nov 2, 2011, 12:16 AM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 519
Nice photos! Good to see it coming along.
Reply With Quote
     
     
  #158  
Old Posted Nov 3, 2011, 11:51 AM
alphachap alphachap is offline
Registered User
 
Join Date: Mar 2011
Posts: 19
Open Air Plaza ?

Quote:
Originally Posted by waterloowarrior View Post
[IMG]
I don't like an open air plaza when it could so easily be enclosed.
It might be a nice place on a perfect summer day,
but for most of the school year it will be unpleasant, cold, windy, rainy, snowy.
All this while it could have been a cosy common public indoor area with benches, tables, etc...
A missed opportunity.
Reply With Quote
     
     
  #159  
Old Posted Nov 3, 2011, 2:01 PM
c_speed3108 c_speed3108 is offline
Registered User
 
Join Date: May 2007
Posts: 1,857
Quote:
Originally Posted by alphachap View Post
I don't like an open air plaza when it could so easily be enclosed.
It might be a nice place on a perfect summer day,
but for most of the school year it will be unpleasant, cold, windy, rainy, snowy.
All this while it could have been a cosy common public indoor area with benches, tables, etc...
A missed opportunity.

I suspect that area above will have just that function meaning both types of spaces will be available.
Reply With Quote
     
     
  #160  
Old Posted Nov 3, 2011, 2:26 PM
adam-machiavelli adam-machiavelli is offline
Registered User
 
Join Date: Jun 2005
Posts: 1,246
Indoor "open air plazas" are a waste of energy and very inefficient use of space. They should be avoided at all costs.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Downtown & Urban Ottawa
Forum Jump



Forum Jump


All times are GMT. The time now is 2:02 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.