First of the 15th floor wall forms have now started going up on the north wing. Should have the west wing 14th floor walls wrapped up by end of next week and 15th floor slab pour. There is a step back on the south end of the west wing for the 15th and 16th floor which makes the floor plate of those floors slightly smaller.
For some reason the masonry contractor stopped work on the exterior brick install on the Talbot St facing podium with only a few more feet at the top to go?