Originally Posted by CF1Fan
They got bridge replacements lines up for the next 3-4 years. So optimistically if they start widening in 2025, they might complete in 2035 with the entire 75km. That's still optimistic but not out of the realm of possibilities.
|
The highway is already being widened south of Highway 9 with construction underway, there is only about 45km remaining. The highway has already been widened south of King Road.
And as others have said, basically all the major structures are done now or will be done by 2027 or so. Structures are the largest time sucks, it's mostly grading left over, and even then a lot of the bridge replacement projects are doing the grading already in their project limits.
2030 may push to 2031 or 2032, but I would be surprised if it's later than that, subject to it getting funding when it needs it, which it should given the current government.