Quote:
Originally Posted by snfenoc
Please note I am not being pessimistic. I'm just being impatient. I'm pretty sure "they" said it would take only 3 months to finish the pile driving.
|
Saca said it would take six months... and back in July and I think I also mentioned
that I talked to some of the pile driver guys working at the site and
they said it would continue into December.
Back when Saca said it would take six months Construction Guy said that
was crazy... three months tops is what CG said
The Towers will be built with cast-in-place concrete which means the
concrete parts have embedded steel cables and after the cement dries, the
cables are pulled like a rubber band and tightened. The same method was
used for the Plaza Lofts on J and 9th.
I think April is a good bet Brandon... a lot of digging has to be done around
the piles before concrete is poured for the foundation, and bad weather
will slow things down.
Before any rebar goes in for the foundation, a tremendous amount of digging
will need to happen around the piles. This picture below was taken of the
Marriott foundation at L and 15th Streets about a year ago. Expect to see a lot
of this in places where piles are grouped together. At the Marriott they only
dug down about 5 feet or so for a 15 story building... so for the Towers as
has been reported, 15 feet of foundation sounds about right.
Hey snfenoc, since when did you start drinking beer?