View from the top of the events centre.

source: Mayor Dawn Arnold's Facebook page.
I believe this photo may have been taken from one of the bar patios (accessible off the suites level, and one level up from the club lounge)
November Construction Update:
PROJECT BY NUMBERS
- All ten bowl main roof trusses are installed.
- The main concourse level will hous
e ten concession areas.
- Fourteen tunnel entrances allow access from the concourse and event level to the seating area.
- Over 2,600 tonnes of steel have been installed to date.
- During peak event operations, the ventilation system will provide 3.2 million liters of treated air per minute to the bowl, offering premium air quality to the spectators.
- The bowl main ventilation ductwork is 1.8m (approx. 6 feet) in diameter.
- To date, over 71,000 man hours have been worked on the site.
- There are approximately 110 people working onsite daily.
CONSTRUCTION OF THE FACILITY
WHERE ARE WE?
– Approximately 20% of the bowl roofing has been installed.
– Structural steel work will be completed in November.
– The upper bowl liner panel is being installed on the north side of the building facing Main St. This will be covered with insulation and siding panels in the coming months.
– Aluminum glass framing is being installed on the plaza side and on the main entrance side.
– The installation of the precast bleachers (or seating steps) is complete.
– With the installation of the bleachers and roof trusses now completed, the big red crane will be leaving the site in November.
– Interior partitions are being framed for washrooms and concession areas on the west (Sobeys) side of the concourse level.
– All concrete floor slabs on the concourse, suite and press levels are completed except for the south (VIA Rail) side of the building where the crane exited the building.
– The Downtown Centre construction project is currently on schedule.
WHAT IS PLANNED
FOR THE NEXT 4 WEEKS?
- Aluminum glass framing and glass installation will continue on the plaza and Main St. entrance side of the facility.
- Structural steel will be completed in November.
- Roofing will continue to be installed on the bowl and concourse levels.
- Metal siding liner panel will continue to be installed on the bowl perimeter.
- Masonry façade will be completed on the east (plaza) side.
- Water and sewer work will continue on the Highfield Street extension on the south (Via Rail) side of the building.
- Covering and temporary winter heat will be installed on the west side of the building to keep crews working through the winter.
- Masonry work will begin on the interior of the event (bottom) level.
- Electrical, plumbing, ventilation and sprinkler contractors will continue to install services throughout the facility.
INTERESTING FACTS
1) The concourse level is open from the top of the main stairwell and down the east (plaza) side of the building allowing for unobstructed views of the event floor.
2) The suite level has direct access to the club lounge and concessions.
3)
Two rooftop patios will be accessible via the suite level. These patios will offer spectacular views of the plaza and the east view of the downtown area.
4) The centre score clock is planned to
recess completely into the roof trusses allowing unobstructed ceiling height of 60’.
Personal note - the new events centre will be so far beyond the current coliseum, it won't even be funny - just spectacular.