Yep they also have an email subscription service to document progress!

-----

Day 71 July 27

Sidewalks are finally being ripped up now





__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #102  
Old Posted Jul 30, 2018, 4:36 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 72 July 30

Today has been surprisingly quiet, at least noise-wise. Looks like leveling work is underway



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #103  
Old Posted Jul 31, 2018, 4:33 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 73 July 31

The peak of summer - half way point of construction season?



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #104  
Old Posted Jul 31, 2018, 5:17 PM
Dupcheck's Avatar
Dupcheck Dupcheck is offline
Registered User
 
Join Date: Jul 2016
Location: London
Posts: 255
Seems like they dig and cover, then dig again then cover it again. The progress looks almost the same every day. I wonder if a lot of the tasks are planned properly?
__________________
Kick Bureaucracy in the Nardz
Reply With Quote
     
     
  #105  
Old Posted Jul 31, 2018, 9:08 PM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,262
Quote:
Originally Posted by Dupcheck View Post
Seems like they dig and cover, then dig again then cover it again. The progress looks almost the same every day. I wonder if a lot of the tasks are planned properly?
From reading the weekly update blog, it sounds like a lot of stuff is repetitive because of the need to keep local businesses hooked up, and there has been temporary utilities installed, and then the new permanent ones. So they have to keep going back in to unhook and hook up. I know the hole in the middle of Richmond and Dundas doesn't seem to look too different each day I drive by it lol
Reply With Quote
     
     
  #106  
Old Posted Aug 1, 2018, 4:52 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 74 Aug 1

Yes I totally agree. Dig a hole, cover it up. 3 days later, dig a hole in the SAME SPOT



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #107  
Old Posted Aug 2, 2018, 4:46 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 75 Aug 2

New pipes to contain new cables



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #108  
Old Posted Aug 3, 2018, 5:26 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 76 Aug 3

Manhole covers look pretty in pink



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #109  
Old Posted Aug 7, 2018, 4:30 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 77 Aug 7

Puddles galore today



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #110  
Old Posted Aug 8, 2018, 4:52 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 78 Aug 8

Despite it being very wet, work continues today - kinda noisy out.



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #111  
Old Posted Aug 9, 2018, 4:43 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 79 Aug 9

The site is being cleaned up a fair bit - maybe they are going to start the next phase soon?



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #112  
Old Posted Aug 10, 2018, 5:07 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 80 Aug 10

Flower beds are being cast.



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #113  
Old Posted Aug 13, 2018, 5:16 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 81 Aug 13

Concrete pouring for more flower gardens





__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #114  
Old Posted Aug 14, 2018, 4:58 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 82 Aug 14

Flower pots have been cast.



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #115  
Old Posted Aug 15, 2018, 4:43 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 83 Aug 15

Lots of digging / commotion going on at Talbot Street today



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #116  
Old Posted Aug 16, 2018, 11:38 AM
Stevo26 Stevo26 is offline
Registered User
 
Join Date: Apr 2009
Posts: 243
Quote:
Originally Posted by haljackey View Post
Day 79 Aug 9

The site is being cleaned up a fair bit - maybe they are going to start the next phase soon?



Yesterday I was coming to work after I attended an appointment in the north end of town, so had to drive down Ridout to get to the parking lot where I park my car. While I drove past the intersection of Dundas and Ridout, I noticed that the construction crews were starting to build forms to make curbs and gutters.

So it looks like we'll soon see the beginnings of the flex street being installed, starting with the extreme west end of Dundas Street.
Reply With Quote
     
     
  #117  
Old Posted Aug 16, 2018, 11:41 AM
Stevo26 Stevo26 is offline
Registered User
 
Join Date: Apr 2009
Posts: 243
Quote:
Originally Posted by Djeffery View Post
From reading the weekly update blog, it sounds like a lot of stuff is repetitive because of the need to keep local businesses hooked up, and there has been temporary utilities installed, and then the new permanent ones. So they have to keep going back in to unhook and hook up. I know the hole in the middle of Richmond and Dundas doesn't seem to look too different each day I drive by it lol
My office is located in the area where the construction is ongoing and I have been wondering why the crews have been digging holes, putting pipes in the holes, then covering up the holes, only to rip them open again.

Now I know. Thanks for posting this.
Reply With Quote
     
     
  #118  
Old Posted Aug 16, 2018, 4:55 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 84 Aug 16

Yes concrete pouring is in progress. More flower beds are done.



__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #119  
Old Posted Aug 17, 2018, 4:41 PM
haljackey's Avatar
haljackey haljackey is online now
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,467
Day 85 Aug 17

I think drainage work is being done today









-----

Update:

Curb / gutter concrete work started this afternoon

__________________
My Twitter

My Simcity Stuff

Last edited by haljackey; Aug 17, 2018 at 7:05 PM.
Reply With Quote
     
     
  #120  
Old Posted Aug 17, 2018, 8:54 PM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,262
I believe what they are pouring in those pics in front of your office are the concrete borders for the brick road and sidewalks.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 12:23 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.