Forming for the posts supporting the NE corner entrance is now up. This has some custom forming for the ramp and stairs for the entrance into the building.
Have now poured some of the 2nd floor walls on the SE wing. The NE corner entrance now has the posts poured. Should see forming next week for the 2nd floor slab over the NE corner. Appear to be forming the north end and SW wing 2nd floor slab now.
Just starting now to form the NE corner lobby entrance 2nd floor slab above where the doors and steps and ramp will be. Working on the north side driveway entrance to the underground parking entrance and garbage area. Imagine they want to get this built as soon as possible so workers can start using the underground parking.
Have poured a couple of 2nd floor walls along the north and west sides of building. Still haven't formed the 2nd floor slab in the NE corner above the entrance.
Poured a couple of 2nd floor walls on the west wing of the building this week. May have finally poured the 2nd floor slab in the NE corner above the entrance way as well. Forming for 3rd floor slab is started along the north section but progress is piece meal and typically slow with Drewlo.
Forming and pouring of 3rd floor walls and posts on the SW wing now underway. Have started forming for 4th floor slab in the SE wing and center section.
They have got a couple of the 4th floor walls on the east wing poured now. Still forming the 3rd floor walls on the south end of the west wing however. Undoubtedly there will be many students looking at renting units in this building once Drewlo eventually finishes it but I would expect many non students will also consider living there.
Have now poured the 4th floor slab in the NE corner and have also poured most of the 4th floor walls on the SE wing. Have started setting up 4th floor wall forms along the north side.
Have now got most of the 4th floor walls and posts poured. Appears they may have poured the 5th floor slab in the SE wing as they have started setting up forming for 5th floor walls there.
Forming is now started for the 7th floor walls on the SE wing. Wrapping up the 6th floor walls now on the SW and north sides. Should be pouring the 7th floor slab on the SW and North sides in the next weeks.