So I went looking for PEI info and can't find it anywhere, same story for NB, and for NL. Even the traffic advisories and construction page for PEI has no info that I could find. Here's some NB advisories and construction projects though.
New Brunswick Traffic Advisories Page
New Brunswick Rte 1 Gateway Project
NB Proposed Projects
Including:
Rte 11:
Acadian Peninsula - 46-kilometre bypass from Pokemouche to Janeville
* Public Information Session in Paquetville November 10, 2009
* Construction to begin 2013 or earlier
* Estimated project costs $200-million
South East New Brunswick
Twinning of 35 kilometres between Route 15 at Shediac and the Girouardville Road in Bouctouche
* Two public information sessions have been held
* Phase 1 of project to expand Route 11 between Moncton to Miramichi to four lanes
* Estimated investment of $942 million
Kent County and Miramichi
Twinning of 21-kilometres between Bouctouche and the Richibouctou River
* Public Information Session held October 27, 2009
* Phase 2 of project to twin Route 11 between Moncton and Miramichi
* Phase 3 involves the twinning of 65 kilometres of highway and several bridges and interchanges from the Richibouctou River to Miramichi
* Preconstruction work is being completed
Rte 7:
Welsford
10.7-kilometre bypass between Welsford and Nerepis
* Construction has started. Seven contracts awarded so far.
* Completion date 2012
* Estimated project costs $65 million. Funded by the Goverments of New Brunswick and Canada
Completion of the Highland Road Interchange in Grand Bay-Westfield – paving of 4.1 kilometres
Rte 1:
Saint John
One Mile House Interchange
* Phase 2 of construction has started.
* Grading, paving and viaduct substructure contracts awarded.
* Project includes a 600-metre structure and associated ramps and roadways that will connect Route 1 to Bayside Drive, and cross the CN rail yard, Marsh Creek and Rothesay Avenue
* Completion date 2012.
* Estimated project costs $65 million. Funded by the Governments of New Brunswick and Canada
Rte 2:
Moncton
Major $6.3 million realignment of the westbound lanes of the Route 2 / Route 134 interchange in Moncton
* Project includes two new bridges at Cooks Brook and CNR overpass on the former Shediac Road)
* $2.95 million to pave 8.4 kilometres of the westbound lanes of Route 2 between Cooks Brook and Mapleton Road
Rte 8:
Fredericton
36 kilometre Marysville – Nashwaak Bypass
* Construction started in 2007 and continues with several contracts. $34.9 budgeted for 2009-2010
* Target completion date 2014
* Estimated project costs $124 million. Funded by the Governments of New Brunswick and Canada
Fredericton
Princess Margaret Bridge Rehabilitation project
* Bridge was built in 1957.
* Construction for Phase 1 continues (Marid Industries Ltd)
* Completion date 2011
(Much more information on the page itself)
Princess Margaret Bridge closure information
Madawaska Maliseet First Nation Rte 2 Interchange
Rte 2, Quebec Border to Saint-Jacques